This federal contract opportunity solicitation seeks replacement of chillers and cooling towers at three locations within Independence National Historical Park in Philadelphia. The solicitation number is 140P2022R0019 and is issued by the National Park Service, an agency of the Department of the Interior. The project involves replacing critical components of chillers one and two, replacing a failing chiller and cooling tower, and replacing two failing cooling towers, all at the central chilled water plant. No response or award dates are included, and the document provides no further pricing or contractual terms.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REFER TO DIVISION 3 SPECIFICATION SECTION - MISCELLANEOUS CAST-IN-PLACE
CONCRETE - FOR REQUIREMENTS IN ADDITION TO THOSE LISTED BELOW.
A QUALITY CONTROL PROGRAM OF FIELD TESTING AND INSPECTION SHALL BE
PERFORMED ON ALL STRUCTURAL CONCRETE WORK IN ACCORDANCE WITH THE
SPECIFICATIONS. SCHEDULE WORK AND PROVIDE ACCESS TO ALLOW THE
TESTING REQUIREMENTS TO BE COMPLETED.
SUBMIT ENGINEERED CONCRETE MIX DESIGNS, INCLUDING REQUIRED BACKUP
DATA, FOR EACH TYPE OF CONCRETE PROPOSED FOR USE FOR REVIEW. ALLOW
ADEQUATE TIME FOR REVIEW PRIOR TO PERFORMING CONCRETE WORK.
DETAIL, FABRICATE, LABEL, SUPPORT AND PLACE ALL CONCRETE REINFORCEMENT
IN ACCORDANCE WITH THE ACI 315 "MANUAL OF STANDARD PRACTICE FOR
DETAILING REINFORCED CONCRETE STRUCTURES" AND ACI 318 "BUILDING CODE
REQUIREMENTS FOR REINFORCED CONCRETE," APPLICABLE EDITIONS.
SUBMIT DETAILED SHOP DRAWINGS INDICATING REINFORCEMENT SIZE, SPACING
AND PLACEMENT FOR REVIEW PRIOR TO FABRICATION. INCLUDE DETAILS AND
LOCATIONS OF ALL CURBS, CONSTRUCTION JOINTS, SLAB DEPRESSIONS, SLEEVES,
OPENINGS, ETC.
CLEAN AND MOISTEN ALL CONSTRUCTION JOINTS IMMEDIATELY PRIOR TO PLACING
FRESH CONCRETE.
DO NOT USE CALCIUM CHLORIDE IN ANY CONCRETE.
HORIZONTAL JOINTS IN CONCRETE POURS ARE NOT PERMITTED.
ALLOW THE TESTING AGENCY TO REVIEW THE REINFORCING PLACEMENT PRIOR
TO PLACING ANY CONCRETE. PROVIDE ADEQUATE ADVANCE NOTICE.
REFER TO ACI 305 FOR REQUIREMENTS FOR PLACING CONCRETE IN HOT WEATHER
AND TO ACI 306 FOR REQUIREMENTS FOR PLACING CONCRETE IN COLD WEATHER.
PROVIDE ONLY CONCRETE AND REINFORCING MATERIALS OF THE TYPES AND
GRADES LISTED IN THE TABLE BELOW:
CONCRETE NOTES
C1
C2
C3
C4
C5
C6
C7
C8
C9
C10
C11
CONCRETE
ALL CONCRETE
REINFORCING
TYPICAL BARS
F'c UNIT WEIGHT
3000 PSI 150 PCF
GRADE
ASTM A615, GRADE 60
STRUCTURAL STEEL FRAMING NOTES
S1
S2
S3
S4
S5
S6
S7
S8
S9
S10
S11.
S12
S13
REFER TO DIVISION 5 SPECIFICATION SECTION - STRUCTURAL STEEL FRAMING - FOR
REQUIREMENTS IN ADDITION TO THOSE LISTED BELOW.
A QUALITY CONTROL PROGRAM OF SHOP AND FIELD TESTING AND INSPECTION
SHALL BE PERFORMED ON STRUCTURAL STEEL FABRICATION, ERECTION, AND
CONNECTIONS IN ACCORDANCE WITH THE SPECIFICATIONS. SCHEDULE WORK AND
PROVIDE ACCESS TO ALLOW THE TESTING REQUIREMENTS TO BE COMPLETED.
DETAIL, FABRICATE AND ERECT STRUCTURAL STEEL IN CONFORMANCE WITH THE
AISC SPECIFICATIONS AND CODES, APPLICABLE EDITIONS.
PERFORM ALL WELDING USING CERTIFIED WELDERS AND IN ACCORDANCE WITH THE
AWS "STRUCTURAL WELDING CODE - STEEL," APPLICABLE EDITION. COMPLY WITH
AISC SPECIFICATION SECTION J2 FOR MINIMUM FILLET WELD SIZE UNLESS
SPECIFICALLY NOTED ON THE DRAWINGS.
SUBMIT ENGINEERED AND CHECKED SHOP DRAWINGS FOR REVIEW. SHOW SHOP
FABRICATION DETAILS, FIELD ASSEMBLY DETAILS, AND ERECTION DIAGRAMS FOR
ALL STRUCTURAL STEEL. SCHEDULE SUBMISSIONS TO ALLOW ADEQUATE TIME FOR
REVIEW PRIOR TO FABRICATION.
PROVIDE A MINIMUM OF (2) BOLTS AT EACH FAYING SURFACE.
PROVIDE CONNECTION DETAILS REQUIRED BY THE SPECIFIC CONSTRUCTION
SEQUENCES.
FABRICATE ALL BEAMS WITH THE NATURAL CAMBER UP. CANTILEVER BEAMS SHALL
BE FABRICATED SO THAT THE NATURAL CAMBER RAISES THE CANTILEVERED END.
AFTER FABRICATION, CLEAN STEEL OF ALL RUST, LOOSE MILL SCALE, DIRT, OIL,
GREASE OR OTHER FOREIGN MATERIALS. REPAIR DAMAGED SURFACES USING
GALVANIZING REPAIR METHODS OUTLINED IN THE DIV 05 SPECIFICATIONS.
DO NOT FIELD CUT ANY STRUCTURAL STEEL WITHOUT THE PRIOR REVIEW AND
ACCEPTANCE. CLEARLY SHOW ON THE SHOP DRAWINGS SUBMITTED FOR REVIEW
ANY MEMBER OPENINGS REQUIRED BY OTHER TRADES.
ERECTION PROCEDURES, SEQUENCES AND COORDINATION OF WORK WITH OTHER
TRADES IS THE RESPONSIBILITY OF THE CONTRACTOR. PROVIDE ANY ADDITIONAL
STEEL REQUIRED FOR ERECTION PURPOSES AT NO COST TO THE OWNER. REMOVE
THIS ADDITIONAL STEEL UNLESS DIRECTED OTHERWISE BY THE OWNER IN WRITING.
PROVIDE TEMPORARY BRACING AND SHORING AS REQUIRED FOR THE SAFETY,
STABILITY AND ALIGNMENT OF THE STRUCTURE. LEAVE TEMPORARY BRACING IN
PLACE FOR AS LONG AS NECESSARY. PERFORM FINAL BOLTING AND WELDING ONLY
ON THOSE PORTIONS OF THE STRUCTURE THAT HAVE BEEN ALIGNED AND PLUMBED
WITHIN THE SPECIFIED TOLERANCES.
PROVIDE NEW MATERIAL CONFORMING TO THE FOLLOWING REQUIREMENTS FOR
ALL STRUCTURAL STEEL:
MEMBER
WIDE FLANGE SHAPES
CHANNELS & ANGLES
HSS SHAPES (ROUND & RECT)
BASE PLATES
HIGH STRENGTH BOLTS, NUTS, & WASHERS
WELDING ELECTRODE
GRADE
ASTM A992
ASTM A36
ASTM A500, GRADE B
ASTM A36
ASTM A325 OR A490 (3/4"Ø MINIMUM)
E70XX
MISCELLANEOUS NOTES
VERIFY EXISTING CONDITIONS AND DIMENSIONS PRIOR TO COMMENCING WORK.
CONSULT THE MECHANICAL, PLUMBING, AND ELECTRICAL DRAWINGS FOR LOCATION
AND SIZE OF CHASES, INSERTS, OPENINGS, SLEEVES, WASHES, DRIPS, REVEALS,
DEPRESSIONS AND OTHER PROJECT REQUIREMENTS.
DETAILS INDICATE REQUIRED CONSTRUCTION AT SPECIFIC LOCATIONS. FOR
LOCATIONS NOT SPECIFICALLY DETAILED, USE SIMILAR CONSTRUCTION TO THE MOST
APPROPRIATE DETAIL.
EQUIPMENT WEIGHTS AND/OR DIMENSIONS INDICATED ON DRAWINGS ARE ASSUMED,
NOTIFY THE CONTRACTING OFFICER IF ACTUAL WEIGHTS AND/OR DIMENSIONS ARE
DIFFERENT.
