This scope of work document outlines requirements for the fabrication of forty-three large-scale aluminum wind chime assemblies for the Tower of Voices memorial at Flight 93 National Memorial in Pennsylvania. The selected contractor will retrieve government-furnished materials from Illinois, refine existing chime designs, fabricate components, assemble and test chimes, and deliver the completed assemblies by June 2020. Key requirements include developing node bar, sail, and dampening material designs; conducting component and factory acceptance testing; and coordinating with National Park Service, families of victims, and designers. The contract will be awarded through solicitation 140P2020R0034 by the National Park Service, with a period of performance from February to November 2020.
View the file
Other files for this federal contract opportunity
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FLIGHT 93 NATIONAL MEMORIAL
SOMERSET COUNTY, PA
TOWER OF VOICES
FLNI 200729
Wind Chime Fabrication Completion
Scope of Work
NATIONAL PARK SERVICE (NPS)
DENVER SERVICE CENTER (DSC)
January 2020
02-02-2020 | Page 2 of 15
Table of Contents
PROJECT INTRODUCTION
1.1 OVERVIEW OF PROJECT SCOPE
1.2 BACKGROUND
1.3 PROJECT STAKEHOLDERS
1.4 PROJECT LOCATIONS
1.5 SCHEDULE
1.6 INFORMATION AND MATERIALS PROVIDED BY NPS
PROJECT REQUIREMENTS
2.1 GENERAL REQUIREMENTS
2.1.1 PERFORMANCE REQUIREMENTS
2.1.2 PROJECT MEETINGS AND COORDINATION
2.2 DESIGN REQUIREMENTS
2.2.1 DOCUMENTATION
2.2.2 REVIEW AND APPROVAL PROCESS
2.3 FABRICATION REQUIREMENTS
2.3.1 TRANSFER OF GOVERNMENT FURNISHED MATERIAL
2.3.2 PRODUCT REQUIREMENTS
2.3.3 QUALITY CONTROL
2.3.4 TESTING
2.3.5 DELIVERY
2.3.6 PROJECT CLOSE-OUT AND WARRANTY
CONTRACT REQUIREMENTS
3.1 FEDERAL ACQUISITION REQUIREMENTS
3.2 SCHEDULE OF VALUES / PROGRESS PAYMENTS
ATTACHMENTS
02-02-2020 | Page 3 of 15
1.0 Project Introduction
Park Acronym and PMIS Number: FLNI 200729
Project Title: Tower of Voices
Project Drawing Number: N/A
1.1 OVERVIEW OF PROJECT SCOPE
This scope of work includes the fabricating, assembling, testing, and delivering forty-three (43)* large-scale aluminum wind chime assemblies for the Tower of Voices at the Flight 93 National Memorial. This scope includes advancing the existing prototype design through minor revisions to existing components as well as the development of new components as necessary to provide for complete functioning chime assemblies. The scope of work includes combining Government furnished materials with other materials, either fabricated per the design or procured commercial off the shelf products, into the final chime assemblies. The Fabrication Contractor shall retrieve the
Government furnished materials from Morton, Illinois and ship the materials to the Fabrication Contractor’s location.
Factory Acceptance Testing shall verify by demonstration that the 43 chimes functional performance and operational requirements have been achieved, by test equipment selected at the Contractor’s discretion. Contractor shall design the Factory Acceptance Test procedures in order to meet this objective and produce a written, detailed report describing and interpreting the results for review and approval by the Contracting Officer.
Design, testing, and fabrication actions are summarized in this scope of work for use in continued effort for final fabrication and delivery.
* Quantity of 43 represents 40 chime assemblies for the Tower of Voices plus three spare assemblies as described in the specifications.
1.2 BACKGROUND
The Flight 93 National Memorial is a National Park Service unit located in Somerset County, Pennsylvania where
United Flight 93 crashed on September 11, 2001. Development of the 2,200-acre park occurred through several phases. The Tower of Voices is the last major phase of work in the development of the Flight 93 National
Memorial. The tower is a monumental, 93-feet tall musical instrument that will hold 40 wind chimes, representing the 40 passengers and crewmembers on the plane. It is intended to be a landmark memorial feature near the entrance to the park and a living memorial in sound to remember the 40 through their ongoing voices.
