Amend__2.pdf

PDF 431 KB Posted

Attached to
Construction of a Water Well
Solicitation number
13-235-SOL-00005
Issued by

View the file

Other files

File Type Posted
Amend__4.pdf PDF
Amend__3.pdf PDF
Amend__1_(section_C.1).pdf PDF
Attach__2_F_ _M_Goals.pdf PDF
SF_1442.pdf PDF
Attach__4_Exhibits.pdf PDF
Solicitation_Body.pdf PDF
Attach__1_Wages.pdf PDF
Attach__3_Submittals.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

13-235-SOL-00005

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Sacramento CA 95814 650 Capitol Mall, Suite 7-100 John E Moss Federal Bldg California Office of the Director

CA 11-M6203/21/2013000002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

03/21/2013

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

This amendment makes the following changes:

1) Revisions to the Bid Schedule (attached)

2) Revisions to Section 02667, 02670, and 16100 (summary attached)

3) Adding section 16900 Process Control System (attached)

4) Adding Exhibit #12 and #13 (attached)

The due date has been extended to 3:00 p.m. April 18, 2013.

All other terms and conditions remain unchanged.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

HARRY J. WEISS

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

Electronically Signed 04/04/2013

SECTION B

Cortina Rancheria Project CA 11-M62

The following Bid Schedule is based on estimated quantities required to meet the specifications. The total extended prices shall be used for quote evaluation purposes only. The actual amount to be paid by the Government under the contract shall be computed on the actual quantities installed at the unit bid prices awarded. The designated ordering office is the Contracting Office, Indian Health Service, California Area Office, Sacramento, California.

UNIT TOTAL

ITEM DESCRIPTION QTY UNIT PRICE PRICE

DIVISION 2 - Site Work

1 Mobilization & Demobilization 1 LS

Section 02100

2 Water Main 50 LF

Section 02667

3 Valve Box 1 EA

4 Water Meters for Individual homes 6 EA

5 Connection to Existing Water main 1 EA

6 Pothole work 1 LS

Section 02670

7 Well Drilling 400 LF

8 Geophysical Logging 1 LS

9 Aquifer Testing 1 LS

10 PVC Well Casing-6 in. 280 LF

11 Well Grouting 50 LF

12 Stainless Steel Well Screen 120 LF

13 Gravel Pack 190 LF

14 Formation Stabilizer 150 LF

15 Well Development 4 HR

16 Test Pumping 20 HR

17 Test Pump Recovery 4 HR

18 Well Disinfection and Water Analysis 1 EA

19 Well Testing and Chemical Analysis 1 EA

20 Well Abandonment 200 LF

21 PVC Drop Pipe-2in. With Sub Cable 400 LF

22 Submersible Pump 1 LS

23 Enclosure System 1 EA

DIVISION 16 - Electrical

24 Buried Electrical Cable 300 LF

Section 16100

25 Process Control System 1 LS

Section 16900

Total Quote

AMENDMENT #2

SECTION 02667

WATER MAINS

FROM:

1.2 UNIT PRICE - MEASUREMENT AND PAYMENT

B. Gate Valve and Box: Paid by the unit, measured to the whole unit. Includes excavation, gate valve, gate valve key, box, thrust blocks, protection posts, backfilling, as-builts, site cleanup, and other appurtenances as necessary

TO:

B. Valve Box: Paid by the unit, measured to the whole unit. Includes excavation, gate valves, check valves, pipe, fittings, gate valve key, box, lid, thrust blocks, restrained joints, drain rock, backfilling, as-builts, site cleanup, and other appurtenances as necessary.

2.3 GATE VALVE BOX

A. Manufacturer: Tyler Pipe or equal.

B. Cast iron and of the sliding type, sized for use with the appropriate valve. Box lid marked "WATER." Box shall extend from the body of the valve to the finished grade and be locking.

2.3 VALVE BOX

A. Concrete valve box with lid for gate and check valves. Box lid marked "WATER." Box shall enclose all check and gate valves. Box floor shall be sloped to a drain. 1-inch Sch40 PVC drain pipe shall end in approximately 1cu yd of 1.5 inch clean, crushed rock. Drain rock will be placed as directed by Project Engineer.

B. Deleted

SECTION 02670

WATER WELL

Q. ENCLOSURE SYSTEM: By the unit as stated in the bid schedule and includes:

Materials and installation of the enclosure and concrete slab, gate valve, hose bib with vacuum/backflow preventer, check valve, pressure gauge, flow meter, pressure relief, plumbing, conduit/cable, circuit breaker load center, pump protection, lightning arrestor, receptacle, buried electrical conduit/cable two feet beyond the edge of well slab, trenching, backfilling, and all other fittings and incidentals.

Q. ENCLOSURE SYSTEM: By the unit as stated in the bid schedule and includes:

Materials and installation of the enclosure and concrete slab, fencing, gate for fence, gate valve, hose bib with vacuum/backflow preventer, check valve, pressure gauge, flow meter, pressure relief, plumbing, conduit/cable, circuit breaker load center, pump protection, lightning arrestor, receptacle, buried electrical conduit/cable two feet beyond the edge of well slab, trenching, backfilling, and all other fittings and incidentals.

R. POTHOLE WORK: Paid by the lump sum and includes: all work to identify or pothole utilities around the new well site prior to drilling and to identify the connection points for the new well on the existing buried electrical and water lines.

DELETED:

3.7 SURFACE SEAL

D. Sealing Conditions: Follow California State Water Wells Standards (Bulletin 74- 81 and 74-90, Part II, Section 9) for sealing wells in various formations.

