This document provides an amendment to a solicitation for road maintenance services. The amendment incorporates questions received from offerors and the associated answers provided by the government. The solicitation is for the Keno, Kennedy, and Elevation Area Road Maintenance project requiring unclassified borrow, roadway excavation and embankment, drainage excavation, drain dip construction and reconstruction, catch basin construction and reconstruction, and keyed riprap class 4. The government will provide all necessary staking and there is no topographic survey. Offerors must acknowledge receipt of the amendment by April 10, 2023. Native materials may be used from excavations within the project area. The government holds permits required for culvert replacements.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140L3623R0011 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

LMA

BILLINGS MT 59101

5001 SOUTHGATE DR.

BLM MT STATE OFC(MT935)

LMA

BILLINGS MT 59101

5001 SOUTHGATE DR.

BLM MT-STATE OFC(MT935)

04/03/20230002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

03/21/2023

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

See Page 2 of 4 for changes incorporated by this amendment.

Period of Performance: 07/17/2023 to 11/15/2024

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Christine Mundt

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

PROJECT DESCRIPTION: Keno, Kennedy, & Elevation Area Road Maintenance Solicitation No. 140L3623R0011

Description of Changes - This amendment incorporates the following information:

1. The Government is providing the Questions received from interested offerors and the associated Answers provided by the Government.

Acknowledgement - See Block 11 above regarding how to acknowledge this amendment. The Government must receive the acknowledgement at the place designated for receipt of offers (See Block 8 of the Standard Form 1442).

Third Party – If you have given a copy of the solicitation to someone else, please forward this amendment accordingly.

Questions and Answers Offerors shall submit questions by 10 April 2023, at 1:00 pm, Mountain Time. Questions submitted after this date and time will not be accepted. Offerors for this RFQ, including subcontractors and teammates, shall consolidate questions related to this solicitation in a Request for Information (RFI) formatted Word document. Any RFI is to be emailed as an editable attachment to Jorge Alvarez (jalvarez@blm.gov) with the subject line: RFI – 140L3623R0011 Keno, Kennedy, & Elevation Area Road Maintenance. Only written RFI’s will be considered and responded to. BLM responses to the RFI will be posted as an amendment to the solicitation on https://sam.gov.

Solicitation Number: 140L3623R0011 Project Title: Keno, Kennedy, & Elevation Area Road Maintenance

1. What control (152.04c) has been set or will be set on the project by the Gov?

• All staking provided by the government. No 152xx pay items on quote schedule.

2. What data (152.04c) will be made available?

• All staking provided by the government. There is no topographic survey for the site. All features will be slope staked and field fit. No 152xx pay items on quote schedule.

3. Will there be design centerline alignments (152.05b)?

• All staking provided by the government. There is no topographic survey or design surfaces for the site. Center line is based off existing road and road width. No 152xx pay items on quote schedule.

4. Original ground topographic verification (152.05c), where does the theoretical ground elevations come from? Is staking required on all of the Roadway excavation and embankment (3.9 miles)?

• All staking provided by the government. There is no topographic survey for the site. No 152xx pay items on quote schedule. Staking is not required for by the contractor for any of the 204 Roadway Excavation and Embankment pay items.

5. Does Drainage Excavation require staking (9935 feet)?

• Government will provide a stake identifying the construction begin and end.

It is the intention of the government that from the beginning and end stake the contractor can construct per the typical section.

• Note ditch lines that are less than 50% full are to be reconstructed under the 303 pay items where ditch line is present.

6. Does Drain Dip construction require staking as opposed to Reshaping Drain Dip?

• It is the intention that the contractor can from a single stake identifying drain dip construct or reconstruct a field fit functioning dip within the length and grades identified in the typical section.

• Drain dip construction implies there is no existing or remnant dip.

https://sam.gov/

Reconstruct drain dip implies there is some remnants of a previously constructed dip. Both will need to be constructed to a field fit functioning drain dip. The reconstruction should be less effort than a construction.

7. Does Catch Basin construction require staking as opposed to Reshaping Catch Basin?

• It is the intention that the contractor can from a single stake identifying catch basin construct/reconstruct a field fit catch basin from the typical section.

The contractor should be able to excavate a 5 ft back of catch basin and slope the back of catch basin to specified slope on the construction stake. Slope is ideally 1.5:1 unless it doesn’t catch within excavator reach in which case the slope will be steepened or a rock buttress added at the government’s expense.

Backslope will be identified per construction stake.

8. Is there a water source that would be provided close to the project?

• Keno Creek, Kennedy Creek and Elk Creek are adjacent water sources.

Contractor would need to seek water rights from other parties or time operations with weather. Note there are no requirements for proctor tested compaction with measured and tested moisture. See supplemental specification section 204 exact language of moisture requirements.

9. Would the native material used to rebuild roads from embankments need to be classified?

• Per Pay item 20403 Roadway excavation and embankment, Unclassified

Borrow, compaction placement method 3.

• Material specified is unclassified and treated as such.

10. 25104 Keyed riprap class 4. Government furnished. Would the government supply hauling to the sited? If not, How far away is the material?

• Material would be conserved by the contractor from excavations performed in the project area or plucked from BLM ownership along the project roads.

Contractor would be responsible for transport of material within the project area.

11. What other permitting is needed for the Keno Creek pipe replacement?

• BLM holds the 124 permit from fish wildlife and parks for culvert replacements in the project site. No other permit required from the BLM for this project.

• Note required project submittal 30 days prior to work 60201C Culvert replacement. Construction plan with Soil Erosion and Sediment Control for stream pipe replacement. See Supplemental Specifications section 157 and FP-14 sections 157 and 107.