This document contains clarification responses to questions regarding a solicitation to install new electrical systems at a four-stall garage building. The clarifications specify that the electrical panel can be located near the back door of the building. Two ceiling light connections are required avoiding the overhead door opening. The variable frequency drive is to be placed on the south side of the dividing wall between the north and middle bays. Outlets listed in the middle bay are not part of the requirement, and the focus is on the north small bay and variable frequency drive placement. Field verification of lighting locations and code compliance for GFCI protection in wet areas is necessary.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Clarifica ons Amendment 002
Clarifications are in blue text.
1. For the conduit entrance into the building, they cannot place the shut/off switch or meter box within 36" of the gas meter. (see picture in folder)We will have to reconsider the panel location. Possibly route to the back wall near the walk door.
1. Panel location near the back door is acceptable, please verify the panel location once construction starts.
2. How many ceiling light connections did engineering plan for in the North Bay?
1. Two (2), avoiding overhead door opening.
3. The Well VFD is located on the West wall. Can it be placed on the South side of the dividing wall between the North and middle bay.
1. The intent is to have it on the south side of the dividing wall between the North and Middle Bay.
4. There are outlets listed on the plans in the middle bay. We do not need that work completed at this time.
1. The outlets are not part of this requirement. The focus is on the North Small bay and VFD placement.
5. I believe we are supposed to be 3 feet away from the gas meter.
1. Field Verify Location with Staff and code requirements.
6. There are circuits to be installed. For example, lighting.
1. Are we tying into existing lighting
1. Yes
2. What are the locations of the lights
1. Field verify location with staff, but they would like (2) additional lights avoiding the overhead door opening.
3. How many
1. 2
4. Are there switch locations or motion
1. No motion lights needed, field verify location with staff
7. VFD location my be different then what Mitch is thinking.
1. have it on the South side of the dividing wall between the North and middle bay.
8. Do you have locations of highlighted circuits to be installed.
1. Locations can be field verified
9. There are 12 highlighted circuits but only 8 if we look at the circuit numbers.
1. 8 circuits would be accurate
10. The 6 “ well pump does not have a circuit number.
1. That would be powered by the VFD
11. Mitch didn’t think that there were going to be any outlets installed in the middle bay other than the VFD.
1. Focus is on North small bay and VFD placement.
12. Are the outlets all GFCI or a GCFI breaker
1. Default to code for wet area.
13. Is this a damp location where everything needs to have GFCI protection
1. Yes