This solicitation seeks proposals for the Fishlake National Forest Supervisor's Office Renovations project. The project involves remodeling an existing office building and updating the surrounding site, including parking lots, lighting, fencing, landscaping, and a new pavilion. Proposals are due by May 19, 2022 and the project is expected to be completed within 270 calendar days of award. Offerors must provide pricing for all base line items and have the option to bid on an asphalt slurry seal. The work will be performed onsite at the Forest Supervisor's Office in Richfield, Utah.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q and A Fishlake NF Supervisory Office 5.18.22.docx | DOCX document | |
| Amendment 2_Fishlake.NFSO.rennovations.Addendum.5.16.2022.docx | DOCX document | |
| Amendment 2_ESheets.FishlakeSO - Correct.pdf | ||
| Amendment 2.pdf | ||
| Site Visit Sign In Sheet.pdf | ||
| Amendment 1-Extend Closing Date.pdf | ||
| Attach_4_Determination of Responsibility.pdf | ||
| ATTACHMENT 3_WAGE DETERMINATION.pdf | ||
| ATTACHMENT 1_SPECS.FISHLAKESO.FINAL.3.2.2022.pdf | ||
| ATTACHMENT 2_DRAWINGS.FINAL.FISHLAKE.4.11.2022.pdf | ||
| Attach_3_Wage Determination.pdf | ||
| Attach_2_Paintrock Road FSSS.pdf | ||
| Attach_1_Paintrock Road Improvements Drawings.pdf | ||
| 1240LT22R0029.pdf | ||
| Attach_4_Determination of Responsibility.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROCUREMENT & PROPERTY SERVICES INSTRUCTIONAL COVER SHEET
ISSUING OFFICE:
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
INTERMOUNTAIN REGION PPS/CSA #8
1249 S VINNELL WAY, SUITE 200 BOISE,
ID 83709
SOLICITATION NO. 1240LT22R0035
OFFERS ARE SOLICITED FOR: FISHLAKE SUPERVISOR'S OFFICE RENNOVATIONS
IMPORTANT – NOTICE TO OFFEROR:
1. This is a complete copy. Information and instructions for submission of proposals as well as contract provisions and specifications are contained in this OFFEROR REFERENCE COPY. This copy should be retained by offerors.
2. Note: An offer guarantee (Bid Bond) IS REQUIRED. Performance and Payment Bonds will be required of the successful offeror. (See Section I, FAR Clause 52.228-15.)
3. All questions regarding this solicitation must be in writing and addressed to the Contracting Officer email Tanya Spanfellner-tanya.spanfellner@usda.gov.
All questions must be received no later than MAY 11,2022 by 1630 MT to be considered prior to solicitation close date. SITE VISIT MAY 4, 2022 at 10AM, Fishlake NF Supervisor Office, 115 E 900 N Richfield Utah, 84701
AT A MINIMUM, OFFEROR SHALL SUBMIT THE FOLLOWING DOCUMENTS BACK WITH THEIR
RESPONSE TO THIS SOLICITATION:
1. SF-1442, Complete, date, and sign.
Provide SAM UNIQUE ENTITY IDENTIFER and email address. Block 14
2. Representations and Certifications Section K 52.204-8. You must complete Representations and
Certifications via SAM, please only submit a response to Paragraph (b)(1) Pg. 30.
3. Provide information required Section L Addenda to FAR clause 52.215-1, paragraph c Pg. 39
4. Fill out the pricing schedule for all items Section B-Schedule, Page 5-6
5. Provide Liability insurance verification
6. Complete Determination of responsibility, Attach 4
7. Submit Bid Guarantee 52.228-1-20% of your price
PROPOSALS ARE DUE MAY 19,2022 BY 1630 MT
Return to:
NAME: TANYA SPANFELLNER
Email:tanya.spanfellner@usda.gov Solicitation No. 1240LT22R0035
ONLY EMAIL PROPOSALS ARE BEING ACCPETED
Please keep a copy of your quote for your records.
NO PAPER SOLICITATIONS SHALL BE ISSUED.
