5 12343420R0003 AMENDMENT 1.pdf
PDF 783 KB Posted
- Solicitation number
- 12343420R0003
About this file
This solicitation package is for a construction project to replace a 48-inch culvert on FR 150 Highland Scenic Highway in Pocahontas County, West Virginia. The work includes constructing a temporary road and bridge, removing the existing pipe, and installing a new culvert with rock headwalls. The estimated price range for all work is between $500,000 and $1,000,000. Offerors must provide pricing for all line items by May 26, 2020. The contract will be a firm fixed-price awarded to the offer representing the best value based on past performance, technical approach, and price. The work must be completed within 180 days of receiving notice to proceed. Performance and payment bonds valued at 100% of the contract price are required. The project has been set aside for HUBZone small businesses.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12343420R0003 Amendment 2.pdf | ||
| 1 Amendment 1 SF-30.pdf | ||
| 2 Meeting Notes.pdf | ||
| 3 Attachment 13.pdf | ||
| 6 REVISED Attachment 2.pdf | ||
| 7 Site Visit Attendance Sheet.pdf | ||
| 4 Attachment 14.pdf | ||
| Attachment 12 Sustainable.doc | DOC document | |
| 12343420R0003.pdf | ||
| Attachment 3.pdf | ||
| Attachment 1.pdf | ||
| Attachment 7.pdf | ||
| Attachment 10 Methodology.doc | DOC document | |
| Attachment 9 Experience.doc | DOC document | |
| Attachment 2.pdf | ||
| Attachment 4.pdf | ||
| Attachment 5.pdf | ||
| Attachment 11 Personnel.doc | DOC document | |
| Attachment 8.pdf | ||
| Attachment 6.pdf |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
12343420R0003
USDA FOREST SERVICE
MONONGAHELA NATIONAL FOREST
1079 MAIN STREET EAST
WHITE SULPHUR SPRINGS, WV 24986
FR 150 HIGHLAND SCENIC HIGHWAY 48" CULVERT REPLACEMENT PROJECT
MONONGAHELA NATIONAL FOREST
MARLINTON RANGER DISTRICT
POCAHONTAS COUNTY, WEST VIRGINIA
Price Range: The Government's estimated price range for all items combined is between $500,000 and $1,000,000.
Bid Guarantee: A bid guarantee in the amount of 20% of the total bid price is required. A copy of Standard Form (SF) 24, Bid Bond, can be downloaded form the following website:
(Note: Faxed copies of Bids, Bid Guarantees or Bonds are not acceptable.)
THIS PROJECT HAS BEEN SET ASIDE FOR HUBZONE SMALL BUSINESS CONCERNS
USDA FOREST SERVICE
MONONGAHELA NATIONAL FOREST
CARRIE EDWARDS; CONTRACTING OFFICER
1079 MAIN STREET EAST
WHITE SULPHUR SPRINGS, WV 24986
994913
Carrie Edwards 304-536-2144
1 4004/06/2020 local time 05/26/2020
4:00 PM
SEE SECTION F
cledwards Highlight
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Construction RFP – AMENDMENT 1 12343420R0003 FR 150 48” Culvert Replacement
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
SCHEDULE OF ITEMS
FR 150 Highland Scenic Highway Temp Road and Pipe Replacement
ITEM
NO.
DESCRIPTION
METHOD
OF
MEASURE
UNIT
EST.
QTY.
