PART I ‐ SCHEDULE OF ITEMS

SECTION B – SERVICES AND PRICES

FR 143 over Squaw Creek Culvert Replacement Park Falls Ranger District

Chequamegon‐Nicolet National Forest

Price County, Wisconsin

B‐ 1 ‐ SCHEDULE OF ITEMS

ITEM

NO.

DESCRIPTION

PAY

UNIT

EST.

QTY.

UNIT

PRICE

TOTAL

PRICE

15101

Mobilization Lump Sum 1

15201

Construction Survey and Staking, Method 1, Tolerance Mile 0.21

Class B

15702

Silt Fence Foot 1000

20101

Clearing and Grubbing, Disposal Method F Acres 0.1

20301

Removal of Pipe Culvert Each 2

20401 Roadway Excavation Cubic Yard 47 $________ $________

20404

Unclassified Borrow, Compaction Method 2 Cubic Yard 350

20415

Waste Excavation Cubic Yard 289

20801

Structure Excavation Cubic Yard 986

20803

Structural Backfill Cubic Yard 290

20805

Dewatering Lump Sum 1

25101 Riprap, Class IV Cubic Yard 30 $________ $________

25116

Geotextile, Type IV, Class 1 Square Yard 100

30103

Aggregate Base, Grading D, Compaction Method B Cubic Yard 100

30118

Screened Aggregate, Grading P, Compaction Method B

Cubic Yard 72

40312 Asphalt Cement, Wisconsin State DOT Grade LT Ton 110 $________ $________

55114 Steel Sheet Piles, Temporary Lump Sum 1 $________ $________

55115 Steel Sheet Piles, Left‐in‐Place Lump Sum 1 $________ $________

55304 Precast Concrete Footings Each 2 $________ $________

60205 Precast Three‐Sided Culvert, 20‐0 span x 12‐0 rise With Wingwalls and Headwalls, Load Rating = HL‐93

Foot 38 $________ $________

60508 Granular Backfill Cubic Yard 203 $________ $________

62503 Seeding, Dry Method Lump Sum 1 $________ $________

62509 Mulching, Dry Method Lump Sum 1 $________ $________

63501 Temporary Traffic Control Lump Sum 1 $________ $________

64804 Streambed Simulation Rock, Bed Class 8 Cubic Yard 40 $________ $________

B‐2 ‐ NOTE: Payment for bond premiums in accordance with Clause 52.232‐5, Payments under Fixed‐Price Construction

Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization.

Payment will be made on actual work performed as described in FP‐14 109.01 unless otherwise noted.

1. The Standard Specifications for Construction of Roads and Bridges on Federal Highway Project FP‐14 edition has been used for this contract. Copies of this book are available at the USFS engineering office.

Contractor Acceptance Statement: By signing the offer, the Contractor agrees to all terms, conditions, and provisions included in the solicitation and agrees to furnish any awarded items at the price set in the schedule unless otherwise excepted as follows: _______________________________________________________________.