A10 Sections B - M.v2.pdf

PDF 544 KB Posted

Attached to
Job Corps Pine Ridge Building 511 – Dorm Siding
Solicitation number
12970225R0002
Issued by

About this file

This document is a comprehensive solicitation for a construction project to rehabilitate Building 511 at the Pine Ridge Job Corps Civilian Conservation Center in Nebraska. The project involves installing new siding, sheathing, insulation, flashing, roof modifications, window and door removal/reinstallation, gutter and downspout work, deck removal, and other exterior tasks. The solicitation is a total small business set-aside with an estimated contract value between $500,000 and $1,000,000, to be awarded as a firm fixed-price contract with a performance period of approximately 150 calendar days.

Key dates include a site visit on 18 December 2024, a pre-proposal conference on 13 January 2025, a question submission cutoff of 17 January 2025, and proposal submissions due by 31 January 2025 at 2359 MT. Offerors must have an active SAM.gov registration and provide a 20% bid bond. The contract will be awarded by the USDA Forest Service, with the project located approximately 13 miles south of Chadron, Nebraska. Evaluation will use a tradeoff process considering past performance, experience, technical approach, and price as equally important factors.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No: 12970225R0002 Project Name: JC Pine Ridge Building 511 Dorm Siding Page 1 of 52

FAC 2024-03 February 23, 2024

Table of Contents

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

B.2 SCHEDULE NOTES

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

C.2 PROJECT LOCATION

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

C.4 TECHNICAL SPECIFICATIONS

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

F.2 OTHER REQUIREMENTS ..................................... Error! Bookmark not defined.

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

G.2 OTHER REQUIREMENTS ..................................... Error! Bookmark not defined.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

H.2 OTHER REQUIREMENTS ..................................... Error! Bookmark not defined.

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 ATTACHMENTS

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 2 of 52

OTHER STATEMENTS OF OFFERORS OR RESPONDENTS

K.1 PROVISIONS

SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR

RESPONDENTS

L.1 PROVISIONS

SECTION M--EVALUATION FACTORS FOR AWARD

M.1 PROVISIONS

M.2 PROPOSAL EVALUATION ................................... Error! Bookmark not defined.

M.3 TECHNICAL EVALUATION FACTORS ............. Error! Bookmark not defined.

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 3 of 52

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

The Schedule of Items is provided as Attachment J.1. Contractor shall complete the Schedule of Items and submit it as part of their offer.

B.2 SCHEDULE NOTES

a) Offeror must fill in the Unit price only. The spreadsheet is formatted to auto populate price.

b) Bonding is required. Contractor shall include bonding premium costs as a flat rate.

Identify the percentage here _______.

c) Items labeled as optional are not required to be exercised by the government. If exercised, the contractor will be required to perform the optional work in accordance with the terms and conditions of this contract. Contractor shall provide costs as part of the proposal as it will be evaluated for award consideration.

d) One award will be made from this solicitation, contractors must submit pricing for all items.

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 4 of 52

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

The project involves the rehabilitation of Building 511 at the Pine Ridge Job Corps Civilian Conservation Center in Dawes County, Nebraska. The work includes siding, sheathing, insulation, flashing installation, roof modifications, window and door removal and re-installation, gutter and downspout work, deck removal, and other exterior tasks.

C.2 PROJECT LOCATION

This project is located at the Pine Ridge Job Corps Center campus located approximately 13 miles south of Chadron, Nebraska. The address is 15710 South Highway 385, Chadron, Nebraska 69337

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

In accordance with FAR 36.204, the estimated price range of this construction project is between $500,000 and $1,000,000.

C.4 TECHNICAL SPECIFICATIONS

The Technical Specifications and Drawings are provided as Attachments J2 and J3, respectively.

452.211-72 Statement of Work/Specifications (FEB 1988) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

452.211-73 Attachments to Statement of Work/Specifications (FEB 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

C.5 BIO-BASED / SUSTAINABLE PRODUCTS

The contractor must comply with the Agriculture Act of 2014; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Farm Security and Rural Investment Act of 2002 9FSRIA), 7 U.S.C. 8102; the Federal Acquisition Regulation; Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy and Economic Performance”, dated October 2, 2009; EO 13423, “Strengthening Federal Environmental, Energy and Transportation Management”, dated January 24, 2007; and Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 5 of 52

February, 2012 to provide biobased products. All supplies and materials shall be of a type and quantity that conform to applicable Federal specifications and standards, and to the extent feasible and reasonable; include the exclusive use of biobased and recycled products.