ALL SUBMITTALS, APPROVALS, REVIEWS, ACCEPTANCE, NOTIFICATIONS, ETC., MUST BE
DIRECTED TO THE CONTRACTING OFFICER.
M1
M2
M3
M4
M5
DESIGN CRITERIA
BUILDING CODE
INTERNATIONAL BUILDING CODE 2018
SNOW LOAD
GROUND SNOW LOAD, Pg FLAT ROOF SNOW LOAD, Pf SNOW EXPOSURE FACTOR, Ce SNOW LOAD IMPORTANCE FACTOR, Is THERMAL FACTOR, Ct
WIND DESIGN DATA
BASIC WIND SPEED (3 SECOND GUST)
WIND IMPORTANCE FACTOR, Iw
RISK CATEGORY
WIND EXPOSURE
INTERNAL PRESSURE COEFFICIENT, Gcpi
COMPONENTS AND CLADDING, P
ROOF SURFACE (ZONE 1)
ROOF EDGE (ZONE 2)
ROOF CORNER (ZONE 3)
WALL SURFACE (ZONE 4)
WALL CORNER (ZONE 5)
EARTHQUAKE DESIGN DATA
RISK CATEGORY
SEISMIC IMPORTANCE FACTOR, Ie SPECTRAL RESPONSE ACCELERATION, Ss
SPECTRAL RESPONSE ACCELERATION, S1
SITE CLASS
SPECTRAL RESPONSE COEFFICIENT, Sds SPECTRAL RESPONSE COEFFICIENT, Sd1
SEISMIC DESIGN CATEGORY
BASIC SEISMIC-FORCE-RESISTING SYSTEM
DESIGN BASE SHEAR
SEISMIC RESPONSE COEFFICIENT, Cs
RESPONSE MODIFICATION FACTOR, R
ANALYSIS PROCEDURE (EQUIVALENT FORCE METHOD)
25 psf
17.5 psf 1.0 1.0 1.0
115 mph 1.0
II
B +0.18 / -0.18
+13.1 / -51.4 psf +13.1 / -70.6 psf +13.1 / -92.4 psf +32.3 / -35 psf +32.3 / -43.2 psf
II
1.00 0.18 0.047
ASSUMED D
0.192 0.075 B
EXISTING REINFORCED
MASONRY SHEAR WALL
NOT CALCULATED
0.096
NOT REQUIRED
{OTHER
SIDE}
{ARROW SIDE}
FIELD WELD SYMBOL S(E)
S(E)
L-P
L-P
DEPTH OF PENETRATION
OR SIZE IN INCHES
WELD ALL AROUND
SYMBOL
R
LENGTH OF WELD IN INCHES
PITCH (CENTER TO CENTER
SPACING) OF WELDS IN
INCHES
SPECIFICATION, PROCESS,
OR OTHER REFERENCE
TAIL (OMITTED WHEN
REFERENCE IS NOT USED)
WELD SYMBOL
REFERENCE LINE
EFFECTIVE THROAT
WELD SYMBOL NOMENCLATURE
STRUCTURAL SYMBOLS AND NOTATIONS
EARTH (DISTURBED)
TOP OF PIER ELEVATION
TOP OF SHELF ELEVATION
TOP OF WALL ELEVATION
FOOTING STEP
WALL/SHELF STEP
(LO)
(HI)
(LO)
(HI)
SLAB ELEVATION
T/SLAB =
SLAB RAMP
SLAB STEP
SLOPED STRUCTURAL FRAMING
(POINTING DOWN SLOPE)
MOMENT CONNECTION AT
CANTILEVER
MOMENT FRAME
BR-1 BRACED FRAME
WORK POINT
WP
HSS HANGER
EARTH (UNDISTURBED)
GRAVEL
ROCK
SAND
SELECT FILL
IMPERVIOUS FILL (CLAY)
CMU
FLOOR OPENINGOPEN
RECESSED CONCRETE
SECTION INDICATION
DIRECTION OF VIEWDRAWING NUMBER
WHERE SECTION IS
DRAWN
SECTION NUMBER
DETAIL INDICATION
DRAWING NUMBER
WHERE DETAIL IS DRAWN
DETAIL NUMBER
DETAIL TITLE
NO SCALE
DETAIL
TYPENAME
SCALE
DETAIL
NUMBER
S301
S301
DIRECTION OF VIEW
SECTION NUMBER
AA
BEAM LEGEND
NOTES:
1. SHEAR REACTIONS, MOMENT REACTIONS, AXIAL FORCES, AND TORQUE FORCES
NOTED ON DRAWINGS ARE UNFACTORED.
2. PROVIDE FULL BEAM MOMENT CAPACITY IF MOMENT REACTION IS NOT NOTED ON
DRAWINGS.
SHEAR REACTION (EACH
END, UNLESS OTHERWISE
NOTED) IN KIPS
BEAM SIZE NUMBER OF HEADED
SHEAR STUDS
BEAM ELEVATION
RELATIVE TO DATUM
SHOP CAMBER
MOMENT REACTION
(EACH END, UNLESS
OTHERWISE NOTED)
IN KIP-FT W16x26 [16]M= 25k
C:3/4" (-3")
AXIAL FORCE (EACH
END, UNLESS
OTHERWISE NOTED)
IN KIPS
A=
TORQUE FORCE
(EACH END, UNLESS
OTHERWISE NOTED)
IN KIP-FT
T=
© 2021 making a difference through engineering
SM
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
Denver // Phoenix
RMH Group project number www.rmhgroup.com
Mechanical • Electrical Industrial • Sustainability
20440
KEY PLAN
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.
06 - 30 - 2021
/3
/2
:5 :5
A
M
As indicated
STRUCTURAL GENERAL NOTES
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL
CHILLED WATER PLANT
520 Chestnut St Philadelphia, PA 19106
NATIONAL PARK
SERVICE
S001
06/30/2021
VWM
MK
ED
2019063.02
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/2021
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/2021
0 CONSTRUCTION DOCUMENTS 06/30/2021
E E.5 F G J
H
13' - 6" 14' - 6" 22' - 9" 26' - 4"
CHILLER CH-1
(12' - 6 1/2")L x (8' - 5")W x (8' - 2 3/4")H (20 339) lbs
NEW (5") CONCRETE HOUSEKEEPING PAD.
EXISTING HOUSEKEEPING PAD TO BE
REMOVED. REPAIR SLAB TO MATCH
ADJACENT.
NOTE 2
NOTE 2
NOTE 2
NOTE 2
CHILLER CH-2
(12' - 7 3/8")L x (11' - 0")W x (9' - 9")H (29 499) lbs
NEW (5") CONCRETE HOUSEKEEPING PAD.
EXISTING HOUSEKEEPING PAD TO BE
REMOVED. REPAIR SLAB TO MATCH
ADJACENT.
NOTE 3
CHILLER CH-3
(12' - 7 3/8")L x (11' - 0")W x (9' - 9")H (29 499) lbs
NEW (5") CONCRETE HOUSEKEEPING PAD.
EXISTING HOUSEKEEPING PAD TO BE
REMOVED. REPAIR SLAB TO MATCH ADJACENT.
EXISTING HOUSEKEEPING
PAD TO BE REMOVED.
REPAIR SLAB TO MATCH
ADJACENT.
NEW PAD EXTENDED FROM
EXISTING PAD AS NECESSARY
TO SUPPORT CWP - 4.
CHWP - 1
(469) lbs
CHWP - 2
(1400) lbs
CHWP - 3
(1400) lbs
CWP - 1
(869) lbs
CWP - 2
(1972) lbs
CWP - 3
(1972) lbs
CWP - 4
(869) lbs
FIRST FLOOR PLAN NOTES
1. TOP OF SLAB ELEVATION IS 0'-0" UNLESS OTHERWISE NOTED.
2. EXISTING CONCRETE HOUSEKEEPING PAD TO REMAIN. VERIFY IN FIELD.
3. EXISTING STEEL FRAMING AND CONCRETE PLATFORM TO REMAIN.
4. OTHER EXISTING CONCRETE HOUSEKEEPING PADS THAT ARE NOT PART
OF THIS WORK NOT SHOWN FOR CLARITY.
0"
1'-0"
PAD
THICKNESS
REINFORCING
NOTE: COORDINATE PLAN SIZE AND LOCATION OF PADS WITH THE RESPECTIVE
CONTRACTOR OR MANUFACTURER.
#4@12" OC
DRILL AND GROUT 4"
INTO EXIST SLAB
REINF, SEE
SCHEDULE BELOW
≤ 8"
> 8"
#4@12" OC EW
#5@12" OC EW
CLR
2"
C
LR
3/ 4"
R
© 2021 making a difference through engineering
SM
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
Denver // Phoenix
RMH Group project number www.rmhgroup.com
Mechanical • Electrical Industrial • Sustainability
20440
KEY PLAN
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.
