Attachment_2_Contract_Tank_Table.pdf

PDF 107 KB Posted

Attached to
Underground Tank Inspection and Testing Services Federal contract opportunity
Solicitation number
140P1424Q0058
Issued by
Department of the Interior National Park Service Intermountain Region

About this file

This document appears to be an attachment containing a list of underground storage tanks and associated inspection and testing requirements for various facilities in Yellowstone National Park. The attached table provides details on the tank locations, sizes, construction materials, required annual inspections and testing (such as function tests, leak detector tests, and integrity tests), as well as the GPS coordinates for each tank location.

The information in this attachment is directly relevant to the federal contract opportunity titled "Underground Tank Inspection and Testing Services" with Solicitation Number 140P1424Q0058. This solicitation is being issued by the Department of the Interior National Park Service Intermountain Region for the provision of underground tank inspection and testing services at Yellowstone National Park. The key products and services required include performing the various annual and triennial inspections and tests outlined in the attachment on the listed underground storage tanks.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FACILITY ID ANNUALLY EVERY 3 YEARS (due 2024)

WY 5198 Canyon Bus Facility

2 ‐ 10,000 gal Fiberglass Tanks

44.740368 ‐110.498423

*Operator's Annual Inspection

*Function Test (6 Sensors)

*Mech. Line Leak Detector Test (2

Detectors)

* Integrity Test (2 Spill Bucket) (2

Turbine Sumps) (2 Dispensers)

WY 3012 Canyon Powerhouse

Gen. 1 ‐ 6,000 gal ST1‐P3 Steel

Tank

44.740364 ‐110.498168 *Operator's Annual Inspection

*Function Test (1 Sensor)

* Integrity Test (1 Spill Bucket) *

Cathodic Protection Test

WY 4283 Canyon Sewer Gen.

1 ‐1,000 gal ST1‐P3 Steel Tank

44.722857 ‐110.489149

*Operator's Annual Inspection

*Function Test (2 Sensors)

* Integrity Test (1 Spill Bucket)(1 Piping

Sump) * Cathodic Protection Test

WY 3007 East Entrance Fleet

1‐ 4,000 gal Dual Compartment

ST1‐P3 Steel Tank

44.488983 ‐110.005425 *Operator's Annual Inspection

*Function Test (1 Sensor)

* Integrity Test (2 Spill Bucket) *

Cathodic Protection Test

WY 5194 Grant Fleet Fuel

3 ‐ 10,000 gal Fiberglass Tanks

44.388841 ‐110.563444

*Operator's Annual Inspection

*Function Test (10 Sensors)

*Mech. Line Leak Detector Test (10

Detectors)

* Integrity Test (3 Spill Buckets)(3

Turbine Sumps)(4 Dispensers)

WY 3897 Grant Main Gen.

1‐ 6,000 gal ST1‐P3 Steel Tank

44.389952 ‐110.561279

*Operator's Annual Inspection

*Function Test (1 Sensor)

* Integrity Test (1 Spill Bucket) *

Cathodic Protection Test

WY 3006 Lake Fleet Fuel

2 ‐ 10,000 gal Fiberglass Tanks

44.562198 ‐110.397676

*Operator's Annual Inspection

*Function Test (6 Sensors)

*Mech. Line Leak Detector Test (2

Detectors)

* Integrity Test (2 Spill Buckets) (2

Turbine Sumps)(2 Dispensers)

WY 5007 Lake Government Gen

1 ‐ 6,000 gal ST1‐P3 Steel Tank

44.562146 ‐110.394762

*Operator's Annual Inspection

*Function Test (1 Sensor)

* Integrity Test (1 Spill Bucket) *

Cathodic Protection Test

WY 3013 Lake Clinic Gen.

1 ‐ 500 gal ST1‐P3 Steel Tank

44.550363 ‐110.402243

*Operator's Annual Inspection

*Function Test (1 Sensor)

* Integrity Test (1 Spill Bucket) *

Cathodic Protection Test

WY 3030 Madison Fleet

2 ‐ 6,000 gal ST1‐P3 Steel Tanks

44.646929 ‐110.858512

*Operator's Annual Inspection

*Function Test (2 Sensors)

* Integrity Test (2 Spill Buckets) *

Cathodic Protection Test

WY 4009 Madison Gen.

1 ‐ 4,000 gal ST1‐P3 Steel Tank

44.647263 ‐110.858518

*Operator's Annual Inspection

*Function Test (1 Sensor)

* Integrity Test (1 Spill Bucket)(1 Piping

Sump)* Cathodic Protection Test

WY 3750 Mammoth Fleet Fuel &

Waste Oil Tank

2 ‐ 5,000 gal Fiberglass Tanks

1 ‐ 4,000 gal ST1‐P3 Steel Tank

44.955611 ‐110.701875 *Operator's Annual Inspection

*Function Test (9 Sensors)

* Integrity Test (2 Spill Buckets) (2

Turbine/Piping Sumps)(4 Dispensers) *

Cathodic Protection Test (on waste oil tank)

WY 3031 Norris Fleet Fuel

1 ‐ 4,000 gal Dual Compartment

ST1‐P3 Steel Tank

1 ‐ 10,000 gal Fiberglass Tank

44.729642 110.693457

*Operator's Annual Inspection

*Function Test (4 Sensors)

*Mech. Line Leak Detector Test (1

Detector)

* Integrity Test (3 Spill Buckets)(1

Turbine Sump)(1 Dispenser)* Cathodic

Protection Test

WY 5192 Old Faithful Fleet

2 ‐ 10,000 gal Fiberglass Tanks

44.454358 ‐110.837621

*Operator's Annual Inspection

*Function Test (6 Sensors)

*Mech. Line Leak Detector Test (2

Detectors)

* Integrity Test (2 Spill Buckets)(2

Turbine Sumps) (2 Dispensers)

WY 3034 South Entrance Gen.

1 ‐ 4,000 gal ST1‐P3 Steel Tank

44.133918 ‐110.666649

*Operator's Annual Inspection

*Function Test (1 Sensor)

* Integrity Test (1 Spill Bucket) *

Cathodic Protection Test

WY 3027 South Entrance Fleet

1 ‐ 4,000 gal Dual Compartment

ST1‐P3 Steel Tank

44.133736 ‐110.666759 *Operator's Annual Inspection

*Function Test (1 Sensor)

* Integrity Test (2 Spill Buckets) *

Cathodic Protection Test

WY 3009 Tower Fleet Fuel

1 ‐ 4,000 gal Dual Compartment

ST1‐P3 Steel Tank

44.915078 ‐110.420945 *Operator's Annual Inspection

*Function Test (1 Sensor)

* Integrity Test (2 Spill Buckets) *

Cathodic Protection Test

MT 34‐08869 NORTHEAST‐FUEL

STATION 1 ‐ 4,000 gal Dual

Compartment

45.004622 ‐110.011659

MT 16‐08870 WEST ENTRANCE

FUEL STATION 1 ‐ 8,000 gal Dual

Compartment

44.656761 ‐111.095111

COORDINATES