Amendment 02.pdf

PDF 135 KB Posted

Attached to
Trail Creek Bridge Construction Federal contract opportunity
Solicitation number
1204M320Q0001
Issued by
Department of Agriculture Forest Service R6-Pacific Northwest Region

About this file

This amendment modifies a solicitation for the Trail Creek Bridge Construction project. The project involves clearing, excavation, temporary bridging, demolition of an existing culvert and bridge, construction of new bridge abutments, installation of precast concrete girders, backfilling, paving, installation of guardrails and riprap, stream restoration, and erosion control. The amendment provides revisions to the solicitation including updating the quantity of class 2 riprap and allowing certain excavated materials to be used onsite. It also includes responses to contractor questions clarifying permit requirements, the source of government furnished materials, payment for stream work, the ability to propose alternate excavation methods, and rock excavation assumptions. The solicitation will be issued on or around December 15, 2019 by the USDA Forest Service Pacific Northwest Region for a project with an estimated value between $1 million and $5 million and set aside exclusively for small businesses.

View the file

Other files for this federal contract opportunity

Other files attached to Trail Creek Bridge Construction, newest first.
File Type Posted
Revised Schedule of Items.pdf PDF
Amendment 01.pdf PDF
Bypass Bridge Manufacturers Drawings.pdf PDF
PL_5200000-0.9_Trail Creek Bridge Signed Drawings.pdf PDF
Trail Creek Supplemental Specifications.pdf PDF
Final Trail Creek Solicitation.pdf PDF
FireProtectionandSuppressionr6_fS_6300_52.pdf PDF
TC_PRESS_RELEASE_MAP.pdf PDF
Synopsis_Trail_Creek_Bridge.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

CONTRACT ID CODE PAGE 1 OF 3 PAGES

2 AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

06/03/2020

4. REQUISITION/PUCHASE REQ. NO. 5. PROJECT NO.(IF APPLICABLE)

6. ISSUE BY CODE 7.ADMINISTERED BY (if other than item 6) CODE

Wallowa-Whitman National Forest 1550 Dewey Ave, Suite A Baker City, OR 97814

8.NAME AND ADDRESS OF CONTRACTOR(No., street, county, State and ZIP Code) 9A.Amend Solicitation. 1204M320Q0001

* 9B.Dated 05/07/2020

* 10A.Mod Contract/Order #

* 10B.Dated (see Item 13) code facility code

11. THIS ITEM APPLIES ONLY TO AMENDMENT OF SOLICITATION

[x] The above numbered solicitation is amended as set forth in the item 14. The hour and date specified for receipt of Offers [ ] is extended [x ] is not extended. Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15 and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted, or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegam or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting and Appropriation Data (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. This change order is issued pursuant to; (specifiy authority)

The changes set forth in item 14 are made in the Contract/Order # in item 10A.

B. The above numbered Contract/Order is modified to reflect the administrative changes (such as changes in paying office, appropriation date, etc.) set forth in item 14, pursuant to the authority of FAR 43.103(b)..

C. This supplemental agreement is entered into pursuant to authority of:

D Other: (Specify type of modification and authority):

E. IMPORTANT: Contractor [ ] is not [ ] is required to sign this document and return _ Original to the issuing office.:

14. DESCRIPTION OF AMENDMENT/MODIFICATION

Project Name and Location: TRAIL CREEK BRIDGE CONSTRUCTION This amendment addresses the following (see attached addendum)

1. Solicitation Revisions for project (see attached addendum)

2. Pre-Bid Inquiries (PBI’s) for Contract Bidding (see attached addendum)

3. Revised Schedule of Items for pricing (see attached addendum)

By signature in Block 15B Contractor releases the Government from all claims relating to this modification. This settlement is complete accord and satisfaction. Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A.NAME AND TITLE OF SIGNER (Type or print)

16A.NAME AND TITLE OF CONTRACTING OFFICER

Contracting Officer

15B.CONTRACTOR/OFFEROR

By ______________________________ (Signature of person authorized to sign)

15C.DATE SIGNED 16B.UNITED STATES OF AMERICA

By______________________________ (Signature of Contracting Officer)

16C.DATE SIGNED

Standard Form 30 Prescribed by GSA FAR (48CFR) 53.243

Addendum to Amendment 2

REVISIONS, PRE-BID INQUIRIES, REQUEST FOR INFORMATION TRAIL CREEK BRIDGE CONSTRUCTION

REVISIONS

Revision-003

There is any error in the calculation for class 2 rip rap, pay item 25101a. The schedule of items has 36 cubic yard of class 2 rip rap.

After rechecking the calculations the volume should be 110 total cubic yards. An updated Schedule of Items is attached. See guardrail rip rap detail sheet 9, and channel section detail sheet 16 for rip rap locations. The class 6 rip rap volumes stay the same.

Revision-004

The proposed staging area on the north side of Trail Creek and west side of FSR 52 can be cleared and built up using road excavation.

The trees from the clearing may be used in stream simulation and any excavation placed there may be left. The excavation will need to be shaped after the project to blend with adjacent ground and to maintain drainage from the roadside ditch; maximum ditch invert elevation will be the top of the culvert at 5+50. The limits of this staging area are approximately stations 4+00 to the spring culvert near sta 5+50, as agreed with the Contracting Officer in the field.

Revision-005

Replace page 3 of the solicitation with Revised Schedule of Items (see attached)

Pre-Bid Inquiries (PBI’s) for Contract Bidding

PBI-008

Question: Is there a limit to the excavation vehicles we can use to haul waste material?

Answer: The contractor may propose to use vehicles over highway load limits and apply for an overload permit from the Forest Service. Any vehicle under highway load limits won’t need a permit.

PBI-009

Question: The government furnished material includes crushed aggregate and rip rap. Will the contractor be required to crush any aggregate?

Answer: No the government has crushed aggregate in the Hoodoo pit for contractor use. Rip rap may be sorted from excavation or hauled from any designated source.

PBI-010

Question: How is the in-stream log jam paid for?

Answer: This is included in pay item 64801, stream simulation.

PBI-011

Question: Will the contractor be able to get a waiver during a Level 4 fire shut down? And how will this affect the project completion period?

Answer: During level 4 shut downs there are several requirements to get a waiver including fire equipment and a water truck. The contractor will be responsible to submit for a waiver and provide the necessary equipment. If this affects the project completion date the Forest Service will adjust as needed.

PBI-012

Question: Can a contractor propose to excavate less asphalt and protect the existing pavement?

Answer: Yes the contractor may propose to excavate less asphalt and roadway on the south side Trail Creek. The contractor will be required to excavate all the designated asphalt on the north side of Trail Creek, to approximately station 7+30. They will then be required to rebuild the roadway and pave both lanes.

PBI-013

Question: Is the Forest Service positive there is no bed rock in the roadway excavation?

Answer: No the Forest Service is only confident on what is shown in the bore hole tests, see sheet 10.

PBI-014

Question: What are the size requirements for Class 2 and Class 6 rip rap?

Answer: The specification is Standard Specification FP-14 705-1 with the max diameter size for Class 2: 15”-21” and class 6: 39”- 45”. The contractor is responsible to meet size gradation requirements within the specification.

Requests for Information (RFI’s) for Plans and Specifications

None