PRICE
TOTAL
15101-0000 Mobilization LS LPSM 1 $ $
15201-0000 Construction Survey and Staking LS LPSM 1 $ $
15301-0000 Contractor Quality Control LS LPSM 1 $ $
20102-0000 Clearing and Grubbing LS LPSM 1 $ $
62501-0000 Turf Establishment LS LPSM 1 $ $
63401-0000 Pavement Markings LS LPSM 1 $ $
63501-0000 Temporary Traffic Control LS LPSM 1 $ $
64602-1000 Building, Restroom Facility LS LPSM 1 $ $
TOTAL – Temp Road and Pipe Replacement: $
FR 150 Highland Scenic Highway Temp Road
15705-1500 Soil Erosion Control, Compost Sock LF LNFT 1200 $ $
20401-0000 Roadway Excavation CY CUYD 371 $ $
20410-0000 Select Borrow CY CUYD 100 $ $
25106-0400 Placed Riprap, Method B, Class 4 TON TON 55 $ $
25501-0000 Concrete Waste Block Abutments LS LPSM 1 $ $
30101-4000A Aggregate Clean #57 TON TON 14 $ $
30101-4000B Aggregate Base Grading D TON TON 88 $ $
30103-0000 Aggregate Base CY CUYD 197 $ $
55504-0000 Pre-Fabricated Steel Bridge Set and Remove LS LPSM 1 $ $
60201-0600 24-Ince Pipe Culvert LF LNFT 61 $ $
TOTAL – Temp Road: $
FR 150 Highland Scenic Highway Pipe Replacement
15705-1500 Soil Erosion Control, Compost Sock LF LNFT 1569 $ $
20401-0000 Roadway Excavation CY CUYD 1029 $ $
20410-0000 Select Borrow (Flowable Fill) 700psi – 1200psi CY CUYD 327 $ $
20702-0100 Geotextile Filter, Class 1, Type A SY SQYD 481 $ $
20820-0000 Dewatering LS LPSM 1 $ $
25102-0300 Placed Riprap, Method B, Class 2 TON TON 25 $ $
25106-0600 Placed Riprap, Method B, Class 6 TON TON 104 $ $
30101-4000 Aggregate Base, 1 ½ Crusher Run TON TON 50 $ $
30103-0000 Aggregate Base, Clean 57 CY CUYD 116 $ $
30206-0500 Roadway Aggregate, Shoulder Finishing LF LNFT 140 $ $
40301-0200 Asphalt Concrete Pavement, WV Wearing 1 TON TON 17 $ $
41301-1400 Asphalt Pavement Milling, 1 ½ inch Depth SY SQYD 187 $ $
55401-2000 Reinforcing Steel, Epoxy Coated LB LB 550 $ $
56506-0000 Coring/Pressure Grouting LF LNFT 111 $ $
60101-0000 Concrete CY CUYD 35 $ $
60103-0220 Concrete, Headwall for 48-inch Pipe Culvert EA EACH 1 $ $
60201-1200 48-inch Pipe Culvert LF LNFT 197 $ $
60203-0200 6-inch Slotted Drain Pipe LF LNFT 348 $ $
60404-0000 Catch Basin EA EACH 1 $ $
61701-1950 Guardrail System G4, Type 4, Class B Wood Posts LF LNFT 150 $ $
61708-1000 Remove and Reset, Guardrail LF LNFT 150 $ $
TOTAL – Pipe Replacement: $
GRAND TOTAL: $
Contractor Acceptance Statement: By signing the offer, the Contractor agrees to all terms, conditions, and provisions included in the solicitation and agrees to furnish any awarded items at the price set in the schedule unless otherwise excepted as follows:
OFFEROR INFORMATION:
BUSINESS NAME: _____________________________________________________________
POINT OF CONTACT NAME: ____________________________________________________
OFFICE PHONE: ____________________ CELL PHONE: ___________________________
EMAIL ADDRESS: __________________________________________
DATA UNIVERSAL NUMBERING SYSTEM (DUNS) NUMBER: _______________________
NOTES:
a) This solicitation will result in the award of one contract. There is a requirement to submit a technical proposal with your offer. See Section L for preparation instructions. Award will be made to the Contractor whose offer represents the Best Value to the Government. Past Performance & Experience, Technical Approach, Sustainable Acquisition and Price will be factored into the award decision. Evaluation criteria is located in Section M. You must submit pricing for all items, including any option items and/or option years to be considered.
b) In order to be eligible for a contract award under this solicitation, you must comply with all requirements of FAR Clause 52.204-7 – System for Award Management. Contractors may register in SAM at www.sam.gov; registration in SAM is free. If you do not have an “active” profile or you do not submit the requested information according to the solicitation provision, you will be considered non-responsive.
c) A pre-proposal meeting and tour will be held on Friday, May 1, 2020 at 10:00 am. Interested parties should plan to meet at the following location: Little Laurel Overlook (GPS 38-20-25.45N 80-09-51.44W).
Due to the complicated site conditions where work is required and the anticipated complexities associated with contract performance it is strongly encouraged that a representative from each interested party attend the scheduled site showing in person.
d) This is a construction project which has the following bonding requirements for offers over $150,000:
1. A bid guarantee in an amount equal to 20 percent of the bid price or $150,000, whichever is less, is required by the time set for submission of bids;
2. The successful offeror will be required to furnish a Performance Bond (SF-25) and Payment Bond (SF-25A) within 10 calendar days of the date they receive notice of award, the penal amount of each shall be 100 percent of the original contract price.