IT IS THE OFFERORS RESPONSIBILITY TO WATCH FOR ANY AND ALL AMENDMENTS TO THE
SOLICITATION
mailto:Spanfellner-tanya.spanfellner@usda.gov
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
1060031
USDA-FS CSA INTERMOUNTAIN 8
1249 S VINNELL WAY SUITE 200
BOISE ID 83709
40LT
TANYA SPANFELLNER 208-258-1041
1x 04/19/2022
1240LT22R0035
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
FISHLAKE SUPERVISOR'S OFFICE RENNOVATIONS
Pre-Bid/ Pre-Proposal Conference
Date: May 4, 2022
Time: 10 AM
Location: Fishlake NF Supervisor Office, 115 E 900 N Richfield Utah, 84701
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 360 calendar days and complete it within ________________ ________________ calendar days after receiving
Section F, FAR 52.211-10
05/19/2022
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
USDA-FS CSA INTERMOUNTAIN 8
1249 S VINNELL WAY SUITE 200
BOISE ID 83709
40LT
TANYA I. SPANFELLNER
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
SAM Unique Entity ID:_______________________________
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 45
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
1240LT22R0035
Delivery Location Code: 8462
FISHLAKE NATIONAL FOREST
115 EAST 900 NORTH
RICHFIELD UT 84701 US
Period of Performance: 08/01/2022 to 07/31/2023
0001 Remodel of the Fishlake National Forest 1 EA
Supervisors Office.
0002 Option 1 1 EA
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Table of Contents
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS
B.2 SCHEDULE NOTES
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
C.2 PROJECT LOCATON
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
C.4 TECHNICAL SPECIFICATIONS
SECTION D--PACKAGING AND MARKING
D-1 PACKING AND MARKING
D-2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
SECTION E--INSPECTION AND ACCEPTANCE
E.1 CLAUSES
SECTION F--DELIVERIES OR PERFORMANCE
F.1 CLAUSES
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 OTHER REQUIREMENTS
SECTION H--SPECIAL CONTRACT REQUIREMENTS
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS
J.1 ATTACHMENTS
PART IV--REPRESENTATIONS AND INSTRUCTIONS
SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND
OTHER STATEMENTS OF OFFERORS OR RESPONDENTS
K.1 PROVISIONS
SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR RESPONDENTS
L.1 PROVISIONS
SECTION M--EVALUATION FACTORS FOR AWARD
M.1 PROVISIONS
M.2 PROPOSAL EVALUATION
M.3 TECHNICAL EVALUATION FACTORS
Solicitation No.: 1240LT22R0035
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS
Item Supplies/Services Method of Meas
Unit QTY Unit Price Total Price
011900 Mobilization LSQ LS 1 $ $ 017320-1 Site Demolition LSQ LS 1 $ $ 010250 Construction Staking LSQ LS 1 $ $ 023701 Sedimentation and Errosion
Control
LSQ LS 1 $ $
026460-1 Dumpster Pad and Screen Enclosure
AQ EA 1 $ $
000501 Remodel Supervisors Office LSQ LS 1 $ $ 260500-1 Site Electrical-Lighting and
Electrical Distribution System
LSQ LS 1 $ $
033545-1 4” Concrete-Sidewalks, Slab DQ SF 1969 $ $ 033545-2 “L” Type Curb and Gutter DQ LF 125 $ $ 033545-3 Reverse Pan Curb and
Gutter
DQ LF 139 $ $
101400 Exterior Signs (Aluminum on Galv. Steel Tube Posts)
AQ EA 4 $ $
101420 Administrative Identification Sign-AS(HDPE)
LSQ LS 1 $ $
101425 3-Panel Log Stanchion Bulletin Board
LSQ LS 1 $ $
129300-1 Picnic Table AQ EA 2 $ $ 129300-2 Bike Rack AQ EA 2 $ $ 129300-3 Bench AQ EA 1 $ $ 136000 Shelter and Concrete Slab LSQ LS 1 $ $ 312100 Project Site Preparation and
Grading (Excludes All Work within 5’of the Building Roof Line)
LSQ LS 1 $ $
321200-1 Hot Mix Asphalt Pavement DQ Ton 708 $ $ 321204-1 Crushed Aggregate Base
Course-Grading “C” (For under Pavements)
DQ CY 36 $ $