Upon entering the park, visitors see the Tower of Voices that marks the gateway to the Memorial site and symbolically introduces the memorial theme. Rings of White Pine trees resonating from the tower, flowering
Hawthorn and Redbud trees, and some reforestation will partially screen this area from the site entrance from
State Route 30 and Approach Road. A paved walkway and a trail from a parking area winds its way through the pine trees to a raised clearing and plaza for the tower. Future trails will originate from the Tower to lead through the park.
The concrete tower structure and sitework are complete and eight prototype chime assemblies currently hang in the tower. The National Park Service installed the eight chimes currently in the tower prior to the dedication of the project site in September 2018. These chimes serve as a basic representation of chimes that will ultimately be in the tower. These eight chimes will be replaced when the chimes fabricated under this contract are delivered https://www.lawinsider.com/clause/factory-acceptance-testing
02-02-2020 | Page 4 of 15 and installed. The chimes consist of 8-inch outside diameter aluminum tubes with 1/2 inch thick walls and vary in length from 5 feet to 10 feet which produce various frequency sounds in a harmonic melody. Each chime consists of a chime tube, suspension components, striker, sail, fasteners, dampening material and tether. The total assembly length is a maximum of approximately 18 feet.
Additional information regarding the Tower of Voices is available on the park website at https://www.nps.gov/flni/getinvolved/tower-of-voices.htm.
1.3 PRINCIPAL STAKEHOLDERS
The following table summarizes the principal stakeholders related to the effort described in this scope of work.
Firm/Organization/Party Description/Role
Fabrication Contractor Complete fabrication of chime assemblies utilizing government furnished materials and designs in accordance with the requirements of this scope of work. Adjust design for final assemblies as necessary. Conduct testing to confirm performance/quality. Deliver chimes to Flight 93 National
Memorial.
Families of Flight 93 Family members of the passengers and crew of United Flight
93. The family members are critical team members and participate in decision making related to the final chime design.
National Park Foundation Nonprofit partner of the National Park Service providing support through private and partnership opportunities.
National Park Service – Flight 93
National Memorial
Steward of Flight 93 National Memorial, including the Tower of Voices.
National Park Service – Denver
Service Center
Project management and contracting office for the Tower of
Voices project.
Design Team Provide design support for existing design. Provide consultation for any design changes on final assembly. Provide calculations for material strength.
Chime Consultant Provide design support for existing design. Serve as an advisor for interpretation of testing results to date.
Chime Installer Install chimes in the Tower of Voices.
1.4 PROJECT LOCATIONS AND CONTACT INFORMATION
Until contract award, all communication shall be directed solely to the Contracting Officer and the Contract
Specialist. No contact with other stakeholders as described above shall occur until after contract award. The location and contact information below if provided for planning and coordination of work activities.
https://www.nps.gov/flni/getinvolved/tower-of-voices.htm
02-02-2020 | Page 5 of 15
Flight 93 National Memorial
Description: Tower of Voices project site
Address: 6424 Lincoln Highway
Stoystown, PA 15563
Point of Contact: Brad Thomas, Brad_Thomas@nps.gov, 714-329-5800
National Park Service – Denver Service Center
Description: Project Management and Contracting Office for Project
Address: National Park Service - Denver Service Center
12795 West Alameda Parkway
Post Office Box 25287
Denver, Colorado 80225
Points of Contact:
Contracting Officer (CO): Darrin Knapp 303-969-2055, Darrin_Knapp@nps.gov
Contract Specialist (CS): Kurt Ulmer, 303-969-2587, Kurt_Ulmer@nps.gov
Project Manager (PM) and Alternative Contracting Officer’s Representative (COR): Paul Rothgery, 303-
987-6685, Paul_Rothgery@nps.gov
Project Specialist (PS) and Contracting Officer’s Representative (COR): Shane Friese, 303-969-2302, Shane_Friese@nps.gov
Morton, Illinois
Description: Location of chime materials and existing fabricated components. Fabricator will retrieve the
Government furnished materials from this location and transfer the materials to the fabricator’s location immediately upon contract award.
Address: To be provided upon contract award
Point of Contact: To be provide upon contract award
1.5 SCHEDULE
Period of Performance is from February 2020 to November 2020. Complete work in this RFP according to following schedule: The chimes must be delivered to the Flight 93 Memorial no later than June 19, 2020.
