The document is a BIM (Building Information Modeling) Execution Plan for the Delta College K Wing Addition & Renovations project, developed by Delta College located in University Center, Michigan. The BIM Execution Plan outlines the strategic approach for implementing Building Information Modeling throughout the project lifecycle, with a focus on creating a comprehensive digital model that will be used for design coordination, clash detection, estimating, energy performance modeling, and future facility maintenance. The plan specifies that a Level of Development (LOD) 300 BIM model will be required at the end of the Construction Documents (CD) phase, which will be used by the Construction Manager (CM) for populating bid components and final trade coordination.
The project's BIM goals include general clash detection of structural, architectural, mechanical, and electrical components, creating an owner's as-built BIM model, and developing a fully functional model for Delta College's facility maintenance staff. The model will incorporate data from MEP (Mechanical, Electrical, Plumbing) trades, potentially including hyperlinks to submittal files. The BIM Execution Plan is considered a living document that can be refined throughout the project's life cycle, with the intent to ensure the project remains on schedule and meets all requirements. The plan emphasizes the importance of information exchanges, defining supporting infrastructure for BIM implementation, and clearly outlining the responsibilities and opportunities associated with the BIM process.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| 2022004-DeltaCollegeKWing-drawing set-010224.pdf | ||
| Addendum-Q_A (1).docx | DOCX document | |
| Certifications.docx | DOCX document | |
| 9 - RFP CMc K Wing Addition _ Renovations Scoring Sheets.pdf | ||
| 1 - RFP CMc - K Wing Addition and Renovations.pdf | ||
| 3 - Delta College Campus Map 2014.pdf | ||
| 10-11-2019 CMc Advertisement.pdf | ||
| Introduction Page.docx | DOCX document | |
| Pricing Sheet.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BIM EXECUTION PLAN
Delta College – K Wing Addition & Renovations
Per the A/E RFP:
BIM model LOD 300 will be required at the end of the CD phase and be available for use by the CM for populating bid components for final coordination of all trades. The
BIM model shall be returned to the Architect by the CM for verification and completion of an Owners as-built BIM model. It is the intent to use this model during the design phase for general clash detection of Structural, Architectural, Mechanical and Electrical coordination of all trade components, estimating and energy performance modelling.
BIM Model Intent:
CM should either hire BIM coordinator directly or sub it to contractors. It is Delta College’s intent to have a fully functional BIM model upon project completion to be used by the Delta College facility maintenance staff. The specific points of data for MEP trades to incorporate into the model are still being determined (including hyperlinks to submittal files), however, it is data that is readily available in submittal information.
The Project BIM Execution Plan (BEP) is a detailed plan that defines how the project will be executed, monitored and organized with regard to BIM.
The intent of the BIM Execution Plan is to provide an outline that will ensure all parties involved are clearly aware of the opportunities and responsibilities associated with projects that implement
BIM.
The plan defines why we are using BIM on the project. It sets goals, objectives and people’s responsibilities and outlines how the process will be executed through the project’s life cycle.
The BIM Execution Plan should be considered a living document and can be developed and refined throughout the project’s life cycle to ensure the project remains on schedule and meets briefed requirements.
Identify BIM goals
Design BIM project execution process
Develop information exchanges
Define supporting infrastructure for BIM implementation
CONTENTS
CONTENTS
PROJECT INFORMATION
PROJECT SCHEDULE
PROJECT GOALS
INFORMATION MANAGEMENT & EXCHANGE
MODEL ELEMENT RESPONSIBILITIES TABLE
MODEL ELEMENTS TABLE
PREPARED BY: COMPANY: DATE:
Name Name 1/16/2024
REVISION RECORD
REVISION DATE BY WHOM COMMENTS
1 8/15/2018 NCB
2 10/10/2019 AEK Updated for K Wing Addition & Renovation Project
PROJECT INFORMATION
Project name: Delta College – K Wing Addition & Renovations
Project owner: Delta College
Project address/location 1961 Delta Rd, University Center, MI
Brief project description: Renovation of all existing spaces located within the K wing, building addition and associated site work.
Contract type/delivery method: A/E and CMc
Contractor engagement - indicative date: A/E – 12/2021, CMc –2/2024
Has a Project BIM Brief been completed? No
PROJECT SCHEDULE
Fill in the table below with any major project milestones which occur during the project’s life cycle.
Project phase/milestone Estimated start date Estimated completion date
Pre-design Per schedule in RFP Per schedule in RFP
Concept design Per schedule in RFP Per schedule in RFP
Preliminary design Per schedule in RFP Per schedule in RFP
Developed design Per schedule in RFP Per schedule in RFP
Detailed design Per schedule in RFP Per schedule in RFP
Construction Per schedule in RFP Per schedule in RFP
Handover Per schedule in RFP Per schedule in RFP
Operation Per schedule in RFP Per schedule in RFP
PROJECT GOALS
List client goals and expectations for the project. This table will help define the BIM Uses required for the project, in alignment with the project goals.