321713 Bollards AQ EA 2 $ $ 322625-1 Wheelstops-6-Foot Concrete AQ EA 25 $ $ 322640-1 Pavement Markings-Parking
Stall Lines 4”Solid Yellow Non Reflective
DQ LF 6540 $ $
322640-2 Pavement Markings-
Accessible Parking Symbol
AQ EA 4 $ $
322706-1 Pulverize Asphalt Pavement and Remove
DQ SY 4337 $ $
323113-1 6 ft. Chainlink Fence DQ LF 175 $ $ 323113-2 Pedestrian Gate-5 Foot Wide
Opening
AQ EA 1 $ $
323113-3 Automatic Slide Gate- 20 Foot Wide Opening
AQ EA 1 $ $
323119-1 Wrought Iron/Tubular Steel Security Fence
DQ LF 180 $ $
323113-4 Pedestrian Gate- 5 Foot Wide Opening
AQ EA 1 $ $
328000 Landscape Irrigation System LSQ LS 1 $ $ 329212 Landscape Concrete Edger
Curbing
AQ LF 140 $ $
329310-1 Exterior Plants and Landscape Boulders
LSQ LS 1 $ $
329310-2 Topsoil-Planting Media AQ CY 15 $ $ 329400 Landscape Decorative
Gravel, Flagstone Steppers and Weed Barrier
LSQ LS 1 $ $
TOTAL BASE $
BID Option-B
321214 Asphalt Slurry Seal (to be applied 6-9 months after asphalt has been placed)
DQ SY 4337 $ $
322640-1 Pavement Markings-Parking Stall Lines 4” Solid Yellow Non Reflective
DQ LF 6540 $ $
TOTAL
OPTION-B
TOTAL BASE + OPTION-B $
B.2 SCHEDULE NOTES
* Designated Method of Measurement:
DQ – Designed/Contract Quantities, AQ - Actual Quantities, LSQ - Lump Sum Quantities, SQ - Staked Quantities
a) Items labeled as optional are not required to be exercised by the government. If exercised, the contractor will be required to perform the optional work in accordance with the terms and conditions of this contract.
b) One award will be made from this solicitation, contractors must submit pricing for all items.
c) Payment for bond premiums in accordance with FAR Clause 52.232-5, Payments Under Fixed-Price
Construction Contracts, shall not be in addition to the contract price. Include bond payments under
151.01 – Mobilization.
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
A. This project consists of remodeling an existing facility for the Fishlake NF Supervisor’s and Richfield Ranger District Office. The facilities are owned and operated by the United States Forest Service as a part of the Fishlake National Forest.
1. The construction work involves remodeling an existing single story wood framed office and updating the site, parking lots, lighting, fencing, gates, landscaping and installing a pavilion.
Carefully review this section and the Schedule of Items while bidding on the work to be done.
2. A general description of the work follows:
3. Base Bid Items:
a. Base Bid Item #1: Mobilization and Bonding. Refer to specification section 001190.
b. Base Bid Item #2: Site Demolition as shown in the drawings and described in specification section 017320
c. Base Bid Item #3: Construction staking as required to construct all components of the work shown in the drawings and described in specification section 010250.
d. Base Bid Item #4: Sedimentation and Erosion Control as required to construct all components of the work shown in the drawings and described in specification section 023701.
e. Base Bid Item #5: Construct dumpster pads and enclosure as shown on the drawings and described in specification section 026460.
f. Base Bid Item #6: Demo and construct office building improvements including concrete, wood framing, as shown in drawings and described in detail in specification section 000501.
g. Base Bid Item #7: Site lighting and electrical. 260500
h. Base Bid Item #8: 4” concrete sidewalks. 033545-1
i. Base Bid Item #9: Type L curb and gutter 033545-2
j. Base Bid Item #10: Reverse pan curb and gutter 033545-3
k. Base Bid Item #11: Exterior signs. 101400
l. Base Bid Item #12: Administrative ID sign and base 101420.