In the performance of this contract, the Contractor shall make maximum use of biobased oils and lubricants that are designated by the United States Department of Agriculture unless the product cannot be acquired: (1) Competitively within a time frame providing for compliance with the contract performance schedule; (2) meeting contract performance requirements; or (3) at a reasonable price. Information about these products is available at http://sftool.gov/green-products/1/construction-materials.

The Federal Acquisition Regulation (FAR) requires Contractors to report the purchase of biobased products under service and construction contracts during the previous Government fiscal year (October 1 thru September 30) and to submit this report no later than October 31 of each year during contract performance and at the end of contract performance (as applicable).

Information about this requirement is available at https://www.biopreferred.gov/BioPreferred/faces/catalog/Catalog.xhtml#.

http://sftool.gov/green-products/1/construction-materials https://www.biopreferred.gov/BioPreferred/faces/catalog/Catalog.xhtml

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 6 of 52

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 7 of 52

SECTION E--INSPECTION AND ACCEPTANCE

E-1: GENERAL

All work shall be conducted under the general direction of the Contracting Officer or designated representative(s) and is subject to Government inspection and testing at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

E-2: FINAL INSPECTION

A walk-thru inspection shall be scheduled PRIOR to the final inspection so major discrepancies found can be corrected prior to the scheduled completion date. The Contractor shall schedule the final inspection by contacting the COR or designated representative in advance of the contract completion date.

E.3 CLAUSES

52.246-12 Inspection of Construction (AUG 1996) 52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements (AUG 1996)

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 8 of 52

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

52.236-15 Schedules for Construction Contracts (APR 1984) 52.242-14 Suspension of Work (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 150 calendar days* from the notice to proceed effective date.

*If awarded, the optional item(s) will be exercised within 120 calendar days after contract award date via written bi-lateral contract modification. The contractor will have 60 calendar days after the option item(s) have been exercised to complete the work under the optional items, which include site clean-up and demobilization.

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 9 of 52

SECTION G--CONTRACT ADMINISTRATION DATA

G-1: GOVERNMENT REPRESENTATIVES

Shawn Atkinson shall serve as the Contract Specialist administering this contract and is the point of contact on all things concerning this contract. The Contract Specialist can be reached at shawn.atkinson@usda.gov.

The Contracting Officer’s Representative (COR) will be William Knaack, reachable at William.knaack@usda.gov or 262-317-9715. The COR delegated authority, responsibilities and contact information will be defined on a delegation letter issued after contract award.

The signing Contracting Officer (CO) will be appointed, and his/her contact information will be provided upon award of the contract. The Contracting Officer has full warrant authority over all contract issues.

G-2: INVOICING REQUIREMENTS

All invoices are to be submitted via the electronic Invoice Processing Platform (IPP) System.

The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice Processing Platform (IPP). The contractor must follow the instructions on how to register and submit invoices via IPP as prescribed in previous communications from USDA and Treasury.

This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm Ensure your company has registered at https://www.ipp.gov/vendors/enrollment-vendors.htm to establish your account. Offeror must have an established account prior to commencement of work.

Invoice Processing Platform (IPP) does not allow for the contractor to change the description of the line items being invoiced against and therefore an itemized invoice must be uploaded as an attachment(s).

G-2.1 Itemized invoice shall include at a minimum:

Contractor Name and Address Contract, Task Order or Purchase Order numbers Invoice Number Description of Services or work completed.

Date of services or completion.

G-2.2 Certified Payrolls

Certified payrolls for Construction: certified payrolls must also be uploaded as an attachment.

Contractor and all subcontractors, through the contractor, shall furnish all certified mailto:shawn.atkinson@usda.gov mailto:William.knaack@usda.gov https://www.ipp.gov/index.htm https://www.ipp.gov/vendors/enrollment-vendors.htm

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 10 of 52 payrolls covering payments to laborers and mechanics for on-site work.

G-2.3 Final Payment

Following completion and acceptance of the work (including return of Government-furnished property and site cleanup), Final payment will made within 30 calendar days after presentation of a properly executed invoice and if required by the contract, a release of all claims against the Government, other than claims arising under this contracted, in stated amounts, which the Contractor specifically accepts from the operation of the release.

G-3: BONDING

The bid bond is due as part of the contractor’s proposal response to the solicitation.

The contractor awarded this contract must provide the finalized performance and payment bonds within 10 calendar days of receipt of award.