06 - 30 - 2021
/3
/2
:5 :5
A
M
As indicated
1ST FLOOR FRAMING PLAN AND
DETAILS
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL
CHILLED WATER PLANT
520 Chestnut St Philadelphia, PA 19106
NATIONAL PARK
SERVICE
S101
06/30/2021
VWM
MK
ED
2019063.02
SCALE: NO SCALE
TYPICAL HOUSEKEEPING PAD DETAIL
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/2021
E E.5 F G J
H
EXISTING W24EXISTING W24
EXISTING W21
EXISTING W21
EXISTING W21
EXISTING W21
EXISTING W21
EXISTING W21
EXISTING W21
EXISTING W16
EXISTING W16
EXISTING W21
S102
EXISTING W21
EXISTING W21
EXISTING W21
EXISTING W21
EXISTING W21
NOTE 4
NOTE 4
NOTE 4
EXISTING W21
NOTE 4
E X
IS
T
IN
G
W
E X
IS
T
IN
G
W
E X
IS
T
IN
G
W
COOLING TOWER CT-2
(18' - 0")L x (11' - 10")W x (16' - 6 1/4")H (15 960) lbs
9' - 5 3/8"2' - 1 3/8"
NOTE 5
NOTE 5 NOTE 5 NOTE 5 NOTE 5
W 6x
[T
O P
W 6x
[B
O T
T O
M
W 6x
[B
O T
T O
M
W6x25 [MIDDLE]
W6x25 [MIDDLE]
W6x25 [MIDDLE]
W6x25 [MIDDLE]
W6x25 [MIDDLE]
W6x25 [MIDDLE]
W 6x
[T
O P
W 6x
[B
O T
T O
M
W 6x
[T
O P
W 6x
[T
O P
W6x25 [MIDDLE]
W6x25 [MIDDLE]
W6x25 [MIDDLE]
W 6x
[B
O T
T O
M
W 6x
[T
O P
W 6x
[B
O T
T O
M
W 6x
[T
O P
W 6x
[B
O T
T O
M
9'
9'
9'
9'
9'
9'
2' - 1 3/8"9' - 5 3/8"9' - 5 3/8"2' - 1 3/8"
COOLING TOWER CT-3
(18' - 0")L x (11' - 10")W x (16' - 6 1/4")H (15 960) lbs
COOLING TOWER CT-1
(18' - 0")L x (11' - 10")W x (16 '- 6 1/4")H (15 960) lbs
NOTE 5
NOTE 6
NOTE 6
NOTE 6
NOTE 6
NOTE 6
NOTE 6
NOTE 1 AND
NOTE 4, TYP
N O
T E
S102
W 6x
[R
A
IL
W 6x
[R
A
IL
W 6x
[R
A
IL
W 6x
[R
A
IL
W
6x
[R A
IL
W 6x
[R
A
IL
11' - 6 3/4"
1-1/2"x3/16" WELDED STEEL GALVANIZED
SERRATED OPEN GRATING W/ BEARING
BARS @ 1-3/16" OC & CROSS BARS @ 4"
OC. TOP/GRATING = 12'-6" ABOVE ROOF.
S102
S102
L4x4x1/4 POST w/ 5"x5"x3/8" BASE PLATE w/ (1) 3/4"Øx4" ADHESIVE
ANCHOR, TYP.
L4x4x3/8
LATERAL BRACE
ACCESS LADDER w/ FALL-ARREST TIE-
OFF. ANCHOR LADDER TO EXIST ROOF
SLAB VIA 5"x5"x3/8" BASE PLATE w/ (1) 3/4"Øx4" ADHESIVE ANCHOR @ EACH RAIL.
SELF-CLOSING GATE GENERAL ROOF PLAN NOTES
1. TOP OF CONCRETE PEDESTALS IS 27' - 0" UNLESS OTHERWISE NOTED THUS; (+ OR -)
2. REFERENCE 1/S102 FOR STRUCTURAL STEEL ELEVATION. BEAM NOTATIONS TOP, MIDDLE, AND BOTTOM REFER
TO LOCATIONS SHOW IN SECTION.
3. EXISTING STEEL DUNNAGE TO BE REMOVED (NOT SHOWN FOR CLARITY).
4. EXISTING CONCRETE PEDESTALS AND TUBESTEEL SUPPORTING PARAPET WALLS TO REMAIN.
5. CENTERLINE OF EXISTING PEDESTALS. CENTER NEW DUNNAGE ON EXISTING CONCRETE PEDESTALS.
6. (3) VIBRATION ISOLATORS CENTERED ABOVE THE SUPPORTING BEAM BELOW, REFER TO 1/S102 FOR DETAILS.
7. INDICATES SPAN DIRECTION OF EXISTING 8" CONCRETE ROOF SLAB ON METAL DECK; VERIFY IN FIELD.
8. ALL NEW DUNNAGE IS TO BE GALVANIZED.
EXISTING PEDESTAL AND ANCHOR
BOLTS TO REMAIN, VERIFY IN FIELD
A
DETAIL A-A
EXISTING ANCHORS TO BE
RESUSED; *FIELD VERIFY
LOCATION, REMOVE
EXISTING NUT AND WASHER,
PROVIDE 1/4" WASHER AND
3/8" DIA NUT
* 4"
4"
COOLING TOWER NOT
SHOWN FOR CLARITY
PROVIDE 1" GROUT W/
3/8"x0'-10"x0'-10" STEEL
PLATE
NEW EXPANSION ANCHORS
(4) 5/8" DIA BOLTS, TYP
2 PLACES
REMOVE EXISTING FLASHING AS
NECESSARY TO EXPOSE TOP OF EXISTING
PEDESTAL. REMOVE EXISTING GROUT PAD
AND EXISTING PLATE. AFTER INSTALLATION
OF NEW FRAMING REPAIR FLASHING TO
MATCH EXISTING.
(2) 5/8" X 6" EMBED EXPANSION ANCHORS
2" 2"
TOP
MIDDLE
BOTTOM
VIBRATION ISOLATORS
RAIL
3/8" STIFFENER PLATE
EA SIDE, TYP
3/16
A
L6x4x3/8 (LLV) SHELF ANGLE
3/4"Øx4" GALV. ADHESIVE
SCREEN ANCHORS @ 16" O.C.
EXIST MASONRY PARAPET WALL
OPEN GRATING PLATFORM
E.5E.5
7' - 0"
S102
3'
1'
L6x4x3/8 (LLV) INTERMEDIATE
SUPPORT BEAM
L6x4x3/8 (LLV) DECK
EDGE BEAM
METAL FLOOR GRATING
L3x3x1/4 RAIL @ 3 SIDES OF
SERVICE PLATFORM, TYP.
L3x3x1/4 INTERMIDATE
VERTICAL SUPPORT
ANGLES
5/8"Ø BOLTS, TYP.
S102
3' - 3"3' - 5 5/8"3' - 3 1/4"
L6x4x3/8 (LLV) INTERMEDIATE
SUPPORT BEAM
L6x4x3/8 (LLV) DECK
EDGE BEAM
METAL FLOOR GRATING
L3x3x1/4 RAIL @ 3 SIDES OF
SERVICE PLATFORM, TYP.
L3x3x1/4 INTERMIDATE
VERTICAL SUPPORT ANGLES
SET VERTICAL FLUSH
WITH HORIZONTAL
SET VERTICAL FLUSH
WITH HORIZONTAL
EXISTING MASONRY
PARAPET WALL
3/4"Øx4" GALV. ADHESIVE
SCREEN ANCHORS, TYP.
© 2021 making a difference through engineering
SM
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
Denver // Phoenix
RMH Group project number www.rmhgroup.com
Mechanical • Electrical Industrial • Sustainability
20440
KEY PLAN
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.