m. Base Bid Item #13: 3 panel log bulletin board 101425
n. Base Bid Item #14: Picnic tables (2 each) 129300-1
o. Base Bid Item #15: Bike racks (2 each) 129300-2
p. Base Bid Item #16: Bench 129300-1
q. Base Bid Item #17: Shelter, concrete slab and footings 13600
r. Base Bid Item #18: Project site prep and grading 312100
s. Base Bid Item #19: Hot Mix Asphalt 321200-1
t. Base Bid Item #20: Crushed aggregate base 321204-1
u. Bid Item #21: Bollards. See 321713
v. Base Bid Item #22: 6’ concrete wheel stops, 322625-1
w. Base Bid Item #23: Pavement Markings - Parking Stall Lines 4" Solid Yellow Non
Reflective 322640-1
x. Base Bid Item #24: Pavement Markings - Accessible Parking Symbol, 322640-2
y. Base Bid Item #25: Pulverize Asphalt Pavement and Reuse - Area for Building
Construction 322706-1
z. Base Bid Item #26: Wrought Iron / Tubular Steel Security Fence, 323113-1
aa. Bid Item #27: Chain link Fencing. See 323113
bb. Base Bid Item #28: Automatic Slide Gate - 20 Foot Wide Opening, 323113-3
cc. Base Bid Item #29: Pedestrian Gate - 5 Foot Wide Opening 323113-5
dd. Base Bid Item #30: Landscape Irrigation System. See section 328000.
ee. Base Bid Item #31: Landscape Concrete Edger Curbing 329212
ff. Base Bid Item #32: Exterior Plant and Landscape boulders. See section 329310
gg. Base Bid Line Item #33: Topsoil and Planting media. See section 329310-2.
hh. Base Bid Item #34: Landscape Decorative Gravel, Flagstone steppers and weed barrier.
See spec section 329400.
4. Optional Bid Items:
a. Optional Bid Item #1: Asphalt Slurry Seal (to be applied 6-9 months after asphalt has been placed). See section 321214.
b. Optional Bid Item #2: Pavement Markings – Remark Parking Stall Lines 4" Solid Yellow Non Reflective. See section 322640-1.
C.2 PROJECT LOCATON
The facility is located at 115 E 900 N Richfield Utah, 84701. The site is located in Sevier County, Utah.
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
The estimated price range of the project is between $1,000,000 and $5,000,000.
C.4 TECHNICAL SPECIFICATIONS
The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to or are included in payment for other pay items in this contract. These items are considered incidental, and no additional compensation will be made.
Section 000501 - Remodel Office Building Section 010250 - Construction Staking Section 011250 - Measurement And Payment With Asphalt Section 011900 - Mobilization Section 012500 - Utility Company Coordination Section 013100 - Project Management And Coordination Section 013300 - Submittal Procedures Section 014130 - Contractor’s Quality Control Section 015000 - Temporary Facilities And Controls Section 017320 - Selective Demolition Section 017700 - Closeout Procedures Section 023701 - Sediment And Erosion Control Measures Section 024100 - Waste Material Disposal Section 024113 - Selective Site Demolition Section 024117 - Hazardous Waste Disposal Section 026460 - Concrete Dumpster Pad Section 033000 - Cast-In-Place Concrete Section 033545 - Concrete Sidewalks And Curb & Gutters Section 044313.16 - Adhered Stone Masonry Veneer Section 047000 - Manufactured Masonry For Sign Bases Section 055000 - Metal Fabrications Section 055213 - Pipe Railings Section 061000 - Rough Carpentry Section 061500 - Wood Tongue And Groove Ceiling
Section 061600 - Sheathing Section 061800 - Glued-Laminated Construction Section 062013 - Exterior Finish Carpentry Section 062023 - Interior Finish Carpentry Section 064116 - Plastic-Laminate-Faced Architectural Cabinets Section 070150.19 - Preparation For Reroofing Section 071113 - Dampproofing Systems Section 072100 - Thermal Insulation Section 073110 - Asphalt Shingles Section 074646 - Fiber-Cement Siding And Soffit Section 076200 - Sheet Metal Flashing And Trim Section 079200 - Joint Sealants Section 081113 - Hollow Metal Doors And Frames Section 081416 - Flush Wood Doors Section 083113 - Access Doors And Frames Section 083513 - Folding Accordian Doors Section 084113 - Aluminum-Framed Entrances And Windows Section 087100 - Door Hardware Section 088000 - Glazing Section 090190 - Maintenance Repainting Section 092900 - Gypsum Board Section 093000 - Tiling Section 095113 - Acoustical Panel Ceilings Section 096513 - Resilient Base And Accessories Section 096519 - Resilient Tile Flooring Section 096813 - Tile Carpeting Section 097700 - Special Wall Finishes Section 099113 - Exterior Painting Section 099114 - Exterior Powder Coatings Section 099123 - Interior Painting Section 099300 - Staining And Transparent Finishing Section 099600 - High-Performance