NW33_E002_-_AD1_0001.pdf
PDF 397 KB Posted
- Attached to
- NIFC 300-JWH UPS REPLACEMENT - GAOA21
- Solicitation number
- 140L3722R0004
About this file
This one-line diagram depicts the electrical infrastructure upgrades required for an UPS replacement project at a National Interagency Fire Center facility in Boise, Idaho. The project involves replacing two UPS units and associated equipment to provide backup power for critical loads. Temporary generators and cabling will be used during the UPS replacement to ensure continuous power to critical panels. The solicitation seeks offers for the design and installation of the electrical system upgrades in accordance with the diagram and specifications. Offerors must coordinate all power outages with the agency and complete all changeovers between normal, temporary, and backup power sources within an eight hour window to minimize downtime.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2 2
AutoCAD SHX Text
208Y/120V CRITICAL LOAD PANEL UPSDBS (E)
AutoCAD SHX Text
AutoCAD SHX Text E002
AutoCAD SHX Text
ONE-LINE DIAGRAM
AutoCAD SHX Text 1000A
AutoCAD SHX Text
EXISTING CRITICAL LOADS
AutoCAD SHX Text G
AutoCAD SHX Text 150kW, 208Y/120V, TEMPORARY GENERATOR
AutoCAD SHX Text
EQUIPMENT AND FUEL PROVIDED BY CONTRACTOR
AutoCAD SHX Text 600A
AutoCAD SHX Text 450A
AutoCAD SHX Text 400A
AutoCAD SHX Text N
AutoCAD SHX Text E
AutoCAD SHX Text L
AutoCAD SHX Text G
AutoCAD SHX Text 600kW, 480Y/277V, 3 , 4WEMERGENCY GENERATOR (E)
AutoCAD SHX Text
EXISTING LOADS
AutoCAD SHX Text
480V EMERGENCY DISTRIBUTION SWITCHBOARD (E)
AutoCAD SHX Text
UPS INPUT
AutoCAD SHX Text
BYPASS INPUT
AutoCAD SHX Text
TO 480V MAIN SWITCHBOARD (E)
AutoCAD SHX Text
800A, 480V, 3-POLE TRANSFER SWITCH (E)
AutoCAD SHX Text
BATTERY UPS 1
AutoCAD SHX Text
UPS 1
AutoCAD SHX Text
UPS 2
AutoCAD SHX Text
BATTERY UPS 2
AutoCAD SHX Text
MB1 (N.C.)
AutoCAD SHX Text
MB2 (N.C.)
AutoCAD SHX Text
IB1 (N.C.)
AutoCAD SHX Text
IB2 (N.C.)
AutoCAD SHX Text
MIS (N.C.)
AutoCAD SHX Text
MBP (N.O.)
AutoCAD SHX Text
INPUT PANEL 400A, 480V, 3-PH, 3W, 35KAIC
AutoCAD SHX Text
(2) 3 #4/0, #2 GND, 2" C
AutoCAD SHX Text
3 #4/0, #4 GND, 2" C
AutoCAD SHX Text
3 #4/0, #4 GND, 2" C
AutoCAD SHX Text
4 #3/0, #3 GND
AutoCAD SHX Text
4 #3/0, #3 GND
AutoCAD SHX Text
3 #3/0, #6 GND, 2" C
AutoCAD SHX Text
3 #3/0, #6 GND, 2" C
AutoCAD SHX Text A. PROVIDE TWO UPS UNITS CONFIGURED FOR PARALLEL PROVIDE TWO UPS UNITS CONFIGURED FOR PARALLEL OPERATION. EACH UPS UNIT SHALL BE RATED 120 TO 125 kW. BASIS OF DESIGN FOR UPS SYSTEM IS EATON 93PM SERIES WITH 150kW FRAME AND 120kW RATING. PROVIDE EATON 93PM OR EQUAL BY ALTERNATE MANUFACTURER, INCLUDING BUT NOT LIMITED TO, APC, SCHNEIDER, LIEBERT, AND VERTIV. B. ALL CONDUCTORS SHALL BE COPPER UNLESS NOTED ALL CONDUCTORS SHALL BE COPPER UNLESS NOTED OTHERWISE.
