This document is a Stormwater Pollution Prevention Plan (SWPPP) template completed for the Harford Community College Stream Restoration project, prepared by the Harford County Department of Public Works in Maryland. The project involves approximately 2,600 linear feet of stream restoration and stabilization, floodplain and buffer enhancement, and infrastructure protection on the Harford Community College campus in Churchville, Maryland. The total project site encompasses 4.32 acres, with a maximum of 1 acre expected to be disturbed at any one time, mostly with same-day stabilization. Construction activities are estimated to begin in August 2026 and conclude in March 2027, with the actual start and completion dates to be amended following the selected contractor's work schedule. The project discharges to Deer Creek, which is listed as an impaired water body with pollutants including nutrients, PCB/PFOS, and sediment. Daily site operations are scheduled for Monday through Friday, 7 a.m. to 5 p.m.

The SWPPP identifies key responsible parties including Danielle Hankins and Lindsey Snyder from Harford County Department of Public Works, with Mike Davies serving as Chief of Environmental Inspections overseeing compliance and corrective actions. Inspection procedures require weekly inspections and inspections within 24 hours of rainfall events exceeding 0.25 inches, with increased frequency of twice weekly inspections due to discharge to impaired waters and Tier II designated waters. Primary pollution prevention measures include geotextile filter bags for dewatering, outlet protection, turbidity monitoring conducted by a third-party contractor, spill response materials, fueling location restrictions (minimum 100 feet from wetlands and regulated areas), and storage of materials within approved stockpile areas. The plan prohibits on-site washing of equipment and applicators, concrete washout, and hazardous waste generation. A portable toilet will be located outside the floodplain for contractor personnel. The selected contractor will be responsible for daily site management, NOI inspections, dewatering inspections, and turbidity monitoring, with 24-hour emergency contact capability maintained by the Harford County Department of Public Works.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Stormwater Pollution Prevention Plan (SWPPP)

Harford Community College

“Construction Stormwater Pollution Prevention Plan

Template The Maryland Department of the Environment (MDE) requires construction operators to develop a Stormwater Pollution Prevention Plan (SWPPP) prior to submitting a Notice of Intent (NOI) for

Construction General Permit (20-CP) coverage (Refer to Part III.F of the permit). To assist with developing a SWPPP that meets the minimum requirements of the General Permit for Stormwater

Associated with Construction Activity, the Maryland Department of the Environment has provided this template.

This template is customizable to your specific project and site.

Once MDE has approved coverage for your project under the 20-CP, include your NOI, your authorization, and a copy of the 20-CP as attachments to the SWPPP.

For more information on the Tier II Checklist, the NOI in ePermits or Cationic Chemical

Treatment, please navigate to our website located here:

https://mde.maryland.gov/programs/water/wwp/Pages/gp_construction.aspx

Instructions for Using the SWPPP Template

Each section of the SWPPP Template includes instructions and space for your project and site information. Read the instructions for each section before you complete that section. The blue text indicates what information is to be included.

The SWPPP Template is an editable document file. You may add tables or additional text and/or delete unneeded or inapplicable fields. The information provided in each section may vary in length.

The following items may help you better prepare for completing the SWPPP:

● Make sure you read the General Permit thoroughly before you begin preparation of your

SWPPP. By doing so, you are ensuring that you have a working understanding of the permit’s underlying requirements.

● Remember to complete the SWPPP prior to submitting your Notice of Intent (NOI) for permit coverage when required.

● If there is more than one construction operator or individual/entity that will be responsible for separate phases or parts of the construction for your project, consider coordinating the development of your SWPPP with the other operators or individuals/entities.

While MDE has made every effort to ensure the accuracy of all instructions contained in the

SWPPP Template, it is ultimately the permit that determines the obligations of regulated construction stormwater discharges. In the event of a conflict between the SWPPP Template and any corresponding provision of the 20-CP, you must abide by the requirements in the permit. MDE welcomes feedback on the SWPPP Template. Future revisions of this document will consider all feedback.

