Attachment E
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_B_-_Specifications.pdf | ||
| Attachment_C_-_Drawings-Plans.pdf | ||
| Attachment_D_-_WI_DNR_General_Permit.pdf | ||
| Attachment_A_-_Schedule_of_Items.pdf | ||
| 12569R19B0002.pdf | ||
| Attachment_F_-_Davis-Bacon_Wage_Determination.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE ARMY
ST. PAUL DISTRICT, CORPS OF ENGINEERS
180 FIFTH STREET EAST, SUITE 700
Regulatory File No. 2017-02250-JMB
Paul Strong, Forest Supervisor USDA - Forest Service 500 Hanson Lake Road Rhinelander, WI 54501
Dear Mr. Strong :
ST. PAUL, MN 55101-1678
MAY .o 1 :zote
This correspondence is in regard to your pre-construction notification (PCN) requesting Department of the Army authorization to discharge fill material (87 SF or 0.002 acres) onto the bed of Squaw Creek for placement of riprap associated with a culvert replacement. A 20'-span x 1 O'-rise Conspan B-Series type structure will be installed over the existing deteriorated corrugated metal pipe arch culvert. Work for the project will also include a temporary discharge of fill material (274.6 SF or 0.006 ac.) below the OHWM for construction of a temporary access road and cofferdam. The project site is located at Squaw Creek on Forest Road 143/Turner Lake Road in Section 1, Township 39 North, Range 3 East, Price County, Wisconsin .
Certain minor activities are eligible for authorization by general permits, which include Nationwide (NWP) and Regional General (RGP) permits. Your project as shown on the enclosed figures labeled MVP-2017-02250-JMB Pages 1 of 3 through 3 of 3, is authorized as one single and complete project by the Transportation RGP, category 1.
In order for this verification to be valid, you must ensure the work is performed in accordance with the enclosed general permit terms, General Conditions, St. Paul District Regional Conditions, and the Wisconsin Department of Natural Resources' 401 Water Quality Certification Conditions. In addition, this verification is subject to the following special conditions:
1. The permittee is responsible for insuring that whoever performs, supervises, or oversees any portion of the physical work associated with the construction of the project has a copy of, is familiar with , and complies with all the terms and conditions of this permit.
2. All areas below the OHWM temporarily impacted as a result of work for the project shall be restored to preconstruction contours and elevations immediately upon completion of the project. Photographs showing representative areas restored shall be provided to the Corps project manager upon completion of the project.
Photographs may be provided by email to jonathan.m.bakken@usace.army.mil
If your project will require off-site fill material that is not obtained from a licensed commercial facility , you must notify us at least five working days before start of work. A cultural resources survey may be required if a licensed commercial facility is not used.
You are also required to complete and return the enclosed Compliance Certification form within 30 days upon completion of your project in accordance with your permit conditions.
Please mail the completed form to the Corps contact identified in the last paragraph.
Regulatory Branch (File No. 2017-02250-JMB)
This verification is valid until February 20, 2023, unless the general permit is modified, suspended, or revoked. If the work has not been completed by that time, you should contact this office to verify that the permit is still valid. Furthermore, if you commence or are under contract to commence this activity before the date of general permit expiration, modification, or revocation, you will have 12 months from the date of expiration , modification or revocation to complete the activity under the present terms and conditions of the general permit.
Our verification of this permit is based on the project description and construction methods provided in your PCN. You are cautioned that a change in the location or plans may invalidate this verification. Proposed changes should be coordinated with this office prior to construction.
Failure to comply with all terms and conditions of this permit verification invalidates this verification and could result in a violation of Section 301 of the Clean Water Act or Section 10 of the Rivers and Harbors Act. You must also obtain all local, State. and other Federal permits that apply to this project.
No jurisdictional determination was requested or prepared for this project. While not required , you may request a jurisdictional determination from the Corps contact indicated below.
If you have any questions, please contact Jonathan Bakken in our Hayward office at
(651) 290-5884orjonathan.m.bakken@usace.army.mil. In any correspondence or inquiries, please refer to the Regulatory file number shown above.