G-4: LABOR INTERVIEWS

The Government (via the Contracting Officer (CO), Contracts Specialist (CS) or Contracting Officer Representative (COR)) may conduct periodic interviews with workers on the job using the Stand Form (SF) 1445, Labor Standards Interview, which may be validated against submitted payroll data.

G-5: CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM

(CPARS)

Contractor Performance Information and Contractor Performance Assessment Reporting System (CPARS) will be used by the Forest Service for evaluating contractor performance.

CPARS is the single USDA-wide system used to collect, maintain, and disseminate contractor performance evaluations to the Past Performance Information Retrieval System (PPIRS). Past performance reporting is required by FAR 42.1502 and 42.1503. The contractor will be notified by email to review evaluation information submitted by the Agency. The contractor will have 60 days to submit comments, rebutting statements, or additional information to the Assessing Official before any evaluation is considered final.

G-6: DEFINITIONS AND CONTRACT ADMINISTRATION DATA

Changes (Modifications) The Contracting Officer is the only person authorized to approve changes in any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract the said authority remains solely with the Contracting Officer. In the event the Contractor effects any such change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof.

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 11 of 52

Contract Award A written award or acceptance of offer mailed or otherwise furnished to the Contractor shall result in a binding contract without further action by either party.

Contracting Officer (CO) Has full authority for the administration of the contract and will personally handle all matters beyond the authority of the CS and COR. Contracting Officers are agents of the Government and are the only officials authorized to enter into any contract or agreement that binds the Government. If you are asked to perform additional work, or make changes not specified in the contract, DO NOT perform the work but immediately notify the Contracting Officer. A Contracting Officer holds a legal warrant, which is a designation of authority to bind the Government.

Contracting Officer’s Representative (COR) The Contracting Officer’s Representative (COR) is the person most responsible for technical advice. The COR is also responsible for maintaining property records, outlining work, material approvals, inspecting work in progress, estimating completed work for partial or progress payments, and conducting pre-final and final inspections. In addition, the COR oversees administrative matters (e.g., submittals, etc.). Also ensures elements of contract requirements are met in accordance with terms and conditions. The COR is NOT authorized to direct changes or bind the Government to any contractual agreement. NOTE: The COR Designation form outlines functions the COR can and cannot perform.

Contract Specialist (CS) - The CS has delegated authority from the Contracting Officer for the administration of the contract and will handle all matters beyond the authority of the COR. Generally, this includes the day-to-day administration of the contract, except for matters pertaining to changes in contract price and time. Any contractual documents that bind the Government must have Contracting Officer approval and signature.

Designation of Authorized Representative of the Contractor The Contractor shall assign a member or employee who will act as Project Manager during the course of this contract or during the course of this project. The official shall be responsible for affording liaison between the contract forces and the contracting offices. This designation shall be in writing and a copy furnished to the Contracting Officer.

Designation of Contracting Officer’s Representative (COR) Designation will be made upon contract issuance and a copy of the designation letters will be furnished to the Contractor. Limits of authority are described in each designation letter.

Government Technical Monitor (GTM) Assists the CO and COR as a technical advisor/inspector to monitor contractor performance. A GTM has no contractual authority. This person exists only to advise the COR in his/her area of expertise.

Notice to Proceed The Contractor shall commence work upon receipt of a properly executed Notice to Proceed.

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 12 of 52

Unauthorized Instructions from Government or Other Personnel The Contractor shall not accept instructions issued by any person employed by the U.S. Government or otherwise other than the Contracting Officer, or the authorized representative of the Contracting Officer acting within the limits of his/her authority.

G.7 CLAUSES

452.215-73 Post Award Conference (NOV 1996) A post award conference with the successful offeror is required. It will be scheduled and held within 10 days after the date of contract award. The conference will be held virtually.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H-1: WAGE DETERMINATION

The wage determination applicable to this work is NE20240079, Dated 04/05/2024.

H-2: PERSONAL PROTECTIVE EQUIPMENT

The contractor shall train workers in the safe operation and use of equipment that the worker may use before the worker begins using such equipment.

Personal protective equipment, including personal protective equipment for eyes, face, head, and extremities shall be provided, used, and maintained in a sanitary and reliable condition wherever it is necessary by reason of hazards or processes encountered which may cause injury or impairment in the function of any part of the body. Defective or damaged personal protective equipment shall not be used.