Reimbursement for bond premiums, in accordance with FAR 52.232-5, Payment under Fixed-Price Construction Contracts and AGAR 452.232-70, Reimbursement for Bond Premiums – Fixed Price Construction Contracts, shall not be in addition to the contract price (See Section I for additional information).
e) In order to make an offer for this project, you are required to complete and return the following:
1. OFFER: Standard Form 1442 (Pages 1 & 2) – Sections 14-20
2. COST PROPOSAL: Schedule of Items – Section B (Pages 3-6)
3. REPRESENTATIONS & CERTIFICATIONS: Representations, Certifications, and other
Statements of Offerors or Respondents – Section K (Pages 31-34)
4. TECHNICAL PROPOSAL: Instructions for the Preparation of Technical and Business Proposals –
Section L (Page 40)
Completed packages should be received by 4:00PM on Tuesday, May 26, 2020 at the following address:
US FOREST SERVICE
MONONGAHELA NATIONAL FOREST
ATTN: CARRIE EDWARDS
12343420R0003
1079 MAIN STREET EAST
WHITE SULPHUR SPRINGS, WV 24986
Email offers will also be accepted at carrie.edwards@usda.gov.
http://www.sam.gov/ mailto:carrie.edwards@usda.gov
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Scope of Contract
The primary objective of this project is to replace a failing culvert; including removal, installation and construction of a temporary bypass on FR150 (Highland Scenic Highway) in Pocahontas County, WV on the Marlinton Ranger District of the Monongahela National Forest. Work will consist of constructing a temporary road, setting a temporary bridge, removing existing pipe, and installing a new 48” culvert with rock headwalls per specifications.
Project Location
FR 150 HIGHLAND SCENIC HIGHWAY
Directions to work site from the Marlinton Ranger Station: drive West on Route 31 for 1.0 miles to U.S. Route
219. Follow U.S. Route 219 North for 7.0 miles to FR 150 Highland Scenic Highway on Left. Follow FR 150 for 8.3 miles.
The Government's estimate is between $500,000 and $1,000,000.
AGAR 452.211-72 Statement Of Work/Specifications (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
AGAR 452.211-73 Attachments To Statement Of Work/Specifications (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
C.1 Sustainable Acquisitions The Contractor shall comply with FAR Part 23 Sustainable Acquisition Policy and all associated laws, rules, regulations, and executive orders referenced therein. Contracts that include the supply of products and for the acquisition of services (including construction) that include the supply of products, require that the products provided are—
(1) Energy-efficient (ENERGY STAR® or Federal Energy Management Program (FEMP)-designated);
(applicable if FAR Clause 52.223-15 is included)
(2) Water-efficient; (applicable if FAR Clause 52.223-15 is included)
(3) Biobased; (applicable if FAR Clause 52.223-2 is included)
(4) Environmentally preferable (e.g., EPEAT®-registered, or non-toxic or less toxic alternatives);
(applicable if FAR Clause 52.223-13,14, or 16 are included)
(5) Non-ozone depleting; (applicable if FAR clause 52.223-11,12,20, or 21 are included), and/or
(6) Made with recovered materials (EPA-Designated products) (applicable if FAR clause 52.223-9 or 17 is included).
(b) The required products in the contract actions for services include products that are—
(1) Delivered to the Government during performance;
(2) Acquired by the contractor for use in performing services at a Federally-controlled facility; or
(3) Furnished by the contractor for use by the Government.
C1.1 Sustainable products identified for this solicitation:
The following is a list of sustainable products that that may be used i n t h e performance of this contract. The list is not all inclusive; the Contractor shall research for available products.
C1.1.1 Energy-efficient and Water-efficient Products ENERGY STAR® at http://www.energystar.gov/; and FEMP at https://www.energy.gov/eere/femp/search-energy-efficient-products www.epa.gov/watersense Roofing Products, low flow toilets, faucets, appliances
C1.1.2 Biobased Products: (requires reporting at www.sam.gov by 10/31 each year) http://www.biopreferred.gov a Diesel Fuel Additives
(1) Any substance, other than one composed solely of carbon and/or hydrogen, that is intentionally added to diesel fuel (including any added to a motor vehicle's fuel system) and that is not intentionally removed prior to sale or use.