Enclosures
Sincerely, Jonathan M. Bakken Regulatory Project Manager cc: Tony Baciak, Jr., P.E. , U.P. Engineers & Architects , Inc. (tbaciak@upea.com) Jim Mineau, Hydrologist, United States Forest Service Umineau@fs.fed.us) Patrick Hampston , Civil Engineer, United States Forest Service (phampston@fs.fed.us)
Wendy Henniges State of Wisconsin Wisconsin Department of Natural Resources 715-365-8916 Wendy. Henniges@wisconsin.gov
Wetlands - Squaw Creek - Turner Lake Road/FR143 Culvert Crossing
DISCLAIMER: The information shown on these maps has been obtained from various sources, and are of varying age, reliability and resolution. These maps are not intended to be used for navigation, nor are these maps an authoritative source of information about legal land ownership or public access. No warranty, expressed or implied, is made regarding accuracy, applicability for a particular use, completeness, or legality of the information depicted on this map. For more information, see the DNR Legal Notices web page: http://dnr.wi.gov/legal/3,960
0.1
1:NAD_1983_HARN_Wisconsin_TM
Miles0.10.06
Notes from WDNR Surface Water Data Viewer Map
Legend
Wetland Class Points
Dammed pond
Excavated pond
Filled excavated pond
Filled/drained wetland
Wetland too small to delineate
Filled Points
Wetland Class Areas
Wetland
Upland
Filled Areas
Municipality
State Boundaries
County Boundaries
Major Roads
Interstate Highway
State Highway
US Highway
County and Local Roads
County HWY
Local Road
Railroads
Tribal Lands
Rivers and Streams
Intermittent Streams
Lakes and Open water tbaciak Callout Squaw Creek Culvert Location b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Text Box MVP-2017-02250-JMB Page 1 of 3 b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Typewritten Text MVP-2017-02250-JMB Page 2 of 3 tbaciak Callout Phase 2 Disturbed Area For Temporary Road Widening
2611.61 SF or 0.06 Acres
tbaciak Polygon tbaciak Polygon tbaciak Polygon tbaciak Callout Phase 2 Temporary Impact within OHWM:
39.38 SF or 0.001 Acres
tbaciak Callout Phase 2 Temporary Impact within OHWM:
66.22 SF or 0.002 Acres
b6oprjmb Typewritten Text MVP-2017-02250-JMB Page 3 of 3 b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Typewritten Text b6oprjmb Typewritten Text
COMPLIANCE CERTIFICATION
Regulatory File Number: 2017-02250-JMB
Name of Permittee: United States Forest Service – Paul Strong
County/State: Price County/Wisconsin
Date of Issuance: 1 May 2018
Upon completion of the activity authorized by this permit and any mitigation required by the permit, sign this certification and return it to the Corps contact identified in your verification letter within 30 days.
Please note that your permitted activity is subject to a compliance inspection by a U.S. Army Corps of Engineers representative. If you fail to comply with this permit, you are subject to permit suspension, modification, or revocation.
By signing below, the permittee is certifying that the work authorized by the above referenced permit has been completed in accordance with the terms and conditions of the permit, and any required mitigation was completed in accordance with the permit conditions.
Signature of Permittee Date
St. Paul District Corps of Engineers, Regulatory Branch Transportation Regional General Permit
To qualify for regional general permit (RGP) authorization, the prospective permittee must comply with the following conditions, as applicable, in addition to any category‐specific requirements and project‐specific conditions imposed by the Corps.
1. Compliance: The permittee is responsible for ensuring that whomever performs, supervises or oversees any portion of the physical work associated with the construction of the project has a copy of and is familiar with all the terms and conditions of the RGP and any special (permit‐specific) conditions included in any written verification letter from the Corps. The activity must also comply with any special conditions added by a state, tribe, or U.S. EPA in its Section 401 Water Quality Certification, or by the state in its Coastal Zone Management Act consistency determination. The permittee is ultimately responsible for ensuring compliance with all the terms and conditions of the RGP. Any authorized structure or fill must be properly maintained, including maintenance to ensure public safety and compliance with applicable RGP general conditions, as well as any activity‐specific conditions added by the Corps to an RGP authorization.