Coatings Section 101400 - Signs Section 101419 - Dimensional Letter Signage Section 101420 - Administrative Identification Sign – As (Hdpe) Section 101423 - Panel Signage Section 101425 - Panel Bulletin Board / Log Stanchion Section 101550 - Toilet Compartments Section 102800 - Toilet And Bath Accessories Section 105113 - Metal Lockers Section 105201 - Fire-Protection Specialties Section 113100 - Residential Appliances Section 122413 - Roller Window Shades Section 123661.16 - Solid Surfacing Countertops Section 124813 - Entrance Floor Mats, Grilles, And Frames Section 129300 - Site Furnishings Section 136000 - Pre-Manufactured Shelter Section 220517 - Sleeves And Sleeve Seals For Plumbing Piping Section 220518 - Escutcheons For Plumbing Piping Section 220523 - General-Duty Valves For Plumbing Piping Section 220523.12 - Ball Valves For Plumbing Piping
Section 220529 - Hangers And Supports For Plumbing Piping And Equipment Section 220553 - Identification For Plumbing Piping And Equipment Section 220719 - Plumbing Piping Insulation Section 221116 - Domestic Water Piping Section 221316 - Sanitary Waste And Vent Piping Section 224100 - Residential Plumbing Fixtures Section 224213.13 - Commercial Water Closets Section 224216.13 - Commercial Lavatories Section 224716 - Pressure Water Coolers Section 230513 - Common Motor Requirements For Hvac Equipment Section 230529 - Hangers And Supports For Hvac Piping And Equipment Section 230548 - Vibration And Seismic Controls For Hvac Section 230593 - Testing, Adjusting, And Balancing For Hvac Section 230713 - Duct Insulation Section 230900 - Instrumentation And Control For Hvac Section 230923.12 - Control Dampers Section 231123 - Facility Natural-Gas Piping Section 233113 - Metal Ducts Section 233416 - Centrifugal Hvac Fans Section 233713.13 - Air Diffusers Section 235416.13 - Gas-Fired Furnaces Section 260500 - Common Work Results For Electrical Section 260519 - Low-Voltage Electrical Power Conductors And Cables Section 260526 - Grounding And Bonding For Electrical Systems Section 260533 - Raceways And Boxes For Electrical Systems Section 260553 - Identification For Electrical Systems Section 260923 - Lighting Control Devices Section 262726 - Wiring Devices Section 262816 - Enclosed Switches Section 270500 - Common Work Results For Communications Section 270526 - Grounding And Bonding For Communications Systems Section 270528 - Pathways For Communications Systems Section 270536 - Cable Trays For Communications Systems Section 271100 - Communications Equipment Room Fittings Section 271200 - Communications Copper Network Cabling Section 321200 - Hot-Mix Asphalt Paving Section 321204 - Crushed Aggregate Base Or Surface Course Section 328000 - Irrigation System Section 323119 - Ornamental Metal Barrier Fence Section 323113 - Chain-Link Fences And Gates Section 322705 - Pavement Sawing Section 322640 - Pavement Marking Section 322622 - Precast Concrete Curb Stops Section 321713 - Bollards Section 321214 - Slurry Seal Section 329212 - Concrete Edger Landscape Curbing Section 329310 - Exterior Plants, Landscape Boulders And Topsoil Section 329400 - Landscape Stone, Flagstone And Weed Barrier
SECTION D--PACKAGING AND MARKING
D-1 PACKING AND MARKING
All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.
D-2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.
SECTION E--INSPECTION AND ACCEPTANCE
E.1 CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
SECTION F--DELIVERIES OR PERFORMANCE
F.1 CLAUSES
52.211-18 Variation in Estimated Quantity (APR 1984) 52.242-14 Suspension of Work (APR 1984)
F.2 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 270 calendar days after Notice to Proceed is issued. The time stated for completion shall include final cleanup of the premises.
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 Post Award Conference (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and held within TBD days after the date of contract award. The conference will be held at virtually via Teams meeting.
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 KEY PERSONNEL
(a) The Contractor shall assign to this contract the following key personnel: Project Foreman.
(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
H.2 USE OF PREMISES
(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor.
(b) Unless excepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the work force at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations.
H.3 ARCHAEOLOGICAL OR HISTORIC SITES
If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.