(2) Neat biodiesel, also referred to as B100, when used as an additive. Diesel fuel additive does not mean neat biodiesel when used as a fuel or blended biodiesel fuel (e.g., B20). 90% - Minimum Biobased Content.
b Hydraulic Fluids - Mobile Equipment Hydraulic fluids formulated for general use in nonstationary equipment, such as tractors, end loaders, or backhoes. 44% - Minimum Biobased Content.
c Penetrating Lubricants Products formulated to provide light lubrication and corrosion resistance in close tolerant internal and external applications including frozen nuts and bolts, power tools, gears, valves, chains, and cables. 68% - Minimum Biobased Content.
d Greases - Truck Lubricants composed of oils thickened to a semisolid or solid consistency using soaps, polymers or other solids, or other thickeners. Lubricants that are designed for use on the fifth wheel of tractor trailer trucks onto which the semi-trailer rests and pivots. 71% - Minimum Biobased Content.
e Gear Lubricants Products, such as greases or oils, that are designed to reduce friction when applied to a toothed machine part (such as a wheel or cylinder) that meshes with another toothed part to transmit motion or to change speed or direction. 58% - Minimum Biobased Content.
f Fuel Conditioners Products formulated to improve the performance and efficiency of engines by providing benefits such as removing accumulated deposits, increasing lubricity, removing moisture, increasing the cetane number, and/or preventing microbial growths within the fuel system. 64% - Minimum Biobased Content.
http://www.energystar.gov/ https://www.energy.gov/eere/femp/search-energy-efficient-products http://www.epa.gov/watersense http://www.sam.gov/ http://www.biopreferred.gov/ g Erosion Control Woven or non-woven fiber materials manufactured for use on construction, demolition, or other sites to prevent wind or water erosion of loose earth surfaces, which may be combined with seed and/or fertilizer to promote growth. 77% - Minimum Biobased Content.
h 2-Cycle Engine Oils Lubricants designed for use in 2-cycle engines to provide lubrication, decreased spark plug fouling, reduced deposit formation, and/or reduced engine wear. 34% - Minimum Biobased Content.
C1.1.3 Environmentally Preferable Products:
www.epa.gov/epeat.
None
C1.1.4 Non-ozone Depleting Products:
http://www.epa.gov/snap
Foams, refrigeration products, air conditioning products
C1.1.5 EPA Designated Products:
https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program
Plastic trash bags, printer ribbons, toner cartridges, print & writing papers, Traffic Barricades, Traffic Cones, Engine Coolants, Rebuilt Vehicular Parts, Re-refined lubricating oils, retread tires, manual grade strapping, signage, sorbents.
C.2 SAFETY AND HEALTH
2.1.1 SUMMARY
A. References: In addition to publications referenced in the Contract and FAR 52.236-13, the following Code of Federal Regulations (CFR) publications designate and define hazardous materials and conditions, and establish procedures for handling these materials and conditions.
1. 29 CFR, Part 1910: Occupational Safety and Health Administration (OSHA) General Industry and Health Standards.
2. 29 CFR, Part 1926: OSHA Construction Industry Standards.
3. 40 CFR, Part 61: National Emission Standards for Hazardous Air Pollutants.
4. 40 CFR, Part 261: Environmental Protection Agency (EPA) Characteristics of Hazardous Waste.
5. 40 CFR, Part 761, EPA Polychlorinated Biphenyls (PCBs), Manufacturing, Processing, Distribution in
Commerce and Use Prohibitions.
B. Acquisition of Publications: Referenced CFR publications may be purchased from the Superintendent of
Documents, U.S. Government Printing Office, Washington, D.C. 20402.
2.1.2 SAFETY MEETING
A. Prior to commencing construction, representatives of the Contractor, including the Superintendent, shall meet with the Government to review the Contract's safety and health requirements.
B. The Contractor's safety and health program shall be reviewed, and implementation of safety and health provisions pertinent to the Work shall be discussed.
http://www.epa.gov/epeat http://www.epa.gov/snap https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program
2.1.3 COMPLIANCE WITH REGULATIONS
A. Contractor Responsibility: The Contractor shall assume full responsibility and liability for compliance with all applicable codes, standards and regulations pertaining to the health and safety of personnel during execution of the Work. The Contractor shall have written safety and health programs in compliance with 29 CFR Parts 1910 and 1926.