06 - 30 - 2021
/3
/2
:5 :5
A
M
As indicated
ROOF FRAMING PLAN AND
DETAILS
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL
CHILLED WATER PLANT
520 Chestnut St Philadelphia, PA 19106
NATIONAL PARK
SERVICE
S102
6/30/2021
VWM
MK
ED
2019063.02
SCALE: 1" = 1'-0"
TYPICAL PEDESTAL ANCHORAGE SECTION
SCALE: 1 1/2" = 1'-0"
SERVICE PLATFORM PARAPET WALL CONNECTION
2 SCALE: 3/4" = 1'-0"
SERVICE PLATFORM SECTION
3 SCALE: 3/4" = 1'-0"
SERVICE PLATFORM SECTION
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/2021
KEY PLAN
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD:
STATE:
REGISTRATION NO.:
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.2/
/2
:3 6:
P
M
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL
CHILLED WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
07/22/21
2019063.02
CONSTRUCTION DOCUMENTS
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
RMH Group project number © 2021www.rmhgroup.com making a difference through engineering
Mechanical • Electrical Industrial • Sustainability Denver // Phoenix
SM
20440
JEFFREY ELSNER
PENNSYLVANIA
43784
JEREMY WHITLEY
PE090921
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
0 CONSTRUCTION DOCUMENTS 07/22/21
E001
ELECTRICAL
LEGEND
DS
APB
MDB
N
YEAR CODE
X
X X
7-22-21
E E.5 F G J H
ED700
UTILITY
TRANSFORMER
UTLITY METER
TRANSFORMER
PANEL A
PANEL A
SECTION 2
PANEL A
SECTION 1
CONTROL
CABINET
WATER TREATMENT EQUIPMENT
IRRIGATION CONTROLLER
INCOMING DOMESTIC
WATER GROUNDING POINT
CONTROL
CABINET
(E)CWP-1 (E)CWP-2 (E)CWP-3
(E)CHWP-1 (E)CHWP-2 (E)CHWP-3
3 3 3
CH-1
33 3 3
MCC-1
CH-2 CH-3
CHWP-4 CHWP-5
AHU-1
1 1
RS-1 RS-2
© 2021 making a difference through engineering
SM
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
Denver // Phoenix
RMH Group project number www.rmhgroup.com
Mechanical • Electrical Industrial • Sustainability
20440
KEY PLAN
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.7 /2
/2
:3
:3
A
M
1/4" = 1'-0"
ELECTRICAL POWER 1ST FLOOR -
REMOVAL
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL CHILLED
WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
ED200
07/22/21
APB
MDB
DS
2019063.02
DRAFT CONSTRUCTION DOCUMENTS
1 REMOVE CHILLER CONDUCTORS BACK TO MCC-1. CUT CONDUIT FLUSH WITH FLOOR AND GROUT
FLUSH WITH FINISHED PAD SURFACE.
KEY NOTES
SHEET NOTES
1. EQUIPMENT INDICATED ON THIS SHEET IS EXISTING. HATCHING INDICATES DEMO.
2. PROVIDE TEMPORARY POWER FOR ALL CONSTRUCTION NEEDS.
3. PATCH AND PAINT ANY DAMAGED SURFACES DUE TO DEMOLITION AND CONSTRUCTION TO MATCH
EXISTING CONDITIONS. SEAL ALL PENETRATIONS THROUGH RATED CEILINGS AND WALLS WITH UL
LISTED SEALANTS AND FIRESTOPPING MATERIALS.
4. MAKE PROVISIONS FOR SEPARATE CONSTRUCTION POWER RECEPTACLES TO AVOID ADDITIONAL
WEAR TO EXISTING DEVICES.
5. REFER TO SHEET ED700 FOR OUTAGE NOTES AND ONELINE DIAGRAM.
6. REFER TO SHEET ED600 FOR ELECTRICAL SCHEDULES.
7. REMOVE LIGHTING PROTECTION COMPONENTS FROM EXISTING COOLING TOWERS. PRESERVE
EQUIPMENT FOR RE-INSTALLATION. REFER TO SHEET E201 FOR NEW WORK.
0' 2' 4' 8' 16'
1/4"=1'-0"
1'
SCALE: 1/4" = 1'-0"
ELECTRICAL POWER 1ST FLOOR REMOVAL PLAN
CONTROL ROOM
2 REFER TO ONELINE DIAGRAM, SHEET EI700 FOR CONFIGURATION OF MCC-1 DURING CONSTRUCTION
AND FOR CONSTRUCTION POWER SOURCES. REFER TO SHEET ED600 AND ED700 FOR SCHEDULES
AND ELEVATION FOR REMOVALS IN THIS EQUIPMENT.
3 REMOVE EXISTING MOTOR CIRCUIT CONDUCTORS. REMOVE CONDUIT TO CEILING AREA SEE POWER
PLAN, SHEET E200 FOR NEW WORK.
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD: JEREMY WHITLEY
STATE: PENNSYLVANIA
REGISTRATION NO.: PE090921
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
E E.5 F G J H
DISPATCH BACKUP
POWER
GENERATOR
CT-2 VFD
CT-3 VFD
CT-1 VFD
CT-3
CT-2 CT-1
EF-1
EF-2
AHU-2
MCC-2
1 1
© 2021 making a difference through engineering
SM
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
Denver // Phoenix
RMH Group project number www.rmhgroup.com
Mechanical • Electrical Industrial • Sustainability
20440
KEY PLAN
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.7 /2
/2
:3
:4
A
M
1/4" = 1'-0"
ELECTRICAL POWER ROOF -
REMOVAL
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL CHILLED
WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
ED201
07/22/21
APB
MDB
DS
2019063.02
DRAFT CONSTRUCTION DOCUMENTS
1 REMOVE LIGHTNING PROTECTION AIR TERMINALS AND CONDUCTORS FROM THREE COOLING TOWERS
AND ASSOCIATED STRUCTURES. DETACH CABLES FROM GROUND POTENTIAL RING AND FROM
DOWNLEADS. PRESERVE TERMINAL POINTS FOR CONNECTION OF NEW CABLES.
KEY NOTES
SHEET NOTES
1. EQUIPMENT INDICATED ON THIS SHEET IS EXISTING. HATCHING INDICATES DEMO.
2. PROVIDE TEMPORARY POWER FOR CONSTRUCTION NEEDS.
3. PATCH AND PAINT ANY DAMAGED SURFACES DUE TO DEMOLITION AND CONSTRUCTION TO MATCH
EXISTING CONDITIONS. SEAL ALL PENETRATIONS THROUGH RATED CEILINGS AND WALLS WITH UL
LISTED SEALANTS AND FIRESTOPPING MATERIALS.
4. MAKE PROVISIONS FOR SEPARATE CONSTRUCTION POWER RECEPTACLES TO AVOID ADDITIONAL
WEAR TO EXISTING DEVICES.
5. REFER TO SHEET ED700 FOR OUTAGE NOTES AND ONELINE DIAGRAM.
6. REFER TO SHEET ED600 FOR ELECTRICAL SCHEDULES.
0' 2' 4' 8' 16'
1/4"=1'-0"
1'
SCALE: 1/4" = 1'-0"
ELECTRICAL POWER ROOF REMOVAL PLAN
ED700
2 EXISTING WALL MOUNTED LIGHTING TO REMAIN. TYPICAL OF SIX WALL MOUNTED FIXTURES.
3 DETACH ALL CIRCUITS AND FEEDER FROM MCC-2. SEE SHEET ED600 FOR SALVAGE OF SELECTED
BREAKERS AND STARTERS. REMOVE SUPPORT STEEL FRAME. CAP CONDUITS DURING CONSTRUCTION
TO PREVENT DIRT AND DEBRIS FROM ENTERING
4 DISCONNECT AND REMOVE MOTOR LEADS CONDUIT AND CONDUCTORS FROM COOLING TOWER TO
VFD ENCLOSURE.
5 REMOVE EXISTING CONDUCTORS BACK TO MCC-2. RELOCATE CONDUIT STUB-UP TO NEW VFD
ENCLOSURE LOCATION. SEAL ROOF PENETRATION.
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD: JEREMY WHITLEY
STATE: PENNSYLVANIA
REGISTRATION NO.: PE090921
EXISTING AHU-1 OA PLENUM
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
0 CONSTRUCTION DOCUMENTS 07/22/2021
A
B
C
D
E
1 2 3 4 5
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD:
STATE:
REGISTRATION NO.:
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.2/
/2
:3 6:
P
M
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL
CHILLED WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
07/22/21
2019063.02
CONSTRUCTION DOCUMENTS
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
RMH Group project number © 2021www.rmhgroup.com making a difference through engineering
Mechanical • Electrical Industrial • Sustainability Denver // Phoenix
SM
20440
PENNSYLVANIA
JEREMY WHITLEY
PE090921
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
0 CONSTRUCTION DOCUMENTS 07/22/21
ED600
ELECTRICAL
PANEL SCHEDULES DEMO
DS
APB
MDB
A
B
C
D
E
1 2 3 4 5
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD:
STATE:
REGISTRATION NO.:
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.2/
/2
:3 6:
P
M
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL
CHILLED WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
07/22/21
2019063.02
CONSTRUCTION DOCUMENTS
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
RMH Group project number © 2021www.rmhgroup.com making a difference through engineering
Mechanical • Electrical Industrial • Sustainability Denver // Phoenix
SM
20440
PENNSYLVANIA
JEREMY WHITLEY
PE090921
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
0 CONSTRUCTION DOCUMENTS 07/22/21
ED700
ELECTRICAL
ONELINE REMOVALS
DS
APB
E E.5 F G J H
MCC-1
CONTROL ROOM
CONTROL
CABINET
UTILITY METER
WATER TREATMENT EQUIPMENT
IRRIGATION CONTROLLER
INCOMING DOMESTIC WATER
GROUNDING POINT
CONTROL CABINET
(E)CWP-1 (E)CWP-2 (E)CWP-3
(E)CHWP-1 (E)CHWP-2 (E)CHWP-3
CHWP-4 CHWP-5
AHU-1
CH-1 CH-2 CH-3
RS-1 RS-2
© 2021 making a difference through engineering
SM
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
Denver // Phoenix
RMH Group project number www.rmhgroup.com
Mechanical • Electrical Industrial • Sustainability
20440
KEY PLAN
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.7 /2
/2
:3
:4
A
M
1/4" = 1'-0"
ELECTRICAL POWER PLAN -
INTERMEDIATE
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL CHILLED
WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
EI200
07/22/21
APB
MDB
DS
2019063.02
DRAFT CONSTRUCTION DOCUMENTS
0' 2' 4' 8' 16'
1/4"=1'-0"
1'
SCALE: 1/4" = 1'-0"
ELECTRICAL POWER 1ST FLOOR INTERMEDIATE PLAN
1 PROVIDE THREE 4-INCH WATERPROOF WALL PENETRATIONS FOR ELECTRICAL SERVICE TO
TEMPORARY CHILLER. PROVIDE SEPARATE PENETRATIONS FOR CHILLER ELECTRICAL FEEDERS,
PERIPHERAL ACCESSORIES CIRCUITS, AND NETWORK COMMUNICATIONS CABLE. WHEN THE NEED FOR
TEMPORARY CHILLER HAS PASSED REMOVE THE SLEEVES AND PATCH PENETRATIONS TO MATCH
BUILDING EXTERIOR AND INTERIOR FINISHES RESPECTIVELY. COORDINATE NUMBER AND SIZE OF
PENETRATIONS WITH MECHANICAL CONTRACTOR BASED UPON THE ACTUAL TEMPORARY CHILLER
PROVIDED.