For Construction Activities At:

Harford Community College Stream Restoration

Harford Community College

Churchville MD 21015

443-412-2000

SWPPP Prepared For:

Harford County Department of Public Works

Danielle Hankins

212 S. Bond Street

Bel Air, MD 21014

410-638-3217 ext 1176

DHankins@harfordcountymd.gov

SWPPP Prepared By:

Harford County Department of Public Works

Lindsey Snyder

212 S. Bond Street

Bel Air, MD 21014

410-638-3217 ext 1394

LSnyder@harfordcountymd.gov

SWPPP Preparation Date:

06/25/2026

Estimated Project Dates

Project Start Date: August 2026

Project Completion Date: March 2027

A SWPPP is required for your site in the following situations (Part III.F.1 of the

Permit). Indicate which of these conditions apply at your site:

☒ My project is within a common plan of development and I am sharing liability between and among operators on the same site. This SWPPP clarifies (To Be

Determined) areas of responsibility.

☐ I plan to use Chemical Additives or Polymers for Sediment Control.

☒ I have the potential for any of the non-stormwater discharges prohibited in permit Part I.D (also listed below). This may include any of these.

1. Wastewater from the Concrete Washout. (Permit Part III.A.3.d).

2. Wastewater from washout and cleanout of stucco, paint, form release oils, curing compounds, and other construction materials. (permit Part

III.A.3.d)

3. Fuels, oils, or other pollutants used in vehicle and equipment operation and maintenance (permit Parts III.A.3.a and III.A.3.c.iii).

4. Soaps or solvents, or detergents used in vehicle and equipment washing or external building washdown (permit Part III.A.3.b);

5. Toxic or hazardous substances from a spill or other release (also see permit

Part III.A.3.c iv, III.A.3.f. and VI.J) (whether the site is known to be contaminated by PCBs, PFAS, mercury, lead, or other metals, or any other source of toxic industrial pollution); and

6. Water contaminated by toxic or hazardous substances from sites managed under Maryland's Voluntary Cleanup Program (VCP) or Land

Restoration Program (LRP).

☒ I plan on implementing controls associated with the activities requiring pollution prevention measures, referenced in Part III.A.3 of the permit.

☐ None of the above, I am voluntarily creating a SWPPP for my construction activity.

Contents SECTION 1: CONTACT INFORMATION/RESPONSIBLE PARTIES (Part III.F.2.a of the permit)

1.1 Operator(s) / Subcontractor(s)

1.2 Stormwater Team (Part III.F.2.b of the permit)

SECTION 2: NATURE OF CONSTRUCTION ACTIVITIES (Part III.F.2.c of the permit)

2.1 Project/Site Information

2.2 Discharge Information

2.3 Description of the Construction Activities (Part III.F.2.c.i - v of the permit)

2.4 Sequence and Estimated Dates of Construction Activities (Part III.F.2.c.vi of the permit)

2.5 Authorized Non-Stormwater Discharges (Part III.F.2.e of the permit)

SECTION 3: DEWATERING AND USE OF CHEMICAL TREATMENT (Part III.F.2.c of the permit)

3.1 Dewatering Practices

3.2 Chemical Treatment

SECTION 4: POLLUTION PREVENTION STANDARDS (Part III.A.3 of the Permit)

4.1 Potential Sources of Pollution

4.2 Spill Prevention and Response

4.3 Fueling and Maintenance of Equipment or Vehicles (Part III.A.3.a in the

Permit)18

4.4 Washing of Equipment and Vehicles (Part III.A.3.b in the Permit)

4.5 Storage, Handling, and Disposal

SECTION 5: INSPECTION, MAINTENANCE, AND CORRECTIVE ACTION

5.1 Inspection Personnel and Procedures (Part III.C of the Permit)

5.2 Corrective Action (Part III.D of the Permit)

SECTION 6: TRAINING (Part III.E of the Permit)

SECTION 7: EROSION AND SEDIMENT CONTROLS (Part III.F.f.i)

SECTION 8: CERTIFICATION AND NOTIFICATION

SECTION 9: Appendices

9.1 Amendment Log

9.2 Site Maps (Part III.F.2.d of the permit)

9.3 Sample Subcontractor Certifications/Agreements

9.4 Cationic Chemical Treatment Approval Form

9.5 Grading and Stabilization Activities Log

9.6 Rainfall Log

9.7 SWPPP Training Log

SECTION 1: CONTACT INFORMATION/RESPONSIBLE PARTIES (Part III.F.2.a of the permit)

1.1 Operator(s) / Subcontractor(s)

Operator(s):

Harford County Department of Public Works

Danielle Hankins

212 S. Bond Street

Bel Air, MD 21014

410-638-3217 ext. 1176

DHankins@harfordcountymd.gov

Construction Contractor to Be Determined

Control of daily site construction activities

NOI inspections

Daily Dewatering Inspections

Turbidity monitoring

Emergency 24-Hour Contact:

Harford County Department of Public Works

Danielle Hankins or Lindsey Snyder

443-862-5367 or 240-422-0992

Instructions – Identify the operator(s) who are responsible for construction activities at the site.

Indicate respective responsibilities, where appropriate.

Remember to include the project’s 24-hour emergency contact.

List subcontractors expected to work on-site.

Notify subcontractors of stormwater requirements applicable to their work.

Consider using Subcontractor Agreements. (See Appendix 9.3)

List any amendments to this SWPPP in Appendix 9.1.

PROJECT IS NOT PART OF A COMMON PLAN DEVELOPEMNT

Common Plan of Development – Roles and Responsibilities.

Entity Contact Info Project Area Responsibility

Developer A Phone # Entire development Final stormwater management and coordination of entities within development.

Builder A Email, phone # Lots adjacent To maintain their perimeter controls and inspections and to maintain fueling area.

Builder B Phone # Lots adjacent To maintain their perimeter controls and inspections and to maintain concrete washout area.

Contractor A Phone # Perimeter of my

LOD.

Performing Inspections for My

Company.

Your Company Page 6 of

SWPPP

Plots 33-45, 62, 73-79. E&SC for these plots, and coordination with Developer A, Builder A, and Builder B on shared areas.

1.2 Stormwater Team (Part III.F.2.b of the permit)

Stormwater Team

Name and/or position, and contact Responsibilities I Have Read the 20-CP and

Understand the Applicable

Requirements

Danielle Hankins

Harford County DPW

MS4 Program Administrator

410-638-3217 ext. 1176

Operator

☒ Yes

Date: 6/30/2025

Lindsey Snyder

Capital Project Manager

410-638-3217 ext.1394

LGSnyder@harfordcountymd.gov

SWPPP

Development

☐ Yes

Date: 6/30/2025

Contractor TBD

E&S (NOI)

Inspections

Operator/Site

Work

Turbidity

Monitoring

☐ Yes

Date:

Instructions – Identify the project’s stormwater team.

Identify everyone by name or position.

Describe everyone’s responsibilities.

Indicate which members are responsible for inspections.

At a minimum, the stormwater team is comprised of individuals who are responsible for:

Overseeing the development of the SWPPP

Any later modifications to the SWPPP

Compliance with the permit requirements (i.e., installing and maintaining stormwater controls, conducting site inspections, and taking corrective actions where required)

Each member of the stormwater team must have ready access to either an electronic or a paper copy of the 20-CP and the SWPPP.

SECTION 2: NATURE OF CONSTRUCTION ACTIVITIES (Part III.F.2.c of the permit)

2.1 Project/Site Information

Project Name and Address

Project/Site Name: Harford Community College Stream Restoration

Project Street/Location: Harford Community College Campus

City: Churchville

State: MD

ZIP Code: 21015

County or Similar Subdivision: Harford County

Business days and hours for the project: Monday-Friday 7am-5pm

Project Latitude/Longitude

Latitude: 39.559581º N

(decimal degrees) Longitude: -76.281440º W

(decimal degrees)

Latitude/longitude data source:

☐ Map ☐ GPS ☒ Other (please specify): ESRI Online Mapping Tool

Additional Project Information

Are you requesting permit coverage as a state or federal entity? ☐ Yes ☒ No

Have you received an assigned MDE SF number for the Erosion and Sediment Control Plan?