SECTION 16100

ELECTRICAL REQUIREMENTS

1.3 UNIT PRICE - MEASUREMENT AND PAYMENT

B. BURIED ELECTRICAL CABLE: Paid by the linear foot, measured to the nearest foot. Includes underground cable, conduit, trench excavation, fittings, electrical connections, backfilling, as-builts and site cleanup.

foot. Includes underground cable/wire, conduit, pull boxes, trench excavation, fittings, electrical connections, backfilling, as-builts and site cleanup.

ADDED:

2.8 WIRING CONNECTORS

E. Cable/Wire size shall be sized to allow no more than a 5% voltage drop between the pump motor and the electrical service entrance panel. 8 gauge wire shall be used for the proposed 1.5HP pump motor.

STANDARD SPECIFICATIONS

SECTION 16100

ELECTRICAL REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. This section includes circuit breaker load centers, pump control boxes, pump protection, wire & cable, and conduit.

1.2 RELATED SECTIONS

A. Section 02200 - Excavating, Trenching and Backfilling

B. Section 15450 - Water System.

A. Work required under Section 16100 shall be merged with pay items defined within the Measurement and Payment portions of other Sections of this contract.

Includes all electrical equipment necessary for the operation of the well pump.

Buried electrical cable is an exception.

foot. Includes underground cable/wire, conduit, pull boxes, trench excavation, fittings, electrical connections, backfilling, as-builts and site cleanup.

1.4 REFERENCES

A. ANSI/NFPA 70 - National Electrical Code.

B. Franklin Electric - Application - Installation - Maintenance Manual.

C. ANSI C80.1 - Rigid Steel Conduit, Zinc Coated.

D. ANSI C80.3 - Electrical Metallic Tubing, Zinc Coated.

E. NECA "Standard of Installation."

F. NEMA TC 3 - PVC Fittings for Use with Rigid PVC Conduit and Tubing.

1.5 PROJECT RECORD DOCUMENTS

A. Accurately record actual locations of underground cable.

PART 2 PRODUCTS

2.1 CIRCUIT BREAKER LOAD CENTER

A. Manufacturers:

1. Square "D"

2. General Electric

3. Westinghouse

4. Substitutions: Will be permitted

B. Minimum integrated short circuit rating: 10,000 amperes rms symmetrical.

C. Molded Case Circuit Breakers: NEMA AB 1, plug-on type thermal trip circuit breakers, with common trip handle for all poles.

D. Enclosure: General purpose.

2.2 PUMP CONTROL BOX

A. Manufacturer:

1. Same as submersible pump manufacturer

2. All components shall be sized correctly for the pump motor model selected

2.3 PUMP PROTECTION

1. Franklin PUMPTEC

2. Other acceptable manufacturers offering equivalent products

2.4 LIGHTNING ARRESTOR

1. Franklin

2. Other acceptable manufacturers offering equivalent products

2.5 RIGID METAL CONDUIT

1. Allied Tube and Conduit

2. AFC

3. Hubbell

4. Substitutions: Will be permitted

B. Rigid Steel Conduit: ANSI C80.1.

C. Fittings: ANSI/NEMA FB 1; steel.

2.6 PLASTIC CONDUIT

A. Description: NEMA TC 2; Schedule 40 PVC.

B. Fittings and Conduit Bodies: NEMA TC 3.

2.7 UNDERGROUND CABLE

1. Okonite

2. General Cable

3. Substitutions: Will be permitted

B. Description: ANSI/NFPA 70, Type UF.

C. Conductor: Copper.

D. Insulation Voltage Rating: 600 volts.

2.8 WIRING CONNECTORS

A. Split Bolt Connectors:

1. Kearney

2. Teledyne Penn-Union

B. Solderless Pressure Connectors:

1. Cadweld

2. Burndy

C. Compression Connectors:

1. Kearney

2. Teledyne Penn-Union

E. Cable/Wire size shall be sized to allow no more than a 5% voltage drop between the pump motor and the electrical service entrance panel. 8 gauge wire shall be used for the proposed 1.5HP pump motor.

PART 3 EXECUTION

3.1 EXAMINATION

A. Verify that equipment is ready for electrical connection, wiring and energization.

B. Verify power source.

3.2 INSTALLATION

A. Install Products in accordance with manufacturer's instructions.

B. Ground electrical equipment in accordance with ANSI/NFPA 70.

C. Make electrical connections in accordance with manufacturer's instructions.

D. Connect the pressure system circuit to the main circuit load center panel board.

E. All electrical work shall be certified by a State of California licensed electrician.

3.3 CONDUIT

A. Requirements:

1. Underground Installation: Schedule 40 PVC

2. Above grade: Rigid steel

3. Minimum Size: 1 inch

B. Mechanically cut conduit with pipe cutters, saws or abrasive wheels only. de-burr cut ends.

C. Immediately before joining pipe, clean pipe ends to be joined.

D. Underground cable shall be installed in PVC conduit under the enclosure pressure system to 2 feet outside of base.

3.4 UNDERGROUND CABLE

A. Protect exposed cable from damage.

B. See Section 02200 for trenching and backfilling.

C. Cable shall be buried a minimum of 18 inches.

3.5 TESTS

A. Submersible Cable: Test for leakage or shorts with a megohmmeter.

Megohmmeter readings shall be 2 megohms or greater.

END OF SECTION 16100

Amend #2
Revised Bid Schedule
Section Changes
16100 Electrical (amend #2)
Exhibit 12 - WATER CONNECTION TO (E) WM Layout1 (1)
Exhibit 13- Well Log from Existing Well #1