KEY NOTES
SHEET NOTES
1. LIGHT LINE WEIGHT INDICATES EXISTING (E). HEAVY LINE WEIGHT INDICATES NEW (N)
CONSTRUCTION.
2. PROVIDE TEMPORARY POWER FOR CONSTRUCTION NEEDS.
3. PATCH AND PAINT ANY DAMAGED SURFACES DUE TO DEMOLITION AND CONSTRUCTION TO MATCH EXISTING CONDITIONS. SEAL ALL PENETRATIONS THROUGH RATED CEILINGS AND WALLS WITH UL
LISED SEALANTS AND FIRESTOPPING MATERIALS.
4.
5. MAKE PROVISIONS FOR SEPARATE CONSTRUCTION POWER RECEPTACLES TO AVOID ADDITIONAL
WEAR TO EXISTING DEVICES.
6. REFER TO SHEET EI700 FOR ONELINE DIAGRAM AND LOAD SUMMARY RELATED TO THIS EQUIPMENT
ELECTRICAL SCHEDULES.
7. REFER TO ED700 FOR OUTAGE NOTES
8. INTERMEDIATE PHASE DRAWINGS INDICATE TEMPORARY POWER CONFIGURATION DURING
CONSTRUCTION AND IS TO BE COMPLETED BEFORE NEW WORK BEGINS, SEE SHEET EI700 FOR
ADDITIONAL INTERMEDIATE PHASE DETAILS FOR TEMPORARY POWER CONFIGURATION. REFER TO SHEET E700 FOR NEW WORK DETAILS TO BE COMPLETED AFTER INTERMEDIATE PHASE IS COMPLETE.
2 REFER TO ONELINE DIAGRAM, SHEET EI700 FOR CONFIGURATION OF MCC-1 DURING CONSTRUCTION
AND FOR CONSTRUCTION POWER SOURCES.
EI700
UTILITY
TRANSFORMER
TRANSFORMER PANEL A
PANEL A
SECTION 2
PANEL A
SECTION 1
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD: JEREMY WHITLEY
STATE: PENNSYLVANIA
REGISTRATION NO.: PE090921
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
A
B
C
D
E
1 2 3 4 5
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD:
STATE:
REGISTRATION NO.:
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.2/
/2
:3 6:
P
M
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL
CHILLED WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
07/22/21
2019063.02
CONSTRUCTION DOCUMENTS
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
RMH Group project number © 2021www.rmhgroup.com making a difference through engineering
Mechanical • Electrical Industrial • Sustainability Denver // Phoenix
SM
20440
PENNSYLVANIA
JEREMY WHITLEY
PE090921
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
0 CONSTRUCTION DOCUMENTS 07/22/21
EI700
ELECTRICAL
ONELINE INTERMEDIATE
DS
APB
E E.5 F G J H
CWP-1 CWP-2
CWP-3 CWP-4
CH-1 CH-2 CH-3
CHWP-1 CHWP-2 CHWP-3
UTILITY METER
UTILITY TRANSFORMER
E700
E500
CWP-1
CWP-2
CWP-3
CWP-4
VFDS
PANEL A
SECTION 1
PANEL A
SECTION 2
CONTROL
PANEL
WATER TREATMENT EQUIPMENT
VFD CHWP-1 VFD CHWP-2 VFD CHWP-3
IRRIGATION CONTROLLER
INCOMING DOMESTIC WATER GROUNDING POINT
CONTROLS CABINET
MCC-1
AHU-1
CHWP-4 CHWP-5
RS-1 RS-2
TRANSFORMER
PANEL A
3 3
E500
© 2021 making a difference through engineering
SM
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
Denver // Phoenix
RMH Group project number www.rmhgroup.com
Mechanical • Electrical Industrial • Sustainability
20440
KEY PLAN
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.7 /2
/2
:3
:3
A
M
1/4" = 1'-0"
ELECTRICAL POWER 1ST FLOOR
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL CHILLED
WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
E200
07/22/21
APB
MDB
DS
2019063.02
DRAFT CONSTRUCTION DOCUMENTS
1 WHEN NEED FOR TEMPORARY CHILLERS HAS PASSED, REMOVE SLEEVES AND PATCH PENETRATIONS
TO MATCH BUILDING EXTERIOR AND INTERIOR FINISHES RESPECTIVELY.
KEY NOTES
SHEET NOTES
1. LIGHT LINE WEIGHT INDICATES EXISTING (E). HEAVY LINE WEIGHT INDICATES NEW (N)
CONSTRUCTION.
2. PROVIDE TEMPORARY POWER FOR CONSTRUCTION NEEDS.
3. PATCH AND PAINT ANY DAMAGED SURFACES DUE TO DEMOLITION AND CONSTRUCTION TO MATCH EXISTING CONDITIONS. SEAL ALL PENETRATIONS THROUGH RATED CEILINGS AND WALLS WITH UL
LISTED SEALANTS AND FIRESTOPPING MATERIALS.
4. REFER TO SHEET E700 FOR ONELINE DIAGRAM AND LOAD SUMMARY RELATED TO THIS EQUIPMENT.
5. REFER TO SHEET E600 FOR ELECTRICAL SCHEDULES AND EQUIPMENT SCHEDULE FOR CONDUIT AND
BRANCH CIRCUIT SIZES.
0' 2' 4' 8' 16'
1/4"=1'-0"
1'
SCALE: 1/4" = 1'-0"
ELECTRICAL POWER 1ST FLOOR PLAN
2 REFER TO SHEET E700 FOR WORK IN MCC-1.
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD: JEREMY WHITLEY
STATE: PENNSYLVANIA
REGISTRATION NO.: PE090921
3 MAINTAIN EMERGENCY EGRESS PATH.
4 BID ALTERNATE, SEE SHEET E700 FOR DETAILS.
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
V V
V
V
E E.5 F G J H
SWBD RP-1
E700
AHU-2
FVNR
STARTER
DISPATCH POWER
BACKUP
GENERATOR
CT-1 VFD
CT-3 VFD
EF-1
EF-2
AHU-2
CT-2 VFD
EF-1 VFD
EXISTING AHU-1 OA PLENUM
CT-1 CT-2
CT-3
© 2021 making a difference through engineering
SM
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
Denver // Phoenix
RMH Group project number www.rmhgroup.com
Mechanical • Electrical Industrial • Sustainability
20440
KEY PLAN
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.7 /2
/2
:3
:3
A
M
1/4" = 1'-0"
ELECTRICAL POWER ROOF
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL CHILLED
WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
E201
07/22/21
APB
MDB
DS
2019063.02
DRAFT CONSTRUCTION DOCUMENTS
1 PROVIDE A NEW SWITCHBOARD WITH E NEMA 4X RATED ENCLOSURE TO REPLACE MCC-2. REFER TO ONELINE DIAGRAM, SHEET E700 FOR CONNECTIONS. SWITCHBOARD SHALL BE MOUNTED ON A STEEL FRAME. PROVIDE A SOLID OR SCREENED BOTTOM PANEL AND TERMINATE EXISTING CONDUITS TO
BOTTOM PANEL. PROVIDE BONDING BUSHINGS AS REQUIRED.
KEY NOTES
SHEET NOTES
1. LIGHT LINE WEIGHT INDICATES EXISTING (E). HEAVY LINE WEIGHT INDICATES NEW (N)
CONSTRUCTION..