The contractor shall provide chain saw chaps to each employee who operates a chain saw, at no cost to the employee. These chaps must be approved by an Underwriters Laboratory or meet Forest Service specification 6170-47. The chaps shall cover the full length of the thigh and shall extend to the top of the boot on each leg.

The contractor shall assure that each employee wears foot protection that provides adequate traction and ankle support. Employees operating chain saws shall wear foot protection that is constructed with cut-resistant material which will protect the employee against contact with a running chain saw.

In any area where the worker is exposed to the potential for flying or falling objects, the contractor shall provide a hard hat, at no cost to the employee, and the contractor shall assure that the employee wears the hard hat. The hard hat must meet the minimum requirements of American National Standards Institute (ANSI) standard Z89.1-1997.

The contractor shall provide, at no cost to the employee, eye protection where there is potential for eye injury due to flying objects. This eye protection must meet the minimum requirements of ANSI standard Z87.1-2003.

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 13 of 52

The contractor shall provide, at no cost to the employee, hearing protection where there is a potential for hearing loss due to high intensity noise for example, chain saw operation.

H-3: SAFETY

Safety, Emergency Communications and Evacuation. Contractor is responsible for the safety of the Contractor’s employees including Subcontractors employees, Government employees associated with the project, and any visitors to the site both Government and private. The Contractor shall submit a Project Safety Plan to the Contracting Officer for review prior to commencement of Work. The project safety plan shall comply with the appropriate Nebraska OSHA and Federal OSHA rules and regulations and must include a medical evacuation and emergency communications plan.

H-3.1 Fire Prevention and Control The Contractor is responsible for controlling the work environment to prevent fires to the maximum extent practicable. The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor's agents or employees.

H-4.1.1 Fire Reporting.

The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site. The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor's agents or employees.

H-3.1.2 Open Fires.

In accordance with State and local regulations and pursuant to 36 CFR 261.50a, the following is prohibited on each National Forest or National Grasslands:

Operating or using any internal or external combustion engine on any timber, brush or grass covered land, including trails traversing such land, without a spark an-ester, maintained in effective working order, meeting either

(i) Department of Agriculture, Forest Service Standard 5100-1 a; or

(ii) the 80 percent efficiency level determined according to the appropriate Society of Automotive Engineers (SAE) recommended Practices J335 and J350.

Violation of this regulation and the general prohibitions of 36 CFR 261.3 to .20 is punishable by a fine of not more than $500 or imprisonment for not more than 6 months or both.

H-3.1.3 Smoking.

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 14 of 52

Smoking is prohibited while operating tractors or open-type vehicles, or while walking or working in an area with flammable fuels.

H-4.2 OSHA Standards

The Contractor is subject to all applicable State and Federal OSHA rules and regulations.

At time of award the contractor shall submit to the COR the Material Safety Data Sheets (MSDS) with the intended use of each of the solutions the contractor proposes to use in the performance of work. MSDS sheets shall be supplied to the COR prior to using the items. The contractor shall not use any materials in which the COR determines to be unsuitable for the work, or harmful to the surfaces it is intended to be applied to. This does not relieve the contractor of any damages resulting from the application of such materials. All containers used shall be clearly marked with manufacturer, type of chemical and intended usage. Mixing of chemicals is not allowed.

H-5 SECURITY

Contractor is responsible for the Contractor’s equipment and materials owned or supplied to the site. Lost, damaged, or stolen equipment or materials shall be replaced at the contractor’s expense. All equipment not equipped with a key lock system shall be secured in such a manner as to make it inoperable to the average person at the end of each working day. All hand tools and other equipment shall be secured at the end of each working day.

The contractor shall be responsible for signing, limiting public access, and safety of the public and/or government employees at the site. All refuse shall be properly stored or removed from the site at the end of each day.

H-6: CAMPING

Contractor may use a self-contained travel trailer or recreational vehicle to camp on National Forest System lands near the project site subject to the approval of the Contracting Officer Representative. All waste material must be transported off-site to a station equipped to handle such waste.

H.7 CLAUSES

452.228-71 Insurance Coverage (NOV 1996) (Alternate I) Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 15 of 52

States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(b) General Liability. (1) The Contractor shall have bodily injury liability coverage written on a comprehensive form of policy of at least $500,000 per occurrence. (2) The Contractor shall have property damage liability insurance shall be required in the amount of $100,000 per occurrence.