The Fabrication Contractor shall provide a schedule prior to the contract Kickoff Meeting that includes the following milestones as a minimum. Additionally, the Fabrication Contractor shall include any critical milestones needed based on experience in this field of work.
1. Contract kickoff meeting
2. Retrieval/Transfer of Government Furnished Materials
3. Assembly of current prototype design at fabricator’s location mailto:Brad_Thomas@nps.gov mailto:Brad_Thomas@nps.gov
02-02-2020 | Page 6 of 15
4. Fabrication of chimes components (including any finish coatings)
5. Assembly of chimes
6. Factory acceptance testing and inspection of each chime
7. Delivery of all materials to the Tower of Voices site
The purpose of the schedule is to ensure adequate planning, coordination and scheduling to meet the delivery date requirement. The schedule shall consider and include coordination with design team and chime consultant as described earlier in this scope of work. Further, the schedule shall consider review and inspection by the National
Park Service and their representatives. The schedule will be monitored during the performance of the contract to ensure the contract remains on schedule. If at any point the schedule is not as provided the contractor shall immediately notify the Government and provide a recovery plan.
The Fabrication Contractor shall ensure project schedule includes own work and Subcontractor work.
Project schedule shall show sequence and interdependence of activities required for complete performance of work. Fabrication Contractor shall ensure work sequences are logical and project schedule shows a coordinated work plan. Proposed durations assigned to each activity shall be Fabrication Contractor's best estimate of time required to complete activity, considering scope and resources planned.
The chimes are required to be delivered to the site No Later Than (NLT) June 19, 2020.
The Fabrication Contractor shall provide support for the installation contractor for any final adjustments during installation onsite. This support may include onsite and/or remote support.
1.6 INFORMATION AND MATERIALS PROVIDED BY NPS
The following documents are contained in section 4.0 ATTACHMENTS of this scope of work.
A. Inventory list of Government furnished materials
B. Specification section 05 05 16 - POWDER COATINGS
C. Specification section 05 70 00 – DECORATIVE METAL
D. Specification section 11 62 18 - WIND CHIMES
E. Design files and shop drawings from prototype testing phase++
F. Tuning Table for Chimes
G. Prototype Testing Results
H. Tower of Voices Construction Drawing Sub Sheet COVER (Sheet 1A of 75)
I. Tower of Voices Construction Drawing Sub Sheet A4.04 (Sheet 43A of 75)+
J. Tower of Voices Construction Drawing Sub Sheet A4.07 (Sheet 46A of 75)+
K. Tower of Voices Construction Drawing Sub Sheet A4.08 (Sheet 47A of 75)+
L. As-constructed documents for the Tower of Voices concrete
M. Scope of Work (SOW)
+ These drawings were provided under the construction contract for the Tower of Voices to provide a general depiction of how the chimes will be suspended in the Tower. With the exception of length and diameter, these drawings do not reflect chime design characteristics and shall only be used as a general reference for how the chimes will be oriented in the Tower.
++Design files contain references to multiple sail designs. Sail “C”(dual air foil) is the design that shall be used as the basis of design for completion of the final chime assemblies.
02-02-2020 | Page 7 of 15
2.0 PROJECT REQUIREMENTS
2.1 GENERAL REQUIREMENTS
2.1.1 CHIME PERFORMANCE REQUIREMENTS
In general, the final wind chime assemblies delivered to Flight 93 National Memorial need to operate under various wind speeds and directions under a variety of environmental conditions. The target performance objectives are provided below:
a. Sound Level Minimum: Approximately 45-60 A-weighted decibels (dBa) at plaza (visitor) elevation
b. Minimum Wind Speed Range to Activate: Approximately 7-10 miles per hour (speed inside tower)
c. Fundamental Tones audible in accordance with the tuning table provided in this section.
Refer to specification section 11 62 18 - WIND CHIMES for additional information and requirements.
The aluminum chime tubes are cut and tuned in accordance with the tuning table below:
Chime Location Note Frequency
Approx.
Tube
Length Chime
Location Note Frequency
Approx.