2. Compliance Certification: Each permittee who receives an RGP verification letter from the Corps must provide a signed certification documenting completion of the authorized activity and implementation of any required compensatory mitigation. The Corps will provide the permittee the certification document with the RGP verification letter. The completed certification document must be submitted to the Corps within 30 days of completion of the authorized activity or the implementation of any required compensatory mitigation, whichever occurs later.
3. Site Inspection: The permittee shall allow representatives from the Corps to inspect the proposed project site and the authorized activity to ensure that it is being, or has been, constructed and maintained in accordance with the RGP authorization.
4. Migratory Birds and Bald and Golden Eagles: The permittee is responsible for ensuring their action complies with the Migratory Bird Treaty Act and the Bald and Golden Eagle Protection Act. The permittee is responsible for contacting appropriate local office of the U.S. Fish and Wildlife Service (FWS) to determine applicable measures to reduce impacts to migratory birds or eagles, including whether “incidental take” permits are necessary and available under the Migratory Bird Treaty Act or Bald and Golden Eagle Protection Act for a particular activity.
5. Endangered Species:
a. No activity is authorized under this RGP which is likely to directly or indirectly jeopardize the continued existence of a federally threatened or endangered species or a species proposed for such designation, as identified under the Endangered Species Act (ESA), 50 CFR 402, or which will directly or indirectly destroy or adversely modify the critical habitat of such species. No activity is authorized under the RGP which “may affect” a listed species or critical habitat, unless ESA Section 7 consultation addressing the effects of the proposed activity has been completed. Direct effects are the immediate effects on listed species and critical habitat caused by the RGP activity. Indirect effects are those effects on listed species and critical habitat that are caused by the RGP activity and are later in time, but still are reasonably certain to occur.
b. As a result of formal or informal consultation with the FWS, the Corps may add species‐specific permit conditions to the RGP verification.
c. Information on the location of federally threatened and endangered species and their critical habitat can be obtained directly from the offices of the FWS on their web page at www.fws.gov/ipac.
6. Calcareous Fens: The permittee may not complete regulated activities in a calcareous fen, unless the Wisconsin Department of Natural Resources has authorized the proposed regulated activity, or the Minnesota Department of Natural Resources has approved a calcareous fen management plan specific to the project. A list of known Minnesota calcareous fens can be found at: http://files.dnr.state.mn.us/eco/wetlands/calcareous_fen_list.pdf.
7. Wild and Scenic Rivers: The permittee may not complete regulated activities which may affect or are located in a designated portions of the National Wild and Scenic River System, or in a river officially designated by Congress as a “study river” for possible inclusion in the system while the river is in an official study status, unless the appropriate Federal agency with direct management responsibility for such river, has determined in writing that the proposed activity will not adversely affect the Wild and Scenic River designation or study status.
8. Historic Properties, Cultural Resources:
a. No activity which may affect historic properties listed or potentially eligible for listing on the National Register of
Historic Places is authorized until the requirements of Section 106 of the National Historic Preservation Act (Section 106) have been satisfied. If PCN is required for the proposed activity, the federal project proponent should follow their own procedures for complying with the requirements of Section 106 and provide documentation of compliance with those requirements.
b. Information on the location and existence of historic and cultural resources can be obtained from the State Historic Preservation Office, Tribal Historic Preservation Offices, and the National Register of Historic Places.
c. Rock or fill material used for activities authorized by this permit must either be obtained from existing quarries or, if a new borrow site is excavated to obtain fill material, the Corps must be notified prior to the use of the new site to determine whether a cultural resources survey of the site is necessary.
9. Discovery of Previously Unknown Remains and Artifacts: If any previously unknown historic, cultural or archeological remains and artifacts are discovered while accomplishing the activity authorized by this permit, the Corps must immediately be notified of the findings. To the maximum extent practicable, construction activities must avoided that may affect the remains and artifacts until the required coordination has been completed. The Corps will initiate the federal, tribal, and state coordination required to determine if the items or remains warrant a recovery effort or if the site is eligible for listing in the National Register of Historic Places.