2.1.4 SUBMITTALS
A. Safety and Health Programs: The Contractor shall submit, for approval, copies of the project safety and health programs, as applicable to the work scope, or required as a result of the safety meeting, including but not necessarily limited to the following:
1. Occupational Noise Exposure.
2. Fall Protection.
3. Personnel Protective Equipment.
4. Control of Hazardous Energy.
5. Electrical Safety Related Work Practices.
6. Lead.
7. Respirator Protection.
8. Confined spaces.
9. Heavy Equipment Operation
PART 2 - PRODUCTS
2.2.1 PERSONNEL PROTECTIVE EQUIPMENT
A. Special facilities, devices, equipment and similar items used by the Contractor in execution of the Work shall comply with 29 CFR Part 1910, Subpart I and other applicable regulations.
PART 3 - EXECUTION
2.3.1 EMERGENCY SUSPENSION OF WORK
A. In accordance with FAR 52.236-13, when the Contractor is notified by the Government, of noncompliance with safety or health provisions of the Contract, the Contractor shall immediately, correct the unsafe or unhealthy condition. In accordance with FAR 52.236-13 if the Contractor fails to comply promptly, all or part of the Work will be stopped by Government notice. The Contractor shall not be allowed any extension of time or compensation for damages in connection with a work stoppage for unsafe or unhealthy conditions.
2.3.2 PROTECTION OF PERSONNEL
A. The Contractor shall take all necessary precautions to prevent injury to the public, occupants, or damage to property of others.
2.3.3 ENVIRONMENTAL PROTECTION
A. Dispose of solid, liquid and gaseous contaminants in accordance with local codes, laws, ordinances and regulations.
B. Comply with applicable federal, state and local noise control laws, ordinances and regulations, including but not limited to 29 CFR 1910.95 and 29 CFR 1926.52.
SECTION D--PACKAGING AND MARKING
{For this Solicitation, there are NO clauses in this Section}
SECTION E--INSPECTION AND ACCEPTANCE
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
SECTION F--DELIVERIES OR PERFORMANCE
52.242-14 Suspension of Work (APR 1984)
52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 calendar days. The time stated for completion shall include final cleanup of the premises.
SECTION G--CONTRACT ADMINISTRATION DATA
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
AGAR 452.215-73 Post Award Conference (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and held within 10 days after the date of contract award. The conference will be held at a date and time to be determined.
G.1 DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE
The contracting Officer will designate a Contracting Officer's Representative(COR) at the time of award.
The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.
On all matters that pertain to the contract terms the contractor must communicate with the Contracting Officer.
Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the contracting officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal for a contract claim.
G.2 GOVERNMENT-FURNISHED PROPERTY
The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract.
• 35’ ADM MODULAR TEMPORARY BRIDGE – The contractor will need to transport the 35’ ADM temporary bridge from the Marlinton stock yard located at the Marlinton Ranger Station to the project area to be utilized during repair work and then returned to the Marlinton stock yard upon completion of the repairs and the reopening of FR 150. The waste blocks (abutments) will be delivered to a location designated by the COR.
o The Marlinton Ranger Station (Marlinton stock yard) is located within 15 miles of the project location o The cost of transporting the bridge shall be covered under 55504-0000 – Pre-Fabricated Steel Bridge Set and Remove in the Schedule of Items
G.3 INVOICING
The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice Processing Platform (IPP). All invoices are to be submitted online via the electronic Invoice Processing Platform. This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm. Your company must register at https://www.ipp.gov/vendors/enrollment-vendors.htm to establish an account in order to submit an invoice on this project.
G. 4. FINAL PAYMENT – RELEASE OF CLAIMS
The Government shall pay the final amount due the Contractor under this contract after—
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed invoice; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release.
RELEASE OF CLAIMS
To be submitted with final invoice
Contract Number:
For and in consideration of payment and pursuant to the terms of the contract cited above, the government of the United States, its officers, agents, and employees are hereby released and discharged from all liabilities, demands, obligations, and claims arising under or by virtue of said contract.
Signature: ________________________________
Printed Name: ________________________________
Title: ________________________________
Company: ________________________________
Date: ________________________________
G.5 INCIDENTAL PAYMENT ITEMS
The intent of the contract is to provide for the complete performance of the project described in the contract.
Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.
G.6 CONTRACTOR CERTIFICATION
Contractor will submit certification with every progress invoice
CONTRACTOR CERTIFICATION
Page of Unit (Region, Forest, District) Project: Contract No.