AutoCAD SHX Text
GENERAL NOTES
AutoCAD SHX Text
SHEET NOTES
AutoCAD SHX Text
1. REPLACE EXISTING FUSES WITH 600V, 400A, CLASS RK1 FUSES. REPLACE EXISTING FUSES WITH 600V, 400A, CLASS RK1 FUSES. 2. CONDUCTORS ROUTED BETWEEN ADJACENT CABINETS USING CONDUCTORS ROUTED BETWEEN ADJACENT CABINETS USING FACTORY ACCESS OPENINGS. 3. EXTEND EXISTING CONDUCTORS AS NEEDED TO REACH NEW EXTEND EXISTING CONDUCTORS AS NEEDED TO REACH NEW EQUIPMENT. 4. PROVIDE KIRK-KEY OR EQUIVALENT MECHANICAL INTERLOCK PROVIDE KIRK-KEY OR EQUIVALENT MECHANICAL INTERLOCK FOR BYPASS AND ISOLATION BREAKERS. ARRANGEMENT SHALL ALLOW BOTH BREAKERS TO BE LOCKED OPEN TO SERVE AS DISCONNECTING MEANS FOR TRANSFORMER. 5. PROVIDE 600A BREAKER TO TEMPORARILY POWER CRITICAL PROVIDE 600A BREAKER TO TEMPORARILY POWER CRITICAL LOAD PANEL DURING UPS REPLACEMENT. MATCH TYPE AND RATINGS OF EXISTING BRANCH BREAKERS. LEAVE BREAKER IN PLACE AFTER UPS REPLACEMENT IS COMPLETE. REPLACE ALL COVERS, BLANKS, ETC. TO RESTORE ENCLOSURE TO ORIGINAL INGRESS PROTECTION LEVEL. 6. PROVIDE TEMPORARY DIESEL FUELED GENERATOR TO SUPPLY PROVIDE TEMPORARY DIESEL FUELED GENERATOR TO SUPPLY POWER TO CRITICAL LOAD PANEL DURING REPLACEMENT OF THE UPS SYSTEM. GENERATOR SHALL BE RENTAL UNIT IN GOOD CONDITION ACQUIRED THROUGH LOCAL CATERPILLAR, CUMMINS OR KOHLER REPRESENTATIVE. THE TOTAL HARMONIC DISTORTION OF THE GENERATOR'S OUTPUT VOLTAGE SHALL NOT EXCEED 5.0%. 7. PROVIDE TEMPORARY CONDUCTORS, ROUTED THROUGH WALL PROVIDE TEMPORARY CONDUCTORS, ROUTED THROUGH WALL LOUVERS. PROVIDE MEANS TO PROTECT CONDUCTORS FROM SHARP EDGES, FOOT TRAFFIC AND OTHER PHYSICAL DAMAGE. 8. CONDUIT ROUTED OVERHEAD ON WALLS AND CEILING. CONDUIT ROUTED OVERHEAD ON WALLS AND CEILING. 9. DRIVE 10 FT. X 3/4" COPPER CLAD GROUND ROD AT DRIVE 10 FT. X 3/4" COPPER CLAD GROUND ROD AT TEMPORARY GENERATOR AND BOND TO GENERATOR WITH #6 GROUNDING ELECTRODE CONDUCTOR. VERIFY AREA IS FREE OF UNDERGROUND UTILITIES PRIOR TO DRIVING GROUND ROD. 10. VERIFY AND MAINTAIN N-G BOND AND CONNECTION TO VERIFY AND MAINTAIN N-G BOND AND CONNECTION TO GROUNDING ELECTRODE SYSTEM. 11. 200/225A CIRCUIT BREAKER AS DIRECTED BY UPS 200/225A CIRCUIT BREAKER AS DIRECTED BY UPS MANUFACTURER.