10. Burial Sites: Burial sites, marked or unmarked, are subject to state law (Wisconsin Statute 157.70 and Minnesota Statutes 306 and 307.08). Native American burial sites on federal or tribal land are subject to the provisions of Native American Graves Protection and Repatriation Act (NAGPRA). Regulated activities may not result in disturbance or removal of human remains until disposition of the remains has been determined by the appropriate authority under these laws, and the work is authorized by the Corps. Regulated activities which result in an inadvertent discovery of human remains must stop immediately, and the Corps, as well as the appropriate state and tribal authority, must be notified. Regulated work at inadvertent discovery sites requires compliance with state law and NAGPRA, as appropriate, prior to re‐starting work.
11. Federally Authorized Corps Civil Works projects: A permittee is not authorized to begin any regulated activities described in this RGP if activities will alter or temporarily or permanently occupy or use a Corps federally authorized civil works project, unless the appropriate Corps office issues a Section 408 permission to alter, occupy, or use the Corps civil works project (pursuant to 33 U.S.C. 408) and the Corps issues written RGP verification. Examples of federal projects include, but are not limited to, works that were built by the Corps and are locally maintained (such as local flood control projects) or operated and maintained by the Corps (such as locks and dams).
12. Dam Safety: Permittees are not authorized to begin regulated activities unless they are able to demonstrate that the structures, when appropriate, comply with applicable state dam safety criteria or have been designed by qualified persons. The Corps may require documentation that the design has been independently reviewed by similarly qualified persons, and appropriate modifications are made to ensure safety.
13. Suitable Material: No activity may use unsuitable material (e.g., trash, debris, car bodies, asphalt, etc.). Material used for construction or discharged must be free from toxic pollutants in toxic amounts (see Section 307 of the Clean Water Act).
14. Restoration of Temporary Impacts: All temporary impacts in waters of the US, including discharges resulting from side casting material excavated from trenching, that occur as a result of the regulated activity must be fully contained with appropriate erosion control or containment methods, be restored to preconstruction contours and elevations, and as appropriate, revegetated with native, non‐invasive vegetation. In temporarily excavated wetlands, the top 6 to 12 inches of the excavation should normally be backfilled with topsoil originating from the wetland. No temporary excavation area, including, but not limited to trenches, may be constructed or backfilled in such a manner as to drain waters of the United States (e.g., backfilling with extensive gravel layers, creating a French drain effect).
15. Duration of Temporary Impacts: Temporary impacts in waters of the U.S., including wetlands, must be avoided and limited to the smallest area and the shortest duration required to accomplish the project purpose.
a. Unless otherwise conditioned in a Corps RGP verification, temporary impacts may not remain in place longer than
90 days between May 15 and November 15. Before those 90 days have elapsed, all temporary discharges must be removed in their entirety.
b. If the temporary impacts would remain in place for longer than 90 days between May 15 and November 15, the PCN must include a request for a waiver from this condition and specify how long temporary impacts will remain and include a restoration plan showing how all temporary fills and structures will be removed and the area restored to pre‐project conditions. The permittee must remove the temporary impacts in their entirety in accordance with the activity authorized their permit verification.
16. Best Management Practices (BMPs): To minimize adverse effects from soil loss and sediment transport that may occur as a result of the authorized work, appropriate BMPs must be implemented and maintained. For authorized work above an OHWM the BMPs must remain in place until the affected area is stabilized with vegetation or ground cover.
For all authorized work below an OHWM, BMPs are required and must prevent or minimize adverse effects (e.g., total suspended solids or sedimentation) to the water column outside of the authorized work area. Heavy equipment working in wetlands or mudflats must be placed on mats, or other measures must be taken to minimize soil disturbance. All BMPs must be inspected and properly maintained following storm events to ensure they are operational. All exposed slopes and stream banks must be stabilized within 24 hours after completion of all tributary crossings.
17. Culverts and Crossings: Unless an RGP verification authorizes otherwise, replacement and installation of culverts or crossings authorized by an RGP are to follow (or be restored to) the natural alignment and profile of the tributary. The culverts or bridges must adequately pass low flow and bankfull events, bedload, sediment load, and provide site‐ appropriate fish and wildlife passage. Example design elements include recessing single culverts to accommodate natural bankfull width and adjusting additional culvert inverts at an elevation higher than the bankfull elevation.
