This is an amendment to a solicitation for the Burley Fire Warehouse Remodel project. The amendment extends the solicitation closing date to August 6, 2021 at 10:00 am MDT. It adds site inspection sign-in information and responses from a tour held on July 13, 2021, as well as specification 099600 for high performance coatings. The amendment also notes asbestos-containing materials were found at the Burley Warehouse. The performance period for the project is extended to run from August 30, 2021 to March 31, 2022. Quoters must acknowledge receipt of the amendment by completing blocks in the form and returning it to the Bureau of Land Management Idaho Region office listed by the deadline.

View the file

Other files

File Type Posted
Sol_140L2621R0005_Amd_0002.pdf PDF
DRAFT_L1416_Burley_Warehouse_ACM_Report_0001.pdf PDF
099600_SF_-_High-Performance_Coatings_0001.doc DOC document
RFI_s_0001.docx DOCX document
Site_Tour_Sign_In_0001.pdf PDF
Burley_Fire_Warehouse_Drawings.pdf PDF
Burley_Fire_Warehouse_Specifications.pdf PDF
Sol_140L2621R0005.pdf PDF
SF-24_Bid_Bond.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140L2621R0005 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

LDA

BOISE ID 83709

1387 S. VINNELL WAY

BLM ID STATE OFC HR&ADMN (ID953)

LDA

BOISE ID 83709

1387 S. VINNELL WAY

BLM ID-STATE OFC HR&ADM SVC (ID953)

07/22/20210001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/17/2021

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

LIST OF CHANGES:

1. The purpose of this amendment is to add the following:

- Site Inspection Sign-in and RFI responses from Tour which was held Tuesday, July 13, 2021.

- Add Specification 099600 High Performance Coatings.

- Add Burley Warehouse ACM.

2. The Performance Period now reads: August 30, 2010 to March 31, 2022.

3. The Solicitation Closing date and time has been extended to Friday, August 6, 2021 at

10:00 am MDT.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Patricia Fort

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140L2621R0005/0001

4. Quoters must acknowledge receipt of this amendment by completing blocks 8, and 15

(A)through (C) and returning a copy to the office listed in block #6.

Period of Performance: 08/30/2021 to 03/31/2022

Change Item 00010 to read as follows(amount shown is the obligated amount):

00010 Burley Warehouse Remodel

Product/Service Code: Y1JZ

Product/Service Description: CONSTRUCTION OF

MISCELLANEOUS BUILDINGS

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110