Tube
Length
A1 D 149 112 5/16” E1 E 334 75"
A2 C 535 59 1/4" E2 E 330 75 7/16"
A3 G 198 97 7/16" E3 G 396 68 7/8"
A4 G 396 68 7/8" E4 D 297 79 9/16"
A5 C 264 84 3/8" E5 F# 372 71 1/16"
B1 C 267 83 7/8" F1 F# 367 71 9/16"
B2 C 528 59 5/8" F2 E 334 75"
B3 E 330 75 7/16" F3 B 495 61 5/8"
B4 F# 372 71 1/16" F4 D 293 80 1/16"
B5 E 334 75" F5 B 495 61 5/8"
C1 D 293 80 1/16" G1 F# 372 71 1/16"
C2 B 495 61 5/8" G2 D 297 79 9/16"
C3 E 334 75" G3 B 501 61 1/4"
C4 F# 367 71 9/16" G4 G 198 97 7/16"
C5 E 330 75 7/16" G5 C 528 59 5/8"
D1 E 330 75 7/16" H1 G 396 68 7/8"
D2 G 396 68 7/8" H2 C 264 84 3/8"
D3 F# 372 71 1/16" H3 C 528 59 5/8"
D4 E 330 75 7/16" H4 C 264 84 3/8"
D5 G 396 68 7/8" H5 B 501 61 1/4"
02-02-2020 | Page 8 of 15
2.1.2 PROJECT MEETINGS AND COORDINATION
Kickoff Meeting
The kickoff meeting will occur at the Fabrication Contractor’s facility after award of the contract. Representatives from the National Park Service, the design team, the chime consultant, and possibly representatives from the
Families of Flight 93 and the National Park Foundation will participate either in person or remotely. The purpose of this meeting is to review the scope, schedule, and technical approach for completion and delivery of the chimes.
The meeting will be scheduled with the Fabrication Contractor upon award of the contract.
Prototype Demonstration
The prototype demonstration will occur at the Fabrication Contractor’s facility after the conveyance of the
Government furnished materials and procurement of any additional materials necessary to construct one complete chime assembly in accordance with the prototype design and any modifications coordinated prior to the demonstration. The demonstration shall confirm the Fabrication Contractor’s understanding of the prototype design as well as provide the means for the Fabrication Contractor to identify any improvements and/or modifications recommended for the final fabrication assemblies. Representatives from the National Park Service, the design team, the chime consultant, and possibly representatives from the Families of Flight 93 and the National
Park Foundation will participate either in person or remotely. The Fabrication Contractor may use artificial wind production in lieu of natural wind for this demonstration. Artificial wind production method shall be submitted to the Contracting Officer for review and approval prior to the demonstration.
The Fabrication Contractor shall schedule this demonstration. This demonstration shall be indicated on the
Fabrication Contractor’s project schedule.
Factory Acceptance Testing
The factory acceptance testing will occur at the Fabrication Contractor’s facility upon completion of all of the chime assemblies. The testing will demonstrate quality of product finishes, performance of the chimes, and the completeness of each assembly. The Fabrication Contractor shall submit proposed testing methods to the
Contracting Officer for review and approval prior to the testing activities.
Representatives from the National Park Service, the design team, the chime consultant, and possibly representatives from the Families of Flight 93 and the National Park Foundation will participate either in person or remotely for this testing. The Fabrication Contractor shall notify the Contracting Officer of the testing a minimum of two weeks prior to the scheduled day(s) of testing. The factory acceptance testing shall be indicated on the Fabrication Contractor’s project schedule.
Weekly Fabrication Coordination Conference Calls
Fabrication contractor shall lead weekly telephone conference calls with the National Park Service and including other project team members. The fabrication coordination conference calls shall include updates to following meeting agenda items:
02-02-2020 | Page 9 of 15
▪ Approval of minutes of previous meetings
▪ Design modifications
▪ Work in progress and projected in the next two weeks
▪ Review of off-site fabrication and delivery
▪ Overall fabrication schedule update
▪ Status of project record drawings/documents
Digital Images for Coordination Discussions
Provide a minimum of five (5) digital images per week documenting fabrication activities. Transmit the digital images to the Contracting Officer’s Representative prior to the weekly fabrication coordination meetings. Provide a written description for each image sent. Description shall include the date of the image, a list of representative components shown in the image, and a comment regarding how the picture coordinates with the weekly fabrication activities.