18. Aquatic Life Movements: No regulated activity may substantially disrupt the necessary life cycle movements of those species of aquatic life indigenous to the waterbody, including those species that normally migrate through the area, unless the activity's primary purpose is to impound water.
19. Spawning Areas: Activities in spawning areas, during spawning seasons, must be avoided to the maximum extent practicable. Activities that result in the physical destruction (e.g., through excavation, fill, or downstream smothering by substantial sedimentation) of a designated or known spawning area are not authorized.
20. Riprap: For RGP categories that allow for the use of riprap material for bank stabilization, only rock must be used and it must be of a size sufficient to prevent its movement from the authorized alignment by natural forces under normal or high flows.
21. Pollutant or Hazardous Waste Spills: The permittee is responsible for removing pollutants and hazardous materials and for minimizing any contamination resulting from a spill in accordance with state and federal laws. In accordance with applicable state, tribal and federal laws and regulations, if a spill of any potential pollutant or hazardous waste occurs, it is the responsibility of the permittee to immediately notify the National Response Center at 1‐800‐424‐8802 or www.nrc.uscg.mil AND
IN WISCONSIN: the WI DNR Spills Team at 1‐800‐943‐0003, or IN MINNESOTA: the Minnesota State Duty Officer at 1‐800‐422‐0798.
22. Clean Construction Equipment: All construction equipment must be clean prior to entering and before leaving the work site in order to prevent the spread of invasive species.
23. Navigation: No activity may cause more than a minimal adverse effect on navigation. Any safety lights and signals prescribed by the U.S. Coast Guard, through regulations or otherwise, must be installed and maintained at the permittee's expense on authorized facilities in navigable waters of the US. The permittee understands and agrees that, if future operations by the United States require the removal, relocation, or other alteration, of the structure or work herein authorized, or if, in the opinion of the Secretary of the Army or his authorized representative, said structure or work shall cause unreasonable obstruction to the free navigation of the navigable waters, the permittee will be required, upon due notice from the Corps, to remove, relocate, or alter the structural work or obstructions caused thereby, without expense to the United States. No claim shall be made against the United States on account of any such removal or alteration.
24. Fills Within 100‐Year Floodplains: The regulated activity must comply with applicable FEMA‐approved state or local floodplain management requirements.
25. Access Roads: Access roads must be sized appropriately and must be constructed in such a way to minimize adverse effects on waters of the US and elevations must be as near as practicable to pre‐construction contours and elevations (e.g., at grade corduroy roads or geotextile/gravel roads). All access roads constructed in waters of the US must be properly bridged or culverted to maintain surface flows.
26. Tributary Modifications. When stream channelization is performed with the construction of a road crossing, both activities should be considered as a single and complete project, which may be authorized by another form of authorization. The Corps does not consider installation of a culvert in a stream bed as stream channelization as long as those activities are conducted in accordance with the terms of the categories described in this permit. Unless the general permit verification authorizes otherwise, replacement and installation of culverts or crossings authorized are to follow (or be restored to) the natural alignment and profile of the tributary, see General Condition 17. Culverts and Crossings.
27. Section 401 Clean Water Act, Water Quality Certification: All regulated activities authorized by the Transportation RGP pursuant to Section 404 of the Clean Water Act require Section 401 Clean Water Act certification or waiver to be considered valid.
28. Transfer of Regional General Permit Verifications: If the permittee sells the property associated with a regional general permit verification, the permittee may transfer the regional general permit verification to the new owner by submitting a letter to the appropriate Corps district office to validate the transfer. A copy of the regional general permit verification must be attached to the letter, and the letter must contain the following statement and signature “When the structures or work authorized by this regional general permit are still in existence at the time the property is transferred, the terms and conditions of this regional general permit, including any special conditions, will continue to be binding on the new owner(s) of the property. To validate the transfer of this regional general permit and the associated liabilities associated with compliance with its terms and conditions, have the transferee sign and date below.”
(Transferee)
(Date)