Name of Contractor: Invoice No. Invoice Date:
I hereby certify, to the best of my knowledge and belief, that--
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) Payments to subcontractors and suppliers have been made, and timely payments will be made for the work activities covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
(3) This request for progress payments/credits does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor's performance.
(Name)
(Title)
(Date)
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 EQUIPMENT CLEANING
All soil moving equipment shall be thoroughly cleaned to make it free of soil, noxious weed seeds, vegetative matter or other debris that could contain or hold seeds prior to being delivered to the project site. Equipment shall be considered free of soil, noxious weed seeds and other such debris when a visual inspection by the C.O.R., prior to the equipment being delivered to the site, does not disclose such material present. Disassembly of equipment components is not required. The Contractor shall notify the Forest Service at least five (5) working days prior to moving each piece of soil moving equipment onto the project site, unless otherwise agreed.
The Contractor shall thoroughly clean all soil moving equipment prior to moving them off a project site or between work areas on a project site that are known to be infested with noxious weed species of concern and other work areas, if any, that are free of noxious weed species of concern. Areas known to be infested with specific noxious weed species of concern to the Forest Service shall be noted in the Schedule of Work. The Contractor and the Forest Service shall agree on the methods of cleaning, location for the cleaning and control of off-site impacts, if any.
When new areas of infestation of noxious weeds of concern to the Forest Service are identified on the project site by either the Forest Service or Contractor they shall be promptly reported to the other party.
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): http://farsite.hill.af.mil/
52.202-1 Definitions (NOV 2013) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (MAY 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) 52.203-17 Contractor Employee Whistleblower Rights & Requirements to Inform Employees of
Whistleblower Rights (APR 2014) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN
2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (OCT 2018) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (JUL 2016) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (JUL 2018) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance
Services or Equipment (AUG 2019) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-2 Audit and Records -- Negotiation (AUG 2016) 52.219-3 Notice of Total HUBZone Set-Aside or Sole Source Award (NOV 2011) 52.219-8 Utilization of Small Business Concerns (OCT 2018) 52.219-14 Limitations on Subcontracting (JAN 2017) 52.219-28 Post Award Small Business Program Rerepresentation (JUL 2013) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2018) http://farsite.hill.af.mil/
52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (AUG 2018) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (MAY
2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment Exceeding $15,000 (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (OCT 2015) 52.222-36 Equal Opportunity for Workers with Disabilities (JUL 2014) 52.222-37 Employment Reports on Veterans (FEB 2016) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (JAN 2019) 52.222-54 Employment Eligibility Verification (OCT 2015) 52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2015) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2017) 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
(SEP 2013)
52.223-3 Hazardous Material Identification and Material Safety Data Alt 1 (Jan 1997) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-15 Energy Efficiency in Energy Consuming Products (DEC 2007) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts
(AUG 2018)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-11 Pledges of Assets (AUG 2018) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds—Construction (OCT 2010) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments Under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017)
52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT 2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013) 52.233-1 Disputes (MAY 2014) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
(APR 1984)
52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)
Alternate I (NOV 1991) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984) Alt 1 (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-6 Subcontracts for Commercial Items (SEP 2019) 52.245-1 Government Property (JAN 2017) - Alt 1 (APR 2012) 52.245-9 Use and Charges (APR 2012) 52.246-21 Warranty of Construction (MAR 1994)
Alternate I (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2015) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)--Alternate I
(SEP 1996)
52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)
52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997)
Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:
(a) The Schedule (excluding the specifications).
(b) Representations and other instructions.
(c) Contract clauses.
(d) Other documents, exhibits, and attachments.
(e) The specifications.
52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008)
(a) Definitions. As used in this clause— “Postconsumer material” means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”
“Recovered material” means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
(b) The Contractor, on completion of this contract, shall—
(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and
(2) Submit this estimate to the Contracting Officer.
52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun 2016)
(a) Definitions. As used in this clause--
“Global warming potential” means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon Dioxide’s global warming potential is defined as 1.0.
“High global warming potential hydrofluorocarbons” means any hydrofluorocarbons in a particular end use for which EPA’s Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables of alternatives available at (http://www.epa.gov/snap/ ).
“Hydrofluorocarbons” means compounds that only contain hydrogen, fluorine, and carbon.