Pre-Installation Conference
The Fabrication Contractor shall participate in a pre-installation conference call led by the National Park
Service. This call will occur prior to delivery of the chime to Flight 93 National Memorial. Participants will include the Fabrication Contractor, the National Park Service, and the installation contractor. The conference call will address the following topics:
▪ Delivery schedule
▪ Unloading and material handling procedures
▪ Chime installation procedures, including personnel safety and protection of existing features
▪ Initial chime cleaning and adjustment after installation
2.2 DESIGN REQUIREMENTS
The elements of the chime assembly below require refinement or completion of design details. Development, revision, and completion of the details is a collaborative effort between the Fabrication Contractor and the design team. The Fabrication Contractor will develop shop drawings for the assembly components. The design team will provide strength of material calculations and feedback related to the component designs.
1. Node bar: This component is the attachment of the chime tube to the internal suspension and striking assembly. Prototype testing to date demonstrated that a two-point connection contributes to undesired rotation at the nod bar. Prototype testing also demonstrated that a four-point (cross) connection may produce dampening of the fundamental tone. Refinement of this component shall advance the design of the four-point (cross) connection in order to minimize dampening caused by the connection. The
Fabrication Contractor, through coordination with the design team, shall develop design details of the refined node bar for approval.
2. Sail connection locations: The upper and lower attachment locations on the sail were fabricated at adjustable mechanisms during prototype testing in order to determine the optimal locations for connection. The Fabrication Contractor, through coordination with the design team, shall develop a fixed/secure final connection detail for approval prior to fabrication.
3. Rigid connections in lieu of universal joints: Prototype assemblies were tested with as many as six universal joints along the suspension system. Prototype test results yielded that optimal wind response required a minimum of three universal joints within the suspension system. Prototype testing assemblies used temporary rigid connections in lieu of universal joints. The Fabrication Contractor, through
02-02-2020 | Page 10 of 15 coordination with the design team, shall develop the final connection details for a rigid assembly at locations where universal joints are no longer needed.
4. Universal joints: The National Park Service is conducting material failure testing of universal joints proposed for use on the chime assemblies. If the test results determine that the size or materials of the universal joints is not suitable for use in the chime assembly due to load requirements, then alternative sizes or materials may be introduced for inclusion in the chime assemblies. Size and/or connection details associated with alternative universal joints may result in modifications to the chime assemblies.
The Fabrication Contractor, through coordination with the design team, shall develop design revisions to accommodate changes to the chime assemblies.
5. Dampening material: Prototype testing confirmed that polyurethane sleeves for the strikers provide for dampening necessary to avoid metal on metal contact between the striker and the chime. The polyurethane sleeves were tested in various durometers. Additional effort is necessary to finalize the selection and design of the polyurethane sleeve. Striker masses for different size chimes may require different durometers of polyurethane for optimum chime sound. The Fabrication Contractor, through coordination with the design team, shall develop final dampening material design for incorporation into the final chime assemblies.
6. Striker mass revisions: Prototype testing identified that varying the striker mass weight provides for variations in the chime performance. The Fabrication Contractor, through coordination with the design team, shall develop final sizing of striker masses for incorporation into the final chime assemblies.
Fabrication Contractor shall plan for fabrication of revised strikers for as many as all forty-three (43) chime assemblies. Reuse of the fabricated strikers with minor modifications will be acceptable if demonstrated that the size of the striker mass is appropriate.
7. Other design revisions as necessary: Other design revisions may be needed in order to accommodate the design revisions described above and/or any other revisions determined necessary by the project team.
2.2.1 DOCUMENTATION
Shop drawings, product data, and as-constructed record drawings are to be provided in a comprehensive and legible format. All dimensions are to be in English units. Electronic files for shop drawings and as-constructed drawings are to be provided in both native and PDF file formats.
▪ Product Data: Collect information in single submittal for each element of fabrication and/or type of product proposed for use. Products submitted and approved for use during prior phases of design do not require submittal/review.
▪ Shop Drawings: Prepare project-specific information, drawn accurately to scale. Shop drawings for previously components approved during prior phases of design and approved for incorporation into the final design do not need to be submitted for review/approval. However, shop drawings for all components are to be included in a comprehensive set of final fabrication drawings.