2. PROVIDE TEMPORARY POWER FOR CONSTRUCTION NEEDS.
3. PATCH AND PAINT ANY DAMAGED SURFACES DUE TO DEMOLITION AND CONSTRUCTION TO MATCH EXISTING CONDITIONS. SEAL ALL PENETRATIONS THROUGH RATED CEILINGS AND WALLS WITH UL
LISTED SEALANTS AND FIRESTOPPING MATERIALS.
4. REFER TO SHEET E700 FOR ONELINE DIAGRAM AND LOAD SUMMARY RELATED TO THIS EQUIPMENT.
5. REFER TO SHEET E600 FOR ELECTRICAL SCHEDULES AND EQUIPMENT SCHEDULE FOR CONDUIT AND
BRANCH CIRCUIT SIZES.
6. ALL ELECTRICAL EQUIPMENT ON THIS SHEET TO BE RATED NEMA 4X.
7. RE-INSTALL LIGHTING PROTECTION SYSTEM ONTO NEW COOLING TOWERS. CONNECT TO EXISTING
POTENTIAL RING AND DOWNLEADS. PROVIDE A UL INSPECTIONS CERTIFICATION.
0' 2' 4' 8' 16'
1/4"=1'-0"
1'
SCALE: 1/4" = 1'-0"
ELECTRICAL POWER ROOF PLAN
2 COORDINATE EXACT LOCATION OF VFD ENCLOSURES WITH STRUCTURAL AND MECHANICAL COOLING TOWER ENCLOSURES. CONFIRM FINAL LOCATION FOR ENCLOSURES WITH OWNER REPRESENTATIVE
TO VERIFY ADEQUATE MAINTENANCE ACCESS.
3 PROVIDE NEW LIGHTNING PROTECTION COMPONENTS FOR COOLING TOWERS AND ASSOCIATED
STRUCTURES. REFER TO PERFORMANCE SPECIFICATIONS FOR REQUIREMENTS. VERIFY COOLING
TOWER STRUCTURE IS ADEQUATELY BONDED. REPAIR LIGHTNING PROTECTION CABLING OR
COMPONENTS THAT HAVE BEEN DAMAGED DURING COOLING TOWER INSTALLATION OR OTHER
CONSTRUCTION RELATED ACTIVITY.
4 EXISTING WALL MOUNTED LIGHT FIXTURES TO REMAIN. TYPICAL OF SIX.
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD: JEREMY WHITLEY
STATE: PENNSYLVANIA
REGISTRATION NO.: PE090921
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
A
B
C
D
E
1 2 3 4 5
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD:
STATE:
REGISTRATION NO.:
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.2/
/2
:3 6:
P
M
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL
CHILLED WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
07/22/21
2019063.02
CONSTRUCTION DOCUMENTS
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
RMH Group project number © 2021www.rmhgroup.com making a difference through engineering
Mechanical • Electrical Industrial • Sustainability Denver // Phoenix
SM
20440
PENNSYLVANIA
JEREMY WHITLEY
PE090921
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
0 CONSTRUCTION DOCUMENTS 07/22/21
E500
ELECTRICAL
ONE-LINE DIAGRAM
DS
APB
A
B
C
D
E
1 2 3 4 5
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD:
STATE:
REGISTRATION NO.:
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.2/
/2
:3 6:
P
M
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL
CHILLED WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
07/22/21
2019063.02
CONSTRUCTION DOCUMENTS
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
RMH Group project number © 2021www.rmhgroup.com making a difference through engineering
Mechanical • Electrical Industrial • Sustainability Denver // Phoenix
SM
20440
PENNSYLVANIA
JEREMY WHITLEY
PE090921
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
0 CONSTRUCTION DOCUMENTS 07/22/21
E600
ELECTRICAL
PANEL SCHEDULES
DS
APB
A
B
C
D
E
1 2 3 4 5
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD:
STATE:
REGISTRATION NO.:
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.2/
/2
:3 6:
P
M
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL
CHILLED WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
07/22/21
2019063.02
CONSTRUCTION DOCUMENTS
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
RMH Group project number © 2021www.rmhgroup.com making a difference through engineering
Mechanical • Electrical Industrial • Sustainability Denver // Phoenix
SM
20440
PENNSYLVANIA
JEREMY WHITLEY
PE090921
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
0 CONSTRUCTION DOCUMENTS 07/22/21
E700
ELECTRICAL ONELINE
DIAGRAM - NEW WORK
DS
APB
A
B
C
D
E
1 2 3 4 5
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD:
STATE:
REGISTRATION NO.:
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.2/
/2
:3 6:
P
M
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL
CHILLED WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
07/22/21
2019063.02
CONSTRUCTION DOCUMENTS
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
RMH Group project number © 2021www.rmhgroup.com making a difference through engineering
Mechanical • Electrical Industrial • Sustainability Denver // Phoenix
SM
20440
JEFFREY ELSNER
PENNSYLVANIA
43784
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
0 CONSTRUCTION DOCUMENTS 07/22/21
M001
MECHANICAL
LEGEND
JE
APB
MJ
N
YEAR CODE
X
X bstroschein PE Seal Template
A
B
C
D
E
1 2 3 4 5
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD:
STATE:
REGISTRATION NO.:
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.2/
/2
:3 6:
P
M
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL
CHILLED WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
07/22/21
2019063.02
CONSTRUCTION DOCUMENTS
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
RMH Group project number © 2021www.rmhgroup.com making a difference through engineering
Mechanical • Electrical Industrial • Sustainability Denver // Phoenix
SM
20440
JEFFREY ELSNER
PENNSYLVANIA
43784
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
0 CONSTRUCTION DOCUMENTS 07/22/21
MD100
MECHANICAL PIPING FLOW
DIAGRAM - REMOVAL
JE
APB
MJ
E E.5 F G J H
M300
M301
3 3 3
7 7
M300
(E)12" CWS
(E)10" CHWS
(E )8
C
H W
S
(E)10" CHWR
(E)8" CHWR(E)10" CHWR
(E)6" CHWS
(E)12" CWS(E)8" CHWR (E)10" CHWS
(E)6" CHWR
(E)12" CWR
(E)12" CWR
(E)6" CHWS
(E)8" CHWR
(E)10" CHWR(E)8" CHWR
(E)10" CHWR
(E )1
2" C
W R
(E)10" CWR
(E)8" CHWR
(E)10" CHWS
(E)10" CHWS
(E)10" CHWS
(E)2 1/2" HWS
(E)2 1/2" HWR
(E)2 1/2" CHWR
(E)2 1/2" CHWS
(E)12" CWS
(E)10" CWS
(E)10" CHWS
(E)6" V
(E)8"
(E)10" CWS
(E )1
0" C
W S
(E )1
0" C
W S
(E )1
0" C
W S
(E)10" CWS
(E)6" CHWR
(E)6" CHWS
(E)6" CHWR
(E)6" CHWS
(E)CHWP-6
(E)CHWP-2
(E)CHWP-3
(E)CHWP-1
(E)CH-1
(E)CH-2
(E)CH-3
(E)CWP-3(E)CWP-2
(E)CWP-1
(E)RS-1 (E)RS-2 (E)AHU-1
(E)CWP-5
(E)CWP-4
(E) EXPANSION
TANK
(E)AS-1
(E) HX-1
© 2021 making a difference through engineering
SM
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
Denver // Phoenix
RMH Group project number www.rmhgroup.com
Mechanical • Electrical Industrial • Sustainability
20440
KEY PLAN
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.7 /2
/2
:4
:3
A
M
1/4" = 1'-0"
MECHANICAL PIPING 1ST FLOOR -
REMOVAL
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL CHILLED
WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
MD201
07/22/21
APB
MJ
JE
2019063.02
DRAFT CONSTRUCTION DOCUMENTS
KEY NOTES
SHEET NOTES
1. LIGHT LINE WEIGHT INDICATES EXISTING. HATCHING INDICATES DEMOLITION.
2. COORDINATE WITH CONTRACTING OFFICER PRIOR TO DISPOSING OF ANY REMOVED MECHANICAL
MATERIALS OR EQUIPMENT.
3. REPAIR ALL SURFACES AND FINISHES DAMAGED DUE TO DEMOLITION OR CONSTRUCTION TO MATCH
EXISTING CONDITIONS.
4. EQUIPMENT AND PIPING SHOWN ON THIS DRAWING ARE BASED ON RECORD INFORMATION PROVIDED IN PART BY OTHERS. THE CONTRACTOR IS RESPONSIBLE FOR FIELD VERIFICATION OF EXISTING CONDITIONS PRIOR TO STARTING WORK AND SHALL NOTIFY THE CONTRACTING OFFICER OF ANY
DISCREPANCIES FOR RESOLUTION.
5. COORDINATE WITH PLANT OPERATORS BEFORE CUTTING, SHUTTING OFF VALVES, OR SHUTTING
DOWN PLUMBING EQUIPMENT OR SYSTEMS AT LEAST SEVEN DAYS BEFORE PERFORMING WORK.
6. COORDINATE DEMOLITION WORK WITH CONTRACTING OFFICER PRIOR TO CONSTRUCTION TO
DETERMINE WORK REQUIRED DURING OFF HOURS OR WEEKENDS.
