AttachmentVIII-Request for Information (RFI)040192021_0004.pdf
PDF 80 KB Posted
- Attached to
- WV-NCTC RENOVATE CREATIVE RESOURCES AND Federal contract opportunity
- Solicitation number
- 140F0421R0010
About this file
This federal contract opportunity announcement solicits construction services for renovating creative resources and a west pond at the Department of the Interior Fish and Wildlife Service. Specifically, the solicitation seeks to renovate existing facilities that support creative programs as well as upgrade a west pond area. Offerors must submit proposals in response to solicitation number 140F0421R0010 by the deadline of April 19, 2021. The award is a firm fixed-price construction contract with an anticipated period of performance from June 2021 to December 2022. Small businesses, including HUBZone small, small disadvantaged, women-owned small, veteran-owned small, and service-disabled veteran-owned small businesses, are encouraged to submit proposals.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140F0421R0010_Amd_0004.pdf | ||
| Sol_140F0421R0010_Amd_0003.pdf | ||
| Attachment-VII RFI.docx04122021_0003.pdf | ||
| Sol_140F0421R0010_Amd_0002.pdf | ||
| Attachment V-Request for Information Responses RFI_0002.pdf | ||
| Attachment III- Revised Statement of Work _0001.pdf | ||
| Sol_140F0421R0010_Amd_0001.pdf | ||
| Attachment IV-DOL Wage Determination.pdf | ||
| Attachment II-Drawings-Specifications.pdf | ||
| Attachment I-Solicitation Documents140F0421R0010.pdf | ||
| Sol_140F0421R0010.pdf | ||
| Attachment III-Statement of Work.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION NO: 140F0421R0010
RENOVATE CREATIVE RESOURCES & WEST POND
REQUEST FOR INFORMATION -RFI
QUESTIONS ANSWERS
Q1: Reading the RFP, on page 40/40 top paragraph, it mentions when writing the technical proposal, we will need to list the key personnel such as the PM, the Site Superintendent and the Quality Control Manager. It also states “These positions shall be filled by three different individuals and the Quality Control Manager should not report directly to the Site Superintendent.”
In the past, the site superintendent and the QC Manger rolls have been served by the same person. For this project, can the Site superintendent and the QC Manager roll be conducted by the same person?
A1: No need for 3 full time people on the project managing it. A PM as an as needed basis, and full time site supervision. There is no need for the QC on a small project like this.
No QC, part time PM and full time site Sup.