2.2.2 REVIEW AND APPROVAL PROCESS
Coordination: Coordinate shop drawing preparation and processing with fabrication activity performance.
Review drawings for legibility, accuracy, completeness, and compliance with Contract Documents.
1. Coordinate shop drawings with fabrication, purchasing, testing, delivery, other submittals, and related activities requiring sequential activity.
2. Partial shop drawings are not acceptable, will be considered non-responsive, and will be returned without review.
02-02-2020 | Page 11 of 15
Processing Time: Allow enough time for submittal review and re-submittals. Start review when Contracting
Officer or Contracting Officer’s Representative confirms receipt of submitted shop drawings and/or product data.
After Contracting Officer completes review, an email is sent to the Fabrication Contractor indicating submittal has been processed. Contract time extensions will not be authorized if submittals are not transmitted with enough time to permit processing, including re-submittals. Allow 10 days for review of each submittal.
Contracting Officer will review each submittal, generate comments on corrections or modifications required, and indicate appropriate action on Electronic Submittal Review Form in one of three ways:
1. Approved: Acceptable with no corrections required.
2. Approved with Notations: Minor corrections or clarifications required. Comments are clear and no further review required. Fabrication Contractor shall address review comments when proceeding with work.
3. Disapproved - Resubmit: Rejected for not according with contract or requiring major corrections or clarifications. Contracting Officer will identify reasons for disapproval. Fabrication Contractor shall revise and resubmit with changes clearly identified.
Use for Fabrication
Use only final submittals marked with Approved or Approved with notations. Ensure notations are incorporated and, at a minimum, keep one copy of final approved submittal on site during fabrication.
2.3 FABRICATION REQUIREMENTS
2.3.1 TRANSFER OF GOVERNMENT FURNISHED MATERIAL
The Fabrication Contractor is responsible for the retrieval of the Government furnished material from Fugate Inc. in
Morton, Illinois, packaging/protection of the Government furnished materials, and the related transportation of the
Government furnished materials to the Fabrication Contractor’s facility.
All hauling activities shall comply with legal and local load restrictions.
2.3.2 PRODUCT REQUIREMENTS
Refer to the inventory of Government furnished materials, related design files, and specification sections for specific product requirements. The following requirements also apply to the products/materials for chime assembly components:
▪ Where a product is specified only by a manufacturer name and model number/brand name, Fabrication
Contractor shall use only that model/brand product, unless a proposed equal is demonstrated by the
Fabrication Contractor.
▪ Where the properties of a product are specified by description and/or with performance criteria, Fabrication
Contractor shall use products that comply with description and/or performance criteria.
▪ Where manufacturers are listed for a particular component, Fabrication Contractor shall use a product made by one of those manufacturers that also complies with other requirements.
02-02-2020 | Page 12 of 15
▪ Where actual brand name products are not identified by either Contracting Officer or Fabrication Contractor, Fabrication Contractor shall identify products to be used.
2.3.3 QUALITY CONTROL
Fabrication Contractor is responsible for quality of work. Inspect and test work as needed to ensure quality of materials, workmanship, construction, and finish, and to ensure functional performance is compliant with project requirements and approved design documents.
Fabrication Contractor accepts ultimate responsibility, liability and duty to control quality of services provided to the Government. Fabrication Contractor shall be responsible for professional quality, technical accuracy, and coordination of designs, drawings, specifications, and other services furnished by Fabrication Contractor, their
Employees, Agents, Assignees, and Subcontractors under the contract. Fabrication Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its designs, drawings, specifications, and other services.
Fabrication Contractor shall demonstrate existence of a Quality Control (QC) system used for work submitted to
NPS. Fabrication Contractor and Subcontractors shall use this QC system and, at a minimum, include:
▪ Coordination of complete chime assembly with physical constraints of the Tower of Voices.
▪ Verification that documents to be submitted are accurate and correct.
▪ Verification that products meet the performance and product material requirements of the contract documents.
• Verification of calibration of measuring devices, laboratory equipment, and instruments at established intervals against certified standards according to National Bureau of Standards (NBS) requirements.
On completion of testing, inspecting, and similar services, repair damaged construction and restore substrates and finishes. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible.