H.4 CONTROL OF EROSION, SEDIMENTATION, AND POLLUTION
(a) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).
(b) Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, or impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
(c) Mechanized equipment shall not be operated in flowing streams without written approval by the Contracting Officer.
H.5 INSURANCE COVERAGE
Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:
(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.
(b) General Liability. (1) The Contractor shall have bodily injury liability coverage written on a comprehensive form of policy of at least $500,000 per occurrence. (2) The Contractor shall have property damage liability insurance shall be required in the amount of $500,000 per occurrence.
(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.
(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
Federal Acquisition Regulation (FAR) Clauses: https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses: https://www.acquisition.gov/agar (AGAR clauses begin with 452) Deviations to clauses may be viewed at:
https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm
52.202-1 Definitions (JUN 2020) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights & Requirements to Inform Employees of
Whistleblower Rights (JUN 2020) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by
Kaspersky Lab and Other Covered Entities (NOV 2021) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or
Equipment (NOV 2021) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (NOV 2021) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.215-2 Audit and Records -- Negotiation (JUN 2020) 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-8 Utilization of Small Business Concerns (OCT 2018) 52.219-9 Small Business Subcontracting Plan (NOV 2021) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm
52.219-14 Limitations on Subcontracting (SEP 2021)
[Contracting Officer check as appropriate.] ☐ By the end of the base term of the contract and then by the end of each subsequent option period; or ☐ By the end of the performance period for each order issued under the contract.
52.219-16 Liquidated Damages --Subcontracting Plan (SEP 2021) 52.219-28 Post Award Small Business Program Rerepresentation (SEP 2021) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2018) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (MAY 2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (NOV 2021) 52.222-54 Employment Eligibility Verification (NOV 2021) 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026 (JAN 2022) 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts (SEP
2013) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun
2016) 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners
(JUN 2016)
52.223-15 Energy Efficiency in Energy Consuming Products (MAY 2020) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts (AUG
2018) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN 2020) 52.223-20 Aerosols (JUN 2016) 52.223-21 Foams. (JUN 2016) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997)
52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT 2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR
1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)
Alternate I (APR 1984) 52.242-5 Payments to Small Business Subcontractors (JAN 2017) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-2 Subcontracts (JUN 2020) 52.244-5 Competition in Subcontracting (DEC 1996) 52.244-6 Subcontracts for Commercial Products and Commercial Services (JAN 2022) (DEVIATION
APR 2020)
52.245-1 Government Property (SEP 2021) - Alt 1 (APR 2012) 52.245-9 Use and Charges (APR 2012) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012) Alternate I (SEP
1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
52.217-7 Option for Increased quantity – Separately Priced Line Item (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 6-9 months after asphalt has been placed.
52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008)
(a) Definitions. As used in this clause— “Postconsumer material” means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”
“Recovered material” means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
(b) The Contractor, on completion of this contract, shall—
(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and
(2) Submit this estimate to identified after contract award.
52.225-9 Buy American Act-Construction Materials (NOV 2021)
(a) Definitions. As used in this clause-
Commercially available off-the-shelf (COTS) item-
(1) Means any item of supply (including construction material) that is-
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at
Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the
Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means-
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if-
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the
United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
__________________NONE______________________________
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute. (1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the
Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material.
However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the
Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction Material Description Unit of Measure Quantity Price (dollars)* Item1:
Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______
Item2:
Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______
[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information.]
52.228-1 Bid Guarantee (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –
(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3 Million, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.228-11 Individual Surety - Pledge of Assets (FEB 2021) (DEVIATION APR 2020)
(a) The Contractor shall obtain from each person acting as an individual surety on a performance bond or a payment bond -
(1)A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and
(2) Standard Form 28, Affidavit of Individual Surety, [except that the words “being duly sworn, depose and say” on the Standard Form 28 are replaced with the word “affirm” and the Standard Form 28 is not required to be sworn and notarized in block 12].
(b)The Contracting Officer may release a portion of the security interest on the individual surety's assets based upon substantial performance of the Contractor's obligations under its performance bond. The security interest in support of a performance bond shall be maintained—
(1) Contracts for the construction, alteration, or repair of any public building or public work of the
Federal Government exceeding $150,000 (40 U.S.C. 3131). Until completion of any warranty period, or for 1 year following final payment, whichever is later.
(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)).
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .