1. Statement of Work.pdf

PDF 154 KB Posted

Attached to
127EAW21R0041 - Silver Lake Boat Launch
Solicitation number
127EAW21R0041
Issued by

About this file

This statement of work and related solicitation document describe requirements for a construction contract to rehabilitate the Silver Lake Boat Launch Facility in June Lake, California. Key work includes demolishing and replacing the existing single-lane boat launch ramp and boarding float, replacing sidewalks and restrooms, repairing parking areas, and installing lighting and signage. The estimated contract value is between $500,000 and $1,000,000. The contract is a total small business set-aside awarded by the Department of Agriculture Forest Service. The selected contractor must perform all work within 175 calendar days after July 5, 2021 in accordance with provided specifications, drawings, and construction handbooks. The solicitation requires licenses, insurance, and compliance with technical and regulatory requirements for the project.

View the file

Other files

File Type Posted
127EAW21R0041.pdf PDF
127EAW21R0041.pdf PDF
10. Davis-Bacon Act WD # CA20210020.pdf PDF
3. DBW Layout - Design - Construction - Handbook.pdf PDF
8. Silver Lake Boat Launch - BMPs.pdf PDF
7. Fire Plan.pdf PDF
6. Silver Lake Boat Launch Drawings.pdf PDF
11. RFI Form.docx DOCX document
5. Drawings of Boarding Float.pdf PDF
2. Silver Lake BLF Specifications.pdf PDF
4. Project Location Maps.pdf PDF
9. Schedule of Items.docx DOCX document
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

C. DESCRIPTION/ SPECIFICATIONS/ STATEMENT OF WORK

C.1 Scope of Work

Description of Work:

The Forest Service is seeking the service of a general contractor to rehabilitate the Silver Lake

Boat Launching Facility (BLF) as described in this statement of work, project specifications and project drawings. Silver Lake BLF, which is in June Lake CA, is a popular boating, kayaking, canoeing, and fishing facility. The BLF is also surrounded by various campgrounds and day-use

Facilities.

The rehabilitation work is anticipated to start in early July through November of 2021, and the facility will be closed off to the public during the rehabilitation work. Both the Section 401 and

Section 404 permits for the project have been obtained.

The rehabilitation work shall be accomplished in accordance with plans and specifications prepared for the project. The Contractor shall perform quality control for the work being performed, and compliance with project specifications shall be verified by professionals selected by the Government or Government’s representative.

Work associated with this contract includes, but is not limited, to the following:

1. Boat Launch Ramp: The Contractor shall demolish the existing eroded single lane boat launch ramp and replace it with a new single lane boat launch ramp. The existing boat launch ramp is approximately 20 feet wide by 50 feet long and extends approximately 15 feet into the lake at a maximum depth of approximately 5 feet.

Note: The water level in Silver Lake will not be lowered during the demolition of the existing boat ramp and the installation/construction of the new boat ramp. Silver Lake’s water levels are constant throughout the year, however the lakes water level decreases slightly during the fall.

2. Boarding Float: The Contractor shall relocate the existing boarding float from its current location to the west side of the newly constructed boat launch ramp. The boarding float is approximately 8 feet wide by 60 feet long and is held in place by a ¾ inch stainless steel cable (approximately 250 ft. long) which is connected to an onshore anchor block and two offshore concrete anchor blocks. The stainless-steel cable is connected to the onshore anchor block by an eye bolt, 1”x12”. The offshore concrete anchor blocks are approximately 2000 pounds each (approx. 3.4 feet wide by 3.4 feet long by 2.3 feet high) and are located approximately 250 feet from the shoreline at a depth of approximately 20 feet. The Contractor shall reuse the existing anchoring system, including the offshore concrete anchor blocks.

Note: The boarding float was installed in 2017(summer) and is usually rolled out of the lake at the end of the recreation season in early November to prevent damage from freezing water. Drawing of the existing boarding float are included in the solicitation.

3. Sidewalk, Curb & Gutter: The Contractor shall demolish the existing sidewalk and curbing and replace it with an ADA compliant path of travel.

4. Restrooms: The Contractor shall demolish the existing flush toilet buildings (2) and lift station. The Contractor shall also purchase and install one double stall vault toilet building to replace the demolished flush toilet buildings.

5. Lighting: The Contractor shall install new security lighting at the head of the new boat launch ramp as shown on the project drawings.

6. Water Supply: The Contractor shall install a new yard hydrant near the new vault toilet building.

Note: The water supply for the new yard hydrant shall come from the existing flush toilet building’s water supply.

7. Parking Area Repair: The Contractor shall repair and resurface the parking area pavement surface, including the installation of a storm drainage system to capture runoff from the parking area. The Contractor shall also restripe and mark out parking spaces and traffic flow directions.

8. Signage: The Contractor shall relocate the existing project credits sign to its new location as shown on the project drawings. The contractor shall also install direction/regulatory signage as shown on the project drawings.

9. Clearing & Grubbing: The Contractor shall remove trees, shrubs, boulders, vegetation materials and other objectionable materials within the limits of excavation. Trees marked for removal are shown on the project drawings.

Contractor Responsibility:

1. The Contractor shall provide everything – including, but not limited to, all equipment, supplies, transportation, labor, and supervision – necessary to complete the project, except that for which the contract clearly states is to be furnished by the Government.

2. The Contractor shall complete the work in conformance with the Department of Boating and Waterways’ Layout, Design and Construction Handbook for small Craft Boat

Launching Facilities.

3. The Contractor is responsible for coordination of all material deliveries and work performed until completion and acceptance of the entire work.

4. The Contractor is responsible for the security of the Contractor’s tools and equipment at all times during the duration of the project. All motorized equipment shall be provided with key locks or other devices to render them inoperable when the Contractor is not on site.

5. The Facility will be closed off to the public during the duration of the project, however the Contractor is responsible for providing temporary fencing to secure the work area from the public.

C.2 Project Location & Description

Location:

The project is located on the Inyo National Forest at the Silver Lake BLF in June Lake, CA.

Silver Lake BLF is located on the west side of Silver Lake, which is part of the June Lake Loop in the Eastern Sierras of California. June Lake Loop is approximately 150 miles south of Reno, Nevada off of CA-158. The closest substantial community to the Silver Lake BLF is Mammoth

Lakes, CA approximately 15 miles to the south.

Directions from Mammoth Lakes:

Travel north on CA-395 for 15 miles and turn left at the June Lake Junction onto CA-158 towards June Lake, CA. Travel for approximately 7 miles, Silver Lake BLF is on the right-hand side.

Exclusions (Non-Work Areas):

All other areas that are not directly adjacent to the project area are considered non-work areas and should not be impacted by the Contractor in any way.

Accessibility:

Project location is accessible by passenger vehicle or truck and is located next to a paved road.

Any prospective contractor desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing from the Contracting Officer soon enough to allow a reply to reach all prospective contractors before the solicitation closing date. Oral explanations or instructions given before the award of a contract will not be binding.

C.3 Maps

For project location maps, see attachments.

Any maps included in Section J are general in nature and are not to be considered as definitively identifying locations.

C.4 Estimated Start Date & Contract Time

Estimated Start Date: July 14, 2021. Work on the ground shall not commence until after July 5, 2021.

Number of Calendar Days Required: 175 Days

See also Section F

C.5 Restrictions on Work

Work may be performed at any time during the period of the contract, except as outlined here.

Nothing in this part shall be construed to take away any of the Government's rights under the

Suspension of Work Clause (52.242-14). Restrictions are as follows:

1. On-site work will not commence until after July 5, 2021. An approved work schedule is required before on-site work can begin.

2. In accordance with the fire plan, if included in Section J.

3. When the Contracting Officer (or designated representative) determines that work must stop due to adverse weather or due to the presence of archeological artifacts.

4. The Contractor shall not use Government trash facilities for waste without the permission of the COR. All construction debris remains the property of the Contractor and shall be properly disposed of off National Forest Land.

5. The Contractor and the Contractor’s employees shall not be permitted to have dogs or other pets on the project site at any time.

6. The Contractor and its subcontractors shall not unlawfully discriminate, harass, or allow harassment against any employee who is employed in the work covered under this contract or against any applicant for such employment because of sex, sexual orientation, race, color, ancestry, religious creed, national origin, physical disability (including HIV and AIDS), mental disability, mental condition (cancer), age, marital status, genetic information, gender, gender identity, gender expression, military or veteran status and denial of family care leave, and that such provisions shall not be limited to: employment, upgrading, promotion or transfer, recruitment, or recruitment advertising, layoff or termination, rates of pay or other forms of compensation, and selection for training including apprenticeship.

7. No placement or v-grooving of concrete for boat launching ramps on the project shall be allowed until the Construction Contractor demonstrates proficiency in creating a satisfactory v-grooved surface by preparing a concrete test panel measuring no less than 6 feet by 4 feet. A Department of Parks and Recreation, Division of Boating and

Waterways (DBW) representative must accept the test panel before the Construction

Contractor shall be allowed to place or v-groove concrete for boat ramps. Precast boat launching ramp panels are exempt from the test panel requirement but must be approved by a DBW representative prior to placement or installation. Test panels must be adjacent to, but not part of, any ramp work to be completed and must remain accessible until all ramp work is completed and accepted by DBW. Contractor may incorporate test panel into other concrete work (i.e. trash enclosure, etc.).

8. The Department of Parks and Recreation, Division of Boating and Waterways and its agents may, at all reasonable times during construction, enter the project area for purposes of inspecting the project area.

9. The Contractor shall comply with all air pollution and environmental control rules, regulations, ordinances, and statutes during the project.

10. The Contractor shall create an erosion control plan and water pollution control plan for all construction activities to limit erosion and sedimentation to Silver Lake.

The plan shall include the following:

a) Locations and management measures to limit erosion and sedimentation to Silver

Lake during and after construction.

b) Location of the concrete washout areas and management practices for control of

PH altering substances.

c) Staging/access area locations.

d) A rain event action plan template.

11. The Contractor shall create a proposal for in-lake turbidity control during the removal of the existing boat launch ramp and installation of the new boat launch ramp, which includes details on curtain location, depth, material type, and securing methods. The plan shall also include curtain maintenance contingencies in the event of curtain failure or damage.

12. The Contractor shall create a turbidity monitoring plan. The plan shall propose turbidity monitoring frequencies and locations to demonstrate that turbidity levels the open water construction area (inside the curtain) are no greater than 3 NTUs compared to levels outside the curtain prior to curtain removal.

13. Work shall be performed during daylight hours between 0730 hrs. and 1900 hrs. local time. Weekends are considered to begin at 5 pm on Fridays and end at 7:30 am on

Mondays. Additional working hours may be negotiated with the Contracting Officer

(CO).

14. Camping and Housing (see also Section H, Camping Permit Compliance)

Camping is not permitted in US Forest Service Campgrounds. Contractor [ ] will [x] will not be permitted to camp elsewhere on US Forest Service land. Camping of Forest

Service land is not a right; permission may be revoked for failure to comply with the terms of the permit.

C.6 Licenses and Insurance

The contractor shall obtain the insurance and licenses listed here.

MSPA Card (Form WH510): This contract [ ] does [X] does not require the contractor to be registered with the US Department of Labor as a Farm Labor Contractor. The Contractor shall provide a current Form WH510 or legible copy.

Other: The Contractor shall obtain and maintain all necessary licenses and permits that are needed to successfully complete the project.

The Contractor shall provide evidence of Worker’s Compensation Insurance or a written explanation as to why the Contractor is exempt from the requirement.

NOTE: Contractor working alone is not required to carry the insurance.

C.7 Technical Requirements

1. Special project specifications and project drawings are included in the solicitation.

The following documents are part of this solicitation:

a. Project Specifications.

b. Silver Lake Boat Launch Replacement - BMPs

c. Project Drawings.

T1.0 Title Sheet

C1.0 Data Sheet

C2.0 General Notes

C3.0 Overall Site Plan

C4.0 Restroom Plan and Elevations

C5.0 Launch Ramp Plan and Profile

C5.1 Launch Ramp Section and Details

C6.0 Parking Lot Paving and Utility Plan

C6.1 Parking Lot Sections and Details

C6.2 Parking Lot Details

C6.3 Storm drain and Path Sections & Details

E1.0 Electrical and Water Details

d. Boarding Float Drawings.

e. Department of Boating and Waterways’ Layout, Design, and Construction Handbook for Small Craft Boat Launching Facilities.

C.7-1 Definitions

Definitions:

NONE

C.7-2 Specifications

1. Silver Lake BLF Specifications

C.7-3 Contractor-Furnished Equipment

The Contractor shall furnish all labor and equipment necessary to complete the work specified in this Contract.

C.7-4 Government-Furnished Equipment

None.