The chime Fabrication Contractor’s quality control program shall ensure that all materials, processes, and components, including raw materials, are in compliance with shop drawings and documents submitted to and accepted by the Contracting
Officer. In addition to the requirements of the Quality Requirements specification section, the following elements shall be included in the QA/QC plan:
a. Traceability of components and materials
b. Allow all incoming material to be checked for engineering compliance and completeness of material certifications.
c. Define and identify committed and segregated material stock for specific use on the Project.
d. Require certifications for all carbon and stainless steels and aluminum materials.
e. Require manufacturer’s Certificate of Compliance with material standards indicated in the shop drawings for all fastening materials listed in the Bill of Materials.
f. Processes and manufacturing
g. Testing inspections and corrective actions
h. Document control
i. Packaging and storage
j. Shipping and handling
02-02-2020 | Page 13 of 15
2.3.4 TESTING
Refer to the testing information completed to date as included with this scope of work. Additional detail of design and prototype testing history will be provided during the project kickoff meeting.
Component Testing
Fabrication Contractor shall develop a component testing plan for the testing of all newly designed or modified components. Testing shall demonstrate that the individual component aligns with the performance requirements described in the contract documents.
Factory Acceptance Testing
The Fabrication Contractor shall complete factory acceptance testing prior to shipment of the chime assemblies to Flight 93 National Memorial. The testing shall verify by demonstration that the 43 chimes functional performance and operational requirements have been achieved, by test equipment selected at the Fabrication
Contractor’s discretion. Contractor shall design the Factory Acceptance Test procedures in order to meet this objective and provide a written, detailed report of all test results. For the purpose of this testing, the chimes may be manually activated if natural wind forces are unavailable.
2.3.5 DELIVERY
The Fabrication Contractor is responsible for the delivery of the material to a specified secure location at Flight 93.
The Government will be present at time of delivery to inspect for acceptance. Unloading of the delivered materials at the site will be by others. All materials accepted will be paid for and the Fabrication Contractor will be relieved of any liability should the materials be lost or damaged after acceptance.
Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft. Comply with manufacturer's written instructions.
Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.
Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.
Inspect products on delivery to ensure compliance with the Contract Documents and to ensure that products are undamaged and properly protected.
All hauling activities shall comply with legal and local load restrictions.
2.3.6 PROJECT CLOSEOUT AND WARRANTY
As-Constructed Drawings
Provide approved electronic fabrication drawings upon completion of Factory Acceptance Testing.
Provide as-constructed drawings on 2 CD-ROMS (Compact Disc-Read Only Memory), each with drawing files in both PDF (Portable Document File) and native file formats.
02-02-2020 | Page 14 of 15
Cleaning
Before scheduling final acceptance testing, thoroughly clean the chime assemblies to remove any dirt, debris, stains, etc. from the finished product.
Spare Parts
Spare parts/materials shall be provided in accordance with the specification requirements.
Operation and Maintenance (O&M) Data: Prior to final inspection, provide two electronic copies on CD-
ROMS with O&M data to Contracting Officer. Data shall include Fabrication Contractor instructions and recommendations for the proper care and maintenance of the chime assemblies.
Warranty
Fabrication Contractor shall provide a minimum warranty of one year. The warranty period will commence upon delivery and acceptance at the Flight 93 National Memorial. Refer to contact clauses for additional information regarding warranty requirements.
3.0 CONTRACT REQUIRMENTS
3.1 FEDERAL ACQUISITION REQUIREMENTS
Refer to Federal Acquisition Regulation (FAR) clauses included with the contract.
3.2 SCHEDULE OF VALUES / PROGRESS PAYMENTS
After contract award and before the Kickoff Meeting, submit schedule of dollar value based on Contract Price
Schedule. Breakdown each lump-sum item into component parts of design, material procurement, fabrication, or testing activities for which progress payments may be requested. Total costs for component parts of work shall equal contract line item amount for that lump-sum item. Contracting Officer may request data to verify accuracy of dollar values. Include overhead and profit in total dollar value in component parts of work for each lump-sum item.
Total cost of items shall equal contract sum. Schedule of Values will form basis for progress payments.
Before first progress payment is processed, Fabrication Contractor and Contracting Officer shall agree on an acceptable Schedule of Values. A cost loaded project schedule approved by the Contracting Officer is an acceptable substitute for a schedule of values.
4.0 ATTACHMENTS
02-02-2020 | Page 15 of 15