AutoCAD SHX Text
(2) 3 #3/0, #3 GND, 2" C
AutoCAD SHX Text
EXISTING 300 KVA 480V-208Y/120V TRANSFORMER
AutoCAD SHX Text
(2) 3 #3/0, #3 GND, 2" C
AutoCAD SHX Text
(2) 4 350 KCMIL, #1 GND
AutoCAD SHX Text 400A
AutoCAD SHX Text 400A
AutoCAD SHX Text 200A
AutoCAD SHX Text 200A
AutoCAD SHX Text
MAINTENANCE/BYPASS PANEL 400A, 480V, 3-PH, 3W, 35KAIC
AutoCAD SHX Text OBTAIN CIRCUIT BREAKER TO BE INSTALLED IN CRITICAL LOAD PANEL INCLUDING ANY MOUNTING ACCESSORIES, LUGS, ETC. REQUIRED. PLACE TEMPORARY GENERATOR, RUN TEMPORARY CABLING TO CRITICAL LOAD PANEL. MAKE ARRANGEMENTS FOR FUEL DELIVERY AND VERIFY GENERATOR FUEL TANK CAN BE ACCESSED BY REFUELING MEANS. CHECK PHASE ROTATION OF CRITICAL LOAD PANEL AND GENERATOR. MARK CABLES WITH PHASE INFORMATION TO ENSURE GENERATOR HAS CORRECT PHASE ROTATION. SHUTDOWN OF LOADS SERVED BY CRITICAL LOAD PANEL WILL BE PERFORMED BY GOVERNMENT. DO NOT PROCEED WITH CHANGEOVER TO TEMPORARY GENERATOR POWER UNTIL NOTIFIED BY GOVERNMENT. GOVERNMENT TO BEGIN SHUTDOWN OF CRITICAL LOADS AT 7:00 AM ON A SATURDAY. TO BEGIN CHANGEOVER SEQUENCE SHUT OFF CRITICAL LOAD PANEL MAIN DISCONNECT AND LOCK/TAG OUT. OPEN ALL BRANCH BREAKERS. ONCE CRITICAL LOAD PANEL IS VERIFIED TO BE DE-ENERGIZED INSTALL NEW CIRCUIT BREAKER AND TERMINATE CONDUCTORS. VERIFY NEW BREAKER IS OPEN. AFTER GOVERNMENT INDICATES IT IS READY TO RESTART CRITICAL LOADS, START GENERATOR AND VERIFY SUPPLY VOLTAGE, FREQUENCY AND PHASE ROTATION ARE CORRECT. CLOSE NEW BREAKER TO ENERGIZE CRITICAL LOAD PANEL. CLOSE CRITICAL LOAD PANEL BRANCH BREAKERS ONE AT A TIME WITH A 10 SECOND DELAY AFTER EACH BREAKER IS CLOSED TO ALLOW THE VOLTAGE AND LOAD TO STABILIZE. TOTAL TIME FROM GOVERNMENT SHUTDOWN OF CRITICAL LOADS TO RESTART ON TEMPORARY GENERATOR POWER SHALL NOT SHALL NOT EXCEED 8 HOURS. AFTER GOVERNMENT VERIFIES THE CRITICAL LOADS ARE OPERATING PROPERLY ON TEMPORARY POWER, PERFORM SHUTDOWN SEQUENCE ON EXISTING UPS SYSTEM TO BE REPLACED. SHUTOFF AND LOCK/TAG OUT THE TWO UPS SYSTEM FEEDERS LABELED 'UPS' AND 'UPS BYPASS' IN THE 480V EMERGENCY DISTRIBUTION SWITCHBOARD. PROCEED WITH REPLACEMENT OF UPS SYSTEM.
AutoCAD SHX Text
CHANGEOVER TO TEMPORARY POWER
AutoCAD SHX Text SCHEDULE CRITICAL LOAD SHUTDOWN WITH GOVERNMENT ONCE UPS SYSTEM HAS BEEN INSTALLED AND TESTED AS REQUIRED BY SPECIFICATION 263353 PART 3 AND PHASE ROTATION ON TRANSFORMER SECONDARY HAS BEEN VERIFIED CORRECT. SHUTDOWN OF LOADS SERVED BY CRITICAL LOAD PANEL WILL BE PERFORMED BY GOVERNMENT. DO NOT PROCEED WITH CHANGEOVER TO NORMAL POWER UNTIL NOTIFIED BY GOVERNMENT. GOVERNMENT TO BEGIN SHUTDOWN OF CRITICAL LOADS AT 7:00 AM ON A SATURDAY. VERIFY KEYS, COMBINATIONS OR OTHER MEANS TO REMOVE LOCKS ON CRITICAL LOAD PANEL MAIN BREAKER ARE AVAILABLE. TO BEGIN CHANGEOVER SEQUENCE SHUT OFF BREAKER IN CRITICAL LOAD PANEL INSTALLED FOR CONNECTING TEMPORARY GENERATOR. OPEN ALL BRANCH BREAKERS. OPEN BREAKER AT GENERATOR AND SHUTDOWN GENERATOR. LOCKOUT GENERATOR/BREAKER TO PREVENT ACCIDENTAL ENERGIZING OF TEMPORARY FEEDER. ONCE CRITICAL LOAD PANEL IS VERIFIED TO BE DE-ENERGIZED REMOVE TEMPORARY FEEDER AND INSTALL ALL COVERS. AFTER GOVERNMENT INDICATES IT IS READY TO RESTART CRITICAL LOADS, CLOSE MAIN BREAKER OF CRITICAL LOAD PANEL AND CLOSE BRANCH BREAKERS ONE AT A TIME WITH A 10 SECOND DELAY AFTER EACH BREAKER IS CLOSED TO ALLOW THE VOLTAGE AND LOAD TO STABILIZE. TOTAL TIME FROM GOVERNMENT SHUTDOWN OF CRITICAL LOADS TO RESTART ON NORMAL POWER SHALL NOT EXCEED 8 HOURS. SHALL NOT EXCEED 8 HOURS. AFTER GOVERNMENT VERIFIES THE CRITICAL LOADS ARE OPERATING PROPERLY ON NORMAL POWER, REMOVE TEMPORARY FEEDER AND GENERATOR.