7. CONTRACTOR SHALL NOT REMOVE ANY SYSTEM FROM SERVICE BEFORE COORDINATING WITH
CONTRACTING OFFICER.
8. CONTRACTOR SHALL SUBMIT A DETAILED SCHEDULE PRIOR TO BEGINNING ANY DEMOLITION IN THE
CHILLER PLANT. THE SCHEDULE SHALL INCLUDE DURATION OF ALL PLANNED OUTAGES, AND
IDENTIFY THE DATE WHEN A TEMPORARY CHILLER WILL NO LONGER BE NEEDED. SEE SHEETS M100, M200, AND M210 FOR TEMPORARY CHILLER INFORMATION AND NEW WORK THAT IS REQUIRED PRIOR
TO SOME OF THE DEMOLITION SHOWN ON THIS SHEET.
9. PROTECT EQUIPMENT, PIPING, AND VALVES THAT REMAIN. UNLESS OTHERWISE NOTED ALL VALVES SHALL BE RETAINED, INSPECTED, AND RE-USED. IF CONTRACTOR NOTICES SIGNIFICANT DAMAGE OR FUNCTIONAL ISSUES WITH AN EXISTING VALVE THE CONTRACTOR SHALL NOTIFY THE CONTRACTING
OFFICER.
10. CONTRACTOR SHALL PROTECT AND ISOLATE EXISTING FIRE DETECTION AND SUPPRESSION SYSTEM
TO PREVENT FALSE ALARMS DUE TO NORMAL CONSTRUCTION ACTIVITIES
0' 2' 4' 8' 16'
1/4"=1'-0"
1'
SCALE: 1/4" = 1'-0"
MECHANICAL PIPING 1ST FLOOR REMOVAL PLAN
1 DEMOLISH SECTION OF PIPING AS NECESSARY TO INSTALL NEW CHECK VALVE AND 6" BYPASS, REFER
TO SHEETS M100 AND M200. COORDINATE OUTAGE TO CAMPUS CHILLED WATER SYSTEM WITH
CONTRACTING OFFICER. IN ORDER TO ACCESS THIS PIPING FOR CONSTRUCTION EITHER DRAIN DOWN PLANT CHILLED WATER PIPING OR PROVIDE FREEZE ISOLATION AROUND THIS SECTION OF PIPING.
2 DEMOLISH SECTION OF PIPING AS NECESSARY TO INSTALL ISOLATION VALVE, REFER TO SHEETS M100 AND M200. COORDINATE OUTAGE TO CAMPUS CHILLED WATER SYSTEM WITH CONTRACTING OFFICER.
IN ORDER TO ACCESS THIS PIPING FOR CONSTRUCTION EITHER DRAIN DOWN PLANT CHILLED WATER
PIPING OR PROVIDE FREEZE ISOLATION AROUND THIS SECTION OF PIPING.
3 REMOVE EXISTING CHILLER INCLUDING ALL COMPONENTS. REMOVE, CONTAIN AND DISPOSE OF R-123 REFRIGERANT PER THE REQUIREMENTS OF THE CLEAN AIR ACT, SECTION 608. SUBMIT COPY OF
RECORD OF DISPOSAL OR RECYCLING. REFER TO STRUCTURAL DRAWINGS FOR DETAILS OF
DEMOLITION OF EQUIPMENT PADS.
4 12" CONDENSER WATER RETURN UP TO ROOF, SEE MD202 FOR CONTINUATION.
5 12" CONDENSER WATER SUPPLY FROM COOLING TOWERS UP TO ROOF, SEE MD202 FOR
CONTINUATION.
6 REMOVE PUMP, PIPING AND VALVES AS SHOWN. REFER TO MD100 AND SECTIONS ON M300 SERIES
SHEETS FOR ADDITIONAL DETAIL. REFER TO STRUCTURAL DRAWINGS FOR DEMOLITION OR
MODIFICATION OF EQUIPMENT PADS.
7 SECONDARY PUMPS TO REMAIN IN OPERATION TO CIRCULATE CHILLED WATER TO CAMPUS. PROTECT
PUMPS DURING DEMOLITION AND CONSTRUCTION.
8 EXISTING SUMP TANKS TO REMAIN UNDER BASE CONTRACTS. REFER TO DETAIL SHEETS FOR BID
ALTERNATE SCOPE FOR THESE TANKS.
9 8" CHWS AND CHWR TO CAMPUS BUILDINGS
10 EXISTING AHU-1. AHU-1 PROVIDES HEATING, COOLING, AND VENTILATION FOR THE CHILLER PLANT
THROUGH DUCTWORK INSIDE THE PLANT (DUCTWORK NOT SHOWN FOR CLARITY). MAINTAIN
OPERATION OF AIR HANDLER OR PROVIDE TEMPORARY HEATING FOR THE PLANT. PROVIDE NEW
FILTERS AT REGULARY INTERVALS DURING CONSTRUCTION SO THAT FILTER PRESSURE DROP DOES
NOT EXCEED 0.33" W.C. PROVIDE NEW FILTERS AT CONCLUSIONG OF CONSTRUCTION.
11 REMOVE EXISTING CHWP-6 AND ASSOCIATED VALVES AND PINPING UP TO PIPING MAIN TEES AND CAP AT DEMOLITION TERMINATION. REFER TO SHEET MD100 FOR MORE DETAIL. REFER TO STRUCTURAL DRAWINGS FOR REMOVAL OF PADS FOR BOTH CHWP-6 AND THE EXISTING PAD THAT WAS INSTALLED
FOR A FUTURE CHWP-7.
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021- 05-17
DESIGNER OF RECORD: JEFFREY ELSNER
STATE: COLORADO
REGISTRATION NO.: 43784
12 COOLING TOWER SUMPS ARE A CONFINED SPACE - ENTRY PERMIT IS REQUIRED.
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
0 CONSTRUCTION DOCUMENTS 07/22/2021
E E.5 F G J H
M301
M301
(E)CT-2
(E)CT-1
(E)CT-3
(E)10" CWR
(E)12" CWS(E)10" CWS
(E)12" CWR
(E)10" CWS
(E)10"
(E)8"
(E)10"
(E)12" CWR
(E)10" CWR
(E)8" (E)6"
(E)10"
(E)EF-2 2
EXISTING AHU-1 OA PLENUM
© 2021 making a difference through engineering
SM
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
Denver // Phoenix
RMH Group project number www.rmhgroup.com
Mechanical • Electrical Industrial • Sustainability
20440
KEY PLAN
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.7 /2
/2
:4
:3
A
M
1/4" = 1'-0"
MECHANICAL PIPING ROOF -
REMOVAL
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL CHILLED
WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
MD202
07/22/21
APB
MJ
JE
2019063.02
DRAFT CONSTRUCTION DOCUMENTS
KEY NOTESSHEET NOTES
1. LIGHT LINE WEIGHT INDICATES EXISTING. HATCHING INDICATES DEMOLITION.
2. COORDINATE WITH CONTRACTING OFFICER PRIOR TO DISPOSING OF ANY REMOVED MECHANICAL
MATERIALS OR EQUIPMENT.
3. REPAIR ALL SURFACES AND FINISHES DAMAGED DUE TO DEMOLITION OR CONSTRUCTION TO MATCH
EXISTING CONDITIONS.
4. EXISTING EQUIPMENT AND PIPING SHOWN ON THIS DRAWING ARE BASED ON RECORD INFORMATION PROVIDED IN PART BY OTHERS. THE CONTRACTOR IS RESPONSIBLE FOR FIELD VERIFICATION OF EXISTING CONDITIONS PRIOR TO STARTING WORK AND SHALL NOTIFY THE CONTRACTING OFFICER
OF ANY DISCREPANCIES FOR RESOLUTION.
5. COORDINATE WITH PLANT OPERATORS BEFORE CUTTING, SHUTTING OFF VALVES, OR SHUTTING
DOWN EQUIPMENT OR SYSTEMS AT LEAST SEVEN DAYS BEFORE PERFORMING WORK.
6. COORDINATE DEMOLITION WORK WITH CONTRACTING OFFICER PRIOR TO CONSTRUCTION TO
DETERMINE WORK REQUIRED DURING OFF HOURS OR WEEKENDS.
7. CONTRACTOR SHALL NOT REMOVE ANY SYSTEM FROM SERVICE BEFORE COORDINATING WITH
CONTRACTING OFFICER.
8. CONTRACTOR SHALL SUBMIT A DETAILED SCHEDULE PRIOR TO BEGINNING ANY DEMOLITION IN THE
CHILLER PLANT. THE SCHEDULE SHALL INCLUDE DURATION OF ALL PLANNED OUTAGES, AND
IDENTIFY THE DATE WHEN A TEMPORARY CHILLER WILL NO LONGER BE NEEDED. SEE SHEETS M100, M200, AND M210 FOR TEMPORARY CHILLER INFORMATION AND NEW WORK THAT IS REQUIRED PRIOR
TO SOME OF THE DEMOLITION SHOWN ON THIS SHEET.