Refer to Appendix D for BIM Uses.
This information could be extracted from the Project BIM Brief and any associated documents, if one has been completed.
Priority (high/med/low)
Goal description - value added objectives BIM Uses
H Design phase general clash detection of structural, architectural, mechanical and electrical coordination of all trade components, estimating and energy performance modelling
H LOD 300 required at end of CD phase and be available for use by the CM for populating bid components for final coordination of all trades. BIM model returned to architect by CM for verification and completion of an Owners as-built BIM Model
H Use of BIM model for Delta College Facility Maintenance Staff
H Implementation of BIM model data into Delta College TMA computerized maintenance management software.
INFORMATION MANAGEMENT & EXCHANGE
Measurement and coordinate systems:
Identify project spatial location (real world co-ordinate and level system).
Project datum TBD
Height datum TBD
Project location Easting Northing
Model positioning Degrees
Model standards As a minimum, each discipline in the project team should model industry proven, best practice methodology, as well as comply with their in-house standards and protocols. However, the client may have specific modelling and documentation requirements and standards which need to be adhered to as part of the BIM deliverables.
These should be specified below.
Model standards to be used
N/A
Model structure Describe and produce a simple diagram to show how the model is separated, e.g., by building, by floors, by zone, by model size, by areas, and/or discipline.
Model description document (MDD) Each modelling team should include a model description document (MDD) or similar agreed document that includes crucial information for each model it publishes.
The document should describe the contents of the model, any major revisions/changes and explain its purpose and limitations.
Permission and access The following document management issues should be considered/resolved and a procedure defined for each: permissions/access, file locations, FTP site location(s), file transfer protocol, file/folder maintenance, etc.
MODEL ELEMENT RESPONSIBILITIES TABLE
This table assigns responsibilities to Model Elements via an Author (MEA) and defines Level of Development (LOD) for those model elements across project stages.
Commissioning
Design
Development
Post
Construction
2D Design
Programming
Performance
Specs
Massing Advanced
SD
DD 50% CD 100% CD
COBie
Design
Data
ARCH LOD 50 LOD 100 LOD 150 LOD 200 LOD 250 LOD 300 LOD 300 LOD 300
MEP-FP LOD 50 LOD 100 LOD 150 LOD 200 LOD 250 LOD 300 LOD 300 LOD 300
STRUCT LOD 50 LOD 100 LOD 150 LOD 200 LOD 250 LOD 300 LOD 300 LOD 300
CIVIL LOD 50 LOD 100 LOD 150 LOD 200 LOD 250 LOD 300 LOD 300 LOD 300
GC LOD 300 LOD 350 LOD 350 LOD 400 LOD 450 LOD 500
Cx LOD 500
OWNER LOD 550 LOD 600
* This table depicts the intent of BIM project lifecycle: utilizing one set of models thru mapping LOD by phase and discipline.
Facility Management
O&M ConstructionDesign
Schematic Design Construction Documents
Discipline
Model-Based
Estimating &
Procurement
Detailing
Shop Dwgs
Fabrication
AS-Built
Record
Modeling
LOD by PHASE & DISCIPLINE
Owner OccupiedPre-Construction Construction
COBie
Field
Data
Systems
Testing
Commissiong
& Handover
Spatial
Planning
Asset
Tracking &
Maintenance
3D Coordination
3D
Coordination
3D
Virtual
Mockups
3D Design
MODEL ELEMENTS TABLE
Notes
SPATIAL
Site boundaries, setbacks
Grids
Levels
Zones
Spaces, rooms
STRUCTURE
Floor structures
Beams
Shaft openings
Stair & ramp structures
Walls – load bearing
Columns
ENCLOSURE
Cladding
Column claddings
Curtain walls
Windows
External doors, openings
INTERIOR
Partitions
Internal doors, openings
Ceilings
Flooring
Balustrading
F, F & E
Casework, joinery
Fixtures
Fittings
Equipment (non-service)
Furniture
Signage
MECHANICAL
Plant external & equipment
Plant internal & equipment
Services in risers
Louvers
Ductwork
Registers
Pipework (above and below floor)
Controls
HYDRAULIC
Plant & equipment
Sanitary fixtures
Pipework (above and below floor)
FIRE PROTECTION
Sprinklers
Pipework (main)
Pipework (branch)
Detection
EWIS / alarm systems
Hydrants
Extinguishers
Services in risers
ELECTRICAL
Electrical fixtures
Power outlets
Switch & distribution boards
Cable trays
Conduit larger than 1.25”
All underground conduit
Lighting
Light switches / controls
Communications
Audio/Visual
Security