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 16 of 52

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR) Clauses:

https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:

https://www.acquisition.gov/agar (AGAR clauses begin with 452) FAR and AGAR Deviations to clauses may be viewed at: Policies & Regulations | USDA

52.202-1 Definitions (JUN 2020) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity

(MAY 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights (NOV 2023) (Whistleblower

Guidance to contractor employees) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (JAN 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY

2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN

2020) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or

Provided by Kaspersky Lab Covered Entities (DEC 2023) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video

Surveillance Services or Equipment (NOV 2021) 52.204-27 Prohibition on a ByteDance Covered Application (JUN 2023) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors

Debarred, Suspended, or Proposed for Debarment (NOV 2021) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar https://www.usda.gov/da/ocp/ppd/policies-regulations https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 17 of 52

52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters

(OCT 2018)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.210-1 Market Research (NOV 2021) 52.215-2 Audit and Records -- Negotiation (JUN 2020) 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-8 Utilization of Small Business Concerns (FEB 2024) 52.219-10 Incentive Subcontracting Program (OCT 2014) 52.219-14 Limitations on Subcontracting (OCT 2022)

☒ By the end of the base term of the contract and then by the end of each subsequent option period; or ☐ By the end of the performance period for each order issued under the contract.

52.219-28 Post Award Small Business Program Rerepresentation (FEB 2024) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY

2018) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations

(MAY 2014)

52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately

Specified Pricing Method) (AUG 2018) 52.222-35 Equal Opportunity for Veterans (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC

2010) 52.222-50 Combating Trafficking in Persons (NOV 2021) 52.222-54 Employment Eligibility Verification (MAY 2022) 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026 (JAN

2022) 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) 52.223-1 Biobased Product Certification (May 2024)

52.223-2 Affirmative Procurement of Biobased Products under Service and Construction

Contracts (SEP 2013) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011)

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 18 of 52

52.223-6 Drug-Free Workplace (MAY 2001) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction

Contracts (AUG 2018) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN

2020) 52.223-21 Foams. (JUN 2016) 52.223-23 Sustainable Products and Services (MAY 2024) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.226-1 Utilization of Indian Organizations and Indian-Owned Economic Enterprises

(JUN 2000)

52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-24 Prohibition of Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT

2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-16 Quantity Surveys (APR 1984)

Alternate 1 (APR 1984)

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 19 of 52

52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-6 Subcontracts for Commercial Products and Commercial Services (JAN 2025) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)

Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991) 452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV

1996) 452.236-70 Additive or Deductive Items (FEB 1988) 452.236-71 Prohibition Against the Use of Lead-Based Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archaeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation, and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)

52.217-7 Option for Increased quantity – Separately Priced Line Item (MAR 1989) The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 120 days from notice to proceed.

52.225-9 Buy American Act-Construction Materials (OCT 2022)

(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are https://www.acquisition.gov/far/part-2#FAR_2_101

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 20 of 52 produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all component used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

https://www.acquisition.gov/far/part-25#FAR_25_105

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 21 of 52

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

[Contracting Officer to list applicable excepted materials or indicate "none"]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 22 of 52

(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components.

(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1) (i)Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 23 of 52 does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison Construction Material Description Unit of Measure Quantity Price (Dollars)* Item1

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______ Item 2

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.]

(End of clause)

52.228-11 Individual Surety - Pledge of Assets (FEB 2021) (DEVIATION MAY 2023)

(a) The Contractor shall obtain from each person acting as an individual surety on a performance bond or a payment bond -

(1)A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and

(2) Standard Form 28, Affidavit of Individual Surety, [except that the words “being duly sworn, depose and say” on the Standard Form 28 are replaced with the word “affirm” and the Standard Form 28 is not required to be sworn and notarized in block 12].

(b)The Contracting Officer may release a portion of the security interest on the individual surety's assets based upon substantial performance of the Contractor's obligations under its performance bond. The security interest in support of a performance bond shall be maintained—

(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 (40 U.S.C. 3131). Until completion of any warranty period, or for 1 year following final payment, whichever is later.

https://www.usda.gov/sites/default/files/documents/far-class-deviation-eliminate-hard-copy-original-documents-signatures-notarization-seals-bonds-other-seals.pdf https://www.acquisition.gov/far/part-28#FAR_28_203_1

Project Name: JC Pine Ridge Building 511 Dorm Siding Page 24 of 52

(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.

(3) Other contracts not subject to the requirements of paragraph (b)(1) of this clause. Until completion of any warranty period, or for 90 days following final payment, whichever is later.

(c) A surety's assets pledged in support of a payment bond may be released to a subcontractor or supplier upon Government receipt of a…