10-KL27-100 Bids - Unofficial.xlsx
XLSX spreadsheet 11 KB Posted
- Attached to
- Goshen Valley Bullhog
- Solicitation number
- KL27-100
- Issued by
- Utah
About this file
This is an unofficial bid summary document associated with an Invitation for Bid (IFB) issued by the State of Utah Division of Purchasing, conducted through the Department of Natural Resources, for Bullhog Services at Goshen Valley. The solicitation is limited to prequalified contractors only and seeks a single contract award to the lowest cost responsive and responsible vendor. The scope of work involves providing Bullhog Services across 1,076 acres, with project completion required by February 19, 2027. No mandatory site visit was specified for this procurement. The vendor selected must guarantee pricing through project completion.
Eight contractors submitted bids for this opportunity, with total costs ranging from $234,568.00 to $3,225,848.00. The lowest bid was submitted by Maynes Equipment Repair at $234,568.00, representing a unit price of $218.00 per acre. Other notable bids included Retroscape LLC at $276,532.00 ($257.00 per acre), Wilkinson Construction Company at $319,572.00 ($297.00 per acre), AKD Advanced Services at $295,383.52 ($274.52 per acre), Hall's HammerTime Construction LLC at $342,157.24 ($317.99 per acre), Kolob Mountain Construction LLC at $360,460.00 ($335.00 per acre), and England Construction at $373,372.00 ($347.00 per acre). One bid of $3,225,848.00 appears anomalous at a unit price of $2,998.00 per acre and may represent a data entry error or alternative pricing structure.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet 1
| AKD Advanced Services | England Construction | Hall's HammerTime Construction LLC | Kolob Mountain Construction LLC | Maynes equipment repair | Retroscape LLC | Summitt Forests, Inc | Wilkinson Construction Company | |||||
| Total Cost | $276,532.00 | $373,372.00 | $295,383.52 | $342,157.24 | $234,568.00 | $360,460.00 | $3,225,848.00 | $319,572.00 | ||||
| # | Items | Quantity | ||||||||||
| Required | Unit |
of
| Measurement | Unit |
| Price | Total |
| Cost | Unit |
| Price | Total |
| Cost | Unit |
| Price | Total |
| Cost | Unit |
| Price | Total |
| Cost | Unit |
| Price | Total |
| Cost | Unit |
| Price | Total |
| Cost | Unit |
| Price | Total |
| Cost | Unit |
| Price | Total |
Cost
| Basket 1: Totals | $276,532.00 | $373,372.00 | $295,383.52 | $342,157.24 | $234,568.00 | $360,460.00 | $3,225,848.00 | $319,572.00 | |||||||||||
| #1-1 | Bullhog Services | 1076 | Acre | $257.00 | $276,532.00 | $347.00 | $373,372.00 | $274.52 | $295,383.52 | $317.99 | $342,157.24 | $218.00 | $234,568.00 | $335.00 | $360,460.00 | $2,998.00 | $3,225,848.00 | $297.00 | $319,572.00 |
File details come from the government source that posted it. Updated .