Sol_140A0323B0001_Amd_0001.pdf
PDF 169 KB Posted
- Solicitation number
- 140A0323B0001
About this file
This document provides details for a federal solicitation seeking construction services for a propane tank access road project on behalf of the Otoe-Missouria Tribe of Oklahoma. The solicitation is for firm fixed-price contracts to provide grading, drainage, paving, and construction of drainage structures for a 2,806 foot long dirt road requiring reconstruction. Services will be performed at the project site located 0.3 miles southwest of the Otoe-Missouria Tribal Complex in Red Rock, Oklahoma. The solicitation is set aside exclusively for Indian Small Business Economic Enterprises as defined by 48 CFR Part 1480. The Bureau of Indian Affairs is issuing this solicitation on behalf of the Tribe. The solicitation includes requirements for bonding, prevailing wage rates, and environmental permits. The bid opening is January 6, 2023 and award is anticipated by February 15, 2023 with a 120 day period of performance after notice to proceed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140A0323B0001 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
A03
Anadarko OK 73005-0328 Contracting Office
100 NORTH RIVERSIDE DRIVE
BIA SPRO 00003
12/29/20220001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
12/01/2022
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
OTOE-MISSOURIA PROPANE ROAD PROJECT - AMENDMENT #1
The following questions were asked at the pre-bid meeting or sent in by the required due date and are being made a part of Amendment #1 to the solicitation.
The Bid Opening date has been extended to January 13, 2023, 2;00PM CT.
1. Will there be a geotechnical report issued because of the soil samples taken by the
Oklahoma Department of Transportation employees at the project?
Answer: There is no current plan for a geotechnical report to be issued for the project.
The soil samples taken by ODOT are for research purposes and not for the current project
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Jocelyn Littlechief
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140A0323B0001/0001 but if a report is made available it will be provided.
2. Question: Where are the trees resulting from clearing and grubbing be placed?
Answer: The trees will be removed under Item
201(A) Clearing and Grubbing. The removed trees are to be placed along the right of way at a location designated by the tribe. Ms. Berdina
Tohee and Mr. Lester Harragarra said the tribal members can use the trees as firewood. The trees do not need to be cut into smaller sections since the tribal maintenance department or tribal members will cut the trees as needed. Ms. Tohee is going to check on the tribal requirements for burning the excess brush at the project.
3. Question: What are the heavy truck restrictions for vehicles 80,000 pounds and under?
Answer: The heavy trucks can access the project from the south from county road CR220 and
Windmill Road and unloaded trucks can exit the project by using the road which runs along the north side of the softball fields and exits on
State Highway 177.
4. Question: Is there a borrow source located near the project?
Answer: Mr. Harragarra stated there is a borrow source located about 0.25 miles north of the project which can be used if a source of borrow is required for the project. Borrow should not be required for the project since there should be some excess material resulting from the roadway construction.
5. Question: Does the fence have to be replaced once it is removed on the north side of the project?
Answer: Item 619(B) Removal of Fence is a Lump
Sum item. The fence is to be removed according to the plans and there is no item for new fencing on the north side of the project. The fencing on the south side of the project is to remain in place.
6. Question: Is the underground sewer line near
Station 27+50 going to be affected by the project?
Answer: The underground sewer line is estimated
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140A0323B0001/0001 to be about 12¿ down from the existing ground surface and should not be affected by the pending construction. Mr. Harragarra is going to email a copy of the sewer plans to the Southern Plains
Transportation office which will be used to check for any potential conflicts or problems with the sewer line. The underground sewer is not shown on the construction plans. Mr. Anderson
Berryhill of the Otoe-Missouria tribe is the point of contact for the location of tribal utilities.
7. Question: What are the spacing requirements for soil compaction tests?
Answer: The compaction tests are typically performed for every 1,500 feet of the project length but this project is only 2806 feet long so the testing should be performed every 500 feet, which will ensure there are an adequate number of tests performed to ensure the necessary compactions is achieved.
8. Correction to Pay Item MnDOT 409, Geotextile
Fabric Type V to ODOT Pay Item 325, Separator
Fabric. The SY does not change but remains at
7800. An updated Bid Schedule attachment is included and should be used. Refer to ODOT Spec for installation.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
BIA SOUTHERN PLAINS REGIONAL OFFICE
PROPANE TANK ACCESS ROAD PROJECT
OTOE-MISSOURIA TRIBE OF OKLAHOMA
BID SCHEDULE SOLICITATION 140A0323B0001
ITEM NUMBER NOTES DESCRIPTION UNIT ESTIMATED
QUANTITY
UNIT PRICE TOTAL
201(A) A CLEARING & GRUBBING LUMP SUM 1
202(H) D EARTHWORK LUMP SUM
220 SWPPP DOCUMENTATION AND MANAGEMENT LUMP SUM
221(B) TEMPORARY SILT FENCE LIN FT 900
221(G) TEMPORARY FIBER LOG LIN FT 100
230(A) 6 SOLID SLAB SODDING SQ YD 4000
303(A) AGGREGATE BASE TYPE A TON 2460
407(B) 8 TACK COAT GALLON 380
325 B SEPARATOR FABRIC SQ YD 7800
411 ( C ) SUPERPAVE, TYPE S4 (PG 64-22 OK)(2.5 INCH) TON
411 ( C ) SUPERPAVE, TYPE S3 (PG 64-22 OK)(2.5 INCH) TON
601(A) TYPE 1 PLAIN RIPRAP CU YD 50
613(A) 9 28" X 18" R.C. PIPE ARCH CLASS A-Ill LIN FT 32
613(L) 9 PREFAB. END SECTION OF 28"X18" RCP ARCH EACH
613(A) 9 30" R.C. PIPE CLASS A-Ill LIN FT 36
613(L) 9 PREFAB END SECTION OF 30" RCP EACH 1
SP DROP INLET STRUCTURE TO 30" RCP EACH 1
619(B) REMOVAL OF EXISTING PIPE LUMP SUM
619(B) REMOVAL OF FENCE LUMP SUM
619(B) 8 SAWING PAVEMENT LUMP SUM
623(F) C BEAM GUARDRAIL W-BEAM SINGLE LIN FT 250
623(G) GUARDRAIL END TREATMENT (TURNDOWN) EACH 6
641 MOBILIZATION LUMP SUM
642(B) CONSTRUCTION STAKING LEVEL II LUMP SUM
643 E CONTRACTOR QUALITY CONTROL (SP) LUMP SUM
850(A) SHEET ALUMINUM SIGNS SQ FT 39.5
851© SQUARE TUBE POST LIN FT 75
854(A) TRAFFIC STRIPE (PAINT) LIN FT 11230
880(J) CONSTRUCTION TRAFFIC CONTROL LUMP SUM
SP F 5' RISE X 10' SPAN CONCRETE BOX CULVERT LIN FT 30
SP G CLASS C CONCRETE CY 10
TOTAL
SP TERO FEES - 3% OF CONTRACT TOTAL
GRAND TOTAL
File details come from the government source that posted it. Updated .