“Ozone-depleting substance” means any substance the Environmental Protection Agency designates in 40 CFR Part 82 as--
(1) Class I, including, but not limited to, chlorofluorocarbons, halons, carbon tetrachloride, and methyl chloroform; or
(2) Class II , including, but not limited to hydrochlorofluorocarbons.
(b) The Contractor shall label products which contain or are manufactured with ozone-depleting substances in the manner and to the extent required by 42 U.S.C. 7671j (b), (c), (d), and (e) and 40 CFR Part 82, Subpart E, as follows:
Warning
Contains (or manufactured with, if applicable) *_______, a substance(s) which harm(s) public health and environment by destroying ozone in the upper atmosphere.
* The Contractor shall insert the name of the substance(s).
(c) Reporting. For equipment and appliances that normally each contain 50 or more pounds of hydrofluorocarbons or refrigerant blends containing hydrofluorocarbons, the Contractor shall—
(1) Track on an annual basis, between October 1 and September 30, the amount in pounds of hydrofluorocarbons or refrigerant blends containing hydrofluorocarbons contained in the equipment and appliances delivered to the Government under this contract by—
(i) Type of hydrofluorocarbon (e.g., HFC-134a, HFC-125, R-410A, R-404A, etc.);
(ii) Contract number; and
(iii) Equipment/appliance;
(2) Report that information to the Contracting Officer for FY16 and to www.sam.gov, for FY17 and after--
(i) Annually by November 30 of each year during contract performance; and
(ii) At the end of contract performance.
(d) The Contractor shall refer to EPA’s SNAP program (available at http://www.epa.gov/snap ) to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables available at http://www.epa.gov/snap .
52.223-20 Aerosols (Jun 2016)
(a) Definitions. As used in this clause--
“Global warming potential” means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide’s global warming potential is defined as 1.0.
http://www.sam.gov/
“High global warming potential hydrofluorocarbons” means any hydrofluorocarbons in a particular end use for which EPA’s Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82, subpart G.
with supplemental tables of alternatives available at http://www.epa.gov/snap/).
“Hydrofluorocarbons” means compounds that contain only hydrogen, fluorine, and carbon.
(b) Unless otherwise specified in the contract, the Contractor shall reduce its use, release, or emissions of high global warming potential hydrofluorocarbons, when feasible, from aerosol propellants or solvents under this contract. When determining feasibility of using a particular alternative, the Contractor shall consider environmental, technical, and economic factors such as--
(1) In-use emission rates, energy efficiency;
(2) Safety, such as flammability or toxicity;
(3) Ability to meet technical performance requirements; and
(4) Commercial availability at a reasonable cost.
(c) The Contractor shall refer to EPA’s SNAP program to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables available at http://www.epa.gov/snap/.
52.223-21 -- Foams. (Jun 2016)
(a) Definitions. As used in this clause--
“Global warming potential” means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide’s global warming potential is defined as 1.0.
“High global warming potential hydrofluorocarbons” means any hydrofluorocarbons in a particular end use for which EPA’s Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82, subpart G.
with supplemental tables of alternatives available at http://www.epa.gov/snap/).
“Hydrofluorocarbons” means compounds that contain only hydrogen, fluorine, and carbon.
(b) Unless otherwise specified in the contract, the Contractor shall reduce its use, release, and emissions of high global warming potential hydrofluorocarbons and refrigerant blends containing hydrofluorocarbons, when feasible, from foam blowing agents, under this contract. When determining feasibility of using a particular alternative, the Contractor shall consider environmental, technical, and economic factors such as--
(1) In-use emission rates, energy efficiency, and safety;
(2) Ability to meet performance requirements; and;
http://www.epa.gov/snap/ http://www.epa.gov/snap/ http://www.epa.gov/snap/
(3) Commercial availability at a reasonable cost.
(c) The Contractor shall refer to EPA’s SNAP program to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables available at http://www.epa.gov/snap/.
52.225-9 Buy American Act-Construction Materials (MAY 2014)
(a) Definitions. As used in this clause— “Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the
Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
“Cost of components” means—
(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
“Domestic construction material” means—
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
http://www.epa.gov/snap/ https://acquisition.gov/far/current/html/Subpart%202_1.html#wp1145508 http://uscode.house.gov/
“Foreign construction material” means a construction material other than a domestic construction material.
“United States” means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: none
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the
Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
http://uscode.house.gov/ http://uscode.house.gov/ https://acquisition.gov/far/current/html/Subpart%2012_5.html#wp1077123
(2) If the Government determines after contract award that an…