Questions Answers 2.docx

DOCX document 2 MB Posted

Attached to
Cooling Cell Replacement Federal contract opportunity
Solicitation number
12305B21R0005
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Northeast Area

About this file

This document contains questions and answers regarding a solicitation for cooling cell replacement services at the United States Department of Agriculture Agricultural Research Service facility in Kearneysville, West Virginia. The solicitation is a total small business set aside with a NAICS code of 238220 and size standard of $16.5 million. The magnitude of construction is between $250,000 and $500,000, and the period of performance is 180 days from notice to proceed. Bid, payment, and performance bonds are required. Site plans and information on the existing control and drainage strategies are provided. The existing strategies are deemed sufficient by the agency, though alternative proposals will be considered.

View the file

Other files for this federal contract opportunity

Other files attached to Cooling Cell Replacement, newest first.
File Type Posted
Questions Answers.docx DOCX document
SOW Cooling Cell Replacement 12-17-2020 AFRS Kearneysville WV.docx DOCX document
12305B21R0005.pdf PDF
Attachment 2 Photographs.pdf PDF
Attachment 5 Contractor COVID Approval Procedure.pdf PDF
Attachment 3 Material Submittal Log.pdf PDF
ARS372.pdf PDF
Attachment 1 Original Drawings.pdf PDF
Attachment 6 Sample COVID Safety Plan.pdf PDF
Attachment 4 Specificatons Cooling Cell Replacement.pdf PDF
ARS371.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for information Solicitation Number 12305B21R0005 Cooling Cell Replacement USDA, AFRS Kearneysville, WV Contractor: W4 Construction Group Kalamazoo, MI 269-350-5772 awilliams@w4cg.com; myoung@w4cg.com

Date submitted:1/29/21

Questions for clarification:

1) Will the government accept the past performance of both parties in a signed teaming agreement when evaluating Factor 2, Past Performance? COR Response: Will accept past performance of both parties in a signed teaming agreement.

2) Will the government provide a site plan showing the arrangement of the greenhouses in relation to the main building and one another? Location Response: Yes, See Attached.

3) The existing controls are “on/off” with communication to the BAS system. Is it the expectation of the government that this control strategy remains in place, or is a more elaborate system desired? Location Response: The current system used will remain in place, for the ridge vents contractor needs to confirm the wind speed detector/indicator functions correctly preventing the ridge vents from coming open.

4) Is there a desire for N+1 redundancy or is the existing strategy sufficient? COR/Location Response: The existing strategy is sufficient.

5) The existing system drains to ground. Is this an acceptable strategy for the new system or should excess cooling water be processed? COR Response: USDA will consider both strategies; award will be based upon which system provides the best value to the government.

6) Can Reverse Osmosis and softener reject water be plumbed to existing waste drain? Location Response: Yes, we currently send softener reject water to drains.

7) Will the contractor have access to government owned roof access equipment to access louvers, motor, and shafts from above? Location Response: scaffolding panels for the glass roof can be used, along with a single personnel lift, but utilizing Government Furnished Property will be "as-is" condition. Contractor shall be responsible for any breakdown repairs that occur during usage.

8) Is there currently a water treatment infrastructure in place? Location Response: The only water treatment in place for the water out to the greenhouses is Chlorine is added to the water. 9A and 9B have a water softener in place but it won't be reused for this project. No other treatment is being utilized.

Attachment:

image1.emf image2.emf