0' 2' 4' 8' 16'
1/4"=1'-0"
1'
SCALE: 1/4" = 1'-0"
MECHANICAL PIPING ROOF REMOVAL PLAN
1 EXISTING ABANDONED REFRIGERANT VENT DISCHARGE. DEMOLISH GOOSE NECK FITTING, SEE M202
FOR NEW WORK TO EXTEND THIS VENT UP ABOVE SCREEN WALL.
2 EXISTING TWO SPEED EXHAUST FAN SHOWN TO REMAIN. NOTE THAT SCOPE SHOWN IS FOR BASIS OF DESIGN TRANE CHILLER. IF JOHNSON CONTROLS CHILLER IS SELECTED THIS FAN MUST REPLACED
WITH THE ALTERNATE FAN AS SCHEDULED ON M600
3 REFER TO STRUCTURAL DRAWINGS FOR DETAILS OF ANY REMOVAL AND DEMOLITION OF COOLING
TOWER SUPPORTS AND DUNNAGE.
4 REMOVE EXISTING MOTORIZED COOLING TOWER ISOLATION VALVE AND RETAIN FOR FUTURE USE.
5 EXISTING MOTORIZED COOLING TOWER ISOLATION VALVE TO REMAIN, PROTECT AND SUPPORT VALVE
DURING CONSTRUCTION. IF VALVE MUST BE REMOVED TO ALLOW CLEARANCE TO INSTALL THE
COOLING TOWER, REINSTALL VALVE IN THE SAME LOCATION.
6 12" CONDENSER WATER RETURN FROM CHILLER PLANT BELOW UP TO COOLING TOWERS. SEE MD201
FOR CONTINUATION BELOW
7 12" CONDENSER WATER SUPPLY FROM TOWERS DOWN TO CHILLER PLANT BELOW, SEE MD201 FOR
CONTINUATION.
8 REMOVE EXISTING, ABANDONED, REFRIGERANT VENT FROM ROOF TO TOP OF WALL.
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021- 05-17
DESIGNER OF RECORD: JEFFREY ELSNER
STATE: COLORADO
REGISTRATION NO.: 43784
9 RETAIN AND RE-USE EXISTING PIPE SUPPORTS IF POSSIBLE, SEE M202 FOR NEW PIPE ROUTING IN
SAME LOCATION.
10 COOLING TOWERS ARE A CONFINED SPACE - ENTRY PERMIT IS REQUIRED.
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
0 CONSTRUCTION DOCUMENTS 07/22/2021
A
B
C
D
E
1 2 3 4 5
THESE DOCUMENTS ARE FOR INTERIM REVIEW AND ARE NOT FOR
REGULATORY APPROVAL, PERMITTING, OR CONSTRUCTION.
DATE: 2021 - 06 - 03
DESIGNER OF RECORD:
STATE:
REGISTRATION NO.:
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203
518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.
P
M
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL
CHILLED WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
07/22/21
2019063.02
CONSTRUCTION DOCUMENTS
12600 West Colfax Avenue, Suite A-400
Lakewood, Colorado 80215
Phone 303-239-0909
RMH Group project number
© 2021www.rmhgroup.com making a difference through engineering
Mechanical • Electrical Industrial • Sustainability Denver // Phoenix
SM
20440
JEFFREY ELSNER
PENNSYLVANIA
43784
A 100% DRAFT CDS FOR CLIENT REVIEW 04/19/21
B 100% FINAL CDS FOR CLIENT REVIEW 05/17/21
0 CONSTRUCTION DOCUMENTS 07/22/21
M100
MECHANICAL PIPING
FLOW DIAGRAM
JE
APB
MJ
E E.5 F G J H
M300
M301
M300
M300
M300
CWP-1
CWP-2 CWP-3 CWP-4
CH-3
CH-2
CH-1
CHWP-1 CHWP-2 CHWP-3
4 4 4
4 4 4
EXISTING MCC
5' - 6 3/8"
2' - 6 3/8"
3' - 5 1/16"
5' - 4 15/16" 4' - 11 1/16"
3'
/8
3' - 2 5/8"
AHU-1RS-2RS-1
6 6
10 10
8" CHWR
8" CHWS
M300
(E)12" CWS
4'
/8
© 2021 making a difference through engineering
SM
12600 West Colfax Avenue, Suite A-400 Lakewood, Colorado 80215 Phone 303-239-0909
Denver // Phoenix
RMH Group project number www.rmhgroup.com
Mechanical • Electrical Industrial • Sustainability
20440
KEY PLAN
1 2 3 4 5 6
A
B
C
D
E
1 2 3 4 5 6
N
DRAWN BY:
CHECKED BY:
DATE:
SCALE:
DESIGNED BY:
EYP PROJECT NUMBER :
# Revision Date
201 Fuller Rd.
5th Fl.
Albany, NY 12203 518 795 3800 eypae.com
Copyright ©
EYP, Inc.
EYP, Inc.7 /2
/2
:4
:0
A
M
1/4" = 1'-0"
MECHANICAL EQUIPMENT &
CLEARANCE PLAN
INDEPENDENCE NATIONAL
HISTORIC PARK CENTRAL CHILLED
WATER PLANT
115 S, 3rd St. Philadelphia, PA 19106
NATIONAL PARK
SERVICE
M200
07/22/21
APB
MJ
JE
2019063.02
DRAFT CONSTRUCTION DOCUMENTS
0' 2' 4' 8' 16'
1/4"=1'-0"
1'
SCALE: 1/4" = 1'-0"
MECHANICAL PIPING EQUIPMENT & CLEARANCE PLAN
SHEET NOTES
1 40" CHILLER VSD CLEARANCE PER NEC. KEEP AREA CLEAR OF OTHER EQUIPMENT OR PIPING FROM
FLOOR TO 12" ABOVE TOP OF VSD.
KEY NOTES
2 TUBE PULL CLEARANCE. KEEP AREA CLEAR OF EQUIPMENT AND PIPING NOT ASSOCIATED WITH THE CHILLER. ALL ISOLATION VALVES SHALL BE INSTALLED ABOVE THIS CLEARANCE, REFER TO SECTIONS
ON SHEET M300
3 CHILLER CONTROL PANEL CLEARANCE. KEEP AREA CLEAR OF PIPING AND EQUIPMENT.
4 MAINTAIN AT LEAST 3 FEET OF CLEARANCE AROUND EQUIPMENT FOR MAINTENANCE ACCESS.
1. LIGHT LINE WEIGHT INDICATES EXISTING. HEAVY LINE WEIGHT INDICATES NEW CONSTRUCTION.
2. REPAIR ALL SURFACES AND FINISHES DAMAGED DUE TO DEMOLITION OR CONSTRUCTION TO MATCH
EXISTING CONDITIONS.
3. EXISTING EQUIPMENT AND PIPING SHOWN ON THIS DRAWING ARE BASED ON RECORD INFORMATION PROVIDED IN PART BY OTHERS. THE CONTRACTOR IS RESPONSIBLE FOR FIELD VERIFICATION OF EXISTING CONDITIONS PRIOR TO STARTING WORK AND SHALL NOTIFY THE CONTRACTING OFFICER
OF ANY DISCREPANCIES FOR RESOLUTION.
4. THIS PLAN SHOWS PIPING AND EQUPMENT BELOW 12' AFF. SEE SHEET M201 FOR PIPING ABOVE THAT LEVEL, ALSO REFER TO M300 SHEETS FOR SECTIONS SHOWING DETAILS THAT ARE DIFFICULT TO
DISPLAY IN A PLAN VIEW.
5 NEC REQUIRED EGRESS CLEARENCE FROM MCC-1. MAINTAIN A MINIMUM 30" WIDE BY 90"
TALLPASSAGEWAY FREE FROM ALL PERMANENT EQUIPMENT AND PIPING. PASSAGE SHALL EXTEND BOTH DIRECTIONS FROM MCC-1 TO THE EXIT DOORS FROM THE PLANT, INCUDING BEHIND CHILLERS #1
AND #2 AS SHOWN.
6 REFER TO STRUCTURAL DRAWINGS FOR DETAILS RELATED TO CHILLER AND PUMP EQUIPMENT PADS.
7 INSTALL NEW REFRIGERANT MONITOR SYSTEM PER SCHEDULE ON SHEET M600. RE-USE EXISTING
SENSOR TUBES AND RECONNECT HARDWIRED CONTROL AND ALARM.
8 LOCATION OF EXISTING PLANT CONTROLLER AND JACE PANELS. REFER TO CONTROLS SHEET FOR
SCOPE OF CONTROLS WORK.
9 INSTALLATION PATH FOR NEW CHILLERS THROUGH OVERHEAD DOOR. FACTORY AUTHORIZED PARTY SHALL DISMOUNT THE CHILLER VARIABLE…
This is the start of the file's text. The full file is on GovTribe.