AutoCAD SHX Text
CHANGEOVER TO NORMAL POWER
AutoCAD SHX Text FOR EACH CHANGEOVER CONTRACTOR SHALL PROVIDE PLANS WITH EXPECTED STEP-BY-STEP TIME STAMPS TO THE GOVERNMENT IN THE FORM CONSTRUCTION SUBMITTALS, 4-WEEKS BEFORE THE PLANNED ACTIVITIES. CONTRACTOR SHALL PROVIDE 24/7 REFUELING PLAN TO BE IMPLEMENTED UNTIL CHANGEOVER TO UPS IS COMPLETE. COORDINATE ALL POWER INTERRUPTIONS WITH GOVERNMENT PRIOR TO PERFORMING WORK.
AutoCAD SHX Text
CHANGEOVER GENERAL REQUIREMENTS
AutoCAD SHX Text
ELECTRICAL ONE LINE
AutoCAD SHX Text
AutoCAD SHX Text E002
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text B
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text C
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text A
AutoCAD SHX Text B
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text C
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text
AutoCAD SHX Text
CHK'D BY:
AutoCAD SHX Text
DESIGN OFFICE:
AutoCAD SHX Text
DESIGNED BY:
AutoCAD SHX Text
PROJECT NO:
AutoCAD SHX Text
DRAWN BY:
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
APPROVED BY:
AutoCAD SHX Text
OF
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
DESCRIPTION
AutoCAD SHX Text
MARK
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
DATE
AutoCAD SHX Text
UNITED STATES DEPARTMENT OF THE INTERIOR
AutoCAD SHX Text
BUREAU OF LAND MANAGEMENT
AutoCAD SHX Text
NIFC 300 - JWH UPS REPLACEMENT
AutoCAD SHX Text
BOISE
AutoCAD SHX Text
IDAHO
AutoCAD SHX Text
NWBLM2021_DO#33
AutoCAD SHX Text
CUSHING TERRELL
AutoCAD SHX Text 8/12/2021
AutoCAD SHX Text
AutoCAD SHX Text
MTB
AutoCAD SHX Text
MTB
AutoCAD SHX Text
MTB
AutoCAD SHX Text
AutoCAD SHX Text
ADDENDUM 1
AutoCAD SHX Text 3-17-22
AutoCAD SHX Text
MTB
AutoCAD SHX Text 15474
AutoCAD SHX Text H
AutoCAD SHX Text A
AutoCAD SHX Text D
AutoCAD SHX Text I
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text E
AutoCAD SHX Text T
AutoCAD SHX Text A
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text S
AutoCAD SHX Text M
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text H
AutoCAD SHX Text A
AutoCAD SHX Text E
AutoCAD SHX Text L
AutoCAD SHX Text T.
AutoCAD SHX Text B
AutoCAD SHX Text E
AutoCAD SHX Text G
AutoCAD SHX Text L
AutoCAD SHX Text I
AutoCAD SHX Text N
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text I
AutoCAD SHX Text G
AutoCAD SHX Text N
AutoCAD SHX Text E
AutoCAD SHX Text L
AutoCAD SHX Text A
AutoCAD SHX Text N
AutoCAD SHX Text O
AutoCAD SHX Text I
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text P
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text N
AutoCAD SHX Text E
AutoCAD SHX Text C
AutoCAD SHX Text I
AutoCAD SHX Text L
AutoCAD SHX Text E
AutoCAD SHX Text R
File details come from the government source that posted it. Updated .