☐ Yes ☒ No

If yes, please provide the assigned number: N/A

Instructions – Provide basic site information.

Provide the nearest cross street if a physical address is unavailable.

The Latitude and Longitude Coordinates must be in Decimal Degrees.

2.2 Discharge Information

Does your project/site discharge stormwater into a Municipal

Separate Storm Sewer System (MS4)?

☐ Yes ☒ No

Are there any waters of this State within 50 feet of your project’s earth disturbances?

☒ Yes ☐ No

Provide the Watershed Basin Code below. If your project discharges to more than one watershed, please provide all basin codes.

Deer Creek 02120202

Lower Susquehanna River 021202

Outfall ID Name of receiving water

Is the receiving water impaired (on the CWA

303(d) list)?

List the pollutants that are causing the impairment

Is there a completed

TMDL for this receiving waterbody

Is this receiving water designated as a Tier II?

[FB-1 thru FB 4]

Stream

Dewatering

Devices

Deer Creek ☒ Yes ☐ No Nutrients

PCB/PFOS

Sediment

☒ Yes ☐ No ☒ Yes ☐ No

[OP-1 thru OP-

4]

CWD Outlet

Protection

Deer Creek ☒ Yes ☐ No Nutrients

PCB/PFOS

Sediment

☒ Yes ☐ No ☒ Yes ☐ No

Instructions – Include information relating to your site’s discharge.

List all the stormwater points of discharge from your site.

Identify each point of discharge with a unique 3-digit ID (e.g., 001, 002).

For each unique point of discharge listed, specify the name of the receiving water of this

State that the stormwater directly discharges.

You may have multiple points of discharge to the same receiving water.

Specify whether any waters of this State that you discharge to are listed as impaired.

List the pollutants causing the impairment.

Identify any completed Total Maximum Daily Loads (TMDL) for any of the waters of this

State that you discharge to.

List the pollutants for which there is a TMDL.

Indicate whether any water of this State that you discharge to is designated as a Tier II.

2.3 Description of the Construction Activities (Part III.F.2.c.i - v of the permit)

General Description of Project

Provide a general description of the nature of your construction activities. For any demolition, include the dates of past renovations:

The Harford Community College Stream Restoration Project includes the following activities:

approximately 2600 linear feet of stream restoration/stabilization, floodplain/buffer enhancement, and infrastructure protection.

Size of Construction Site

Size of Property: 4.32 ac

Total Acreage Expected to be Disturbed by Construction Activities: 4.32 ac

Maximum Acreage Expected to be Disturbed at Any One Time: 1 ac (mostly same-day stabilization)

Type of Construction Site (check all that apply):

☐ Single-Family Residential ☐ Multi-Family Residential ☐ Commercial ☐ Industrial

☐ Institutional ☐ Highway or Road ☐ Utility ☒ Other Stream Restoration Project

Will there be demolition of any structure built or renovated before January 1, 1980?

☐ Yes ☒ No

If yes, do any of the structures being demolished have at least 10,000 square feet of floor space? ☐ Yes ☐ No ☒ N/A

Instructions – Provide a general description of the construction activities at your site.

Indicate the size of the property (in acres), the total acreage to be disturbed by the construction activities, and the maximum acreage expected to be disturbed at any one time.

Indicate the type of construction site. Include any demolition activities, and if the predevelopment land use was for agriculture.

Provide a list and description of all pollutant-generating activities.

Examples: paving operations; concrete, paint, and stucco washout and waste disposal; solid waste storage and disposal; and dewatering operations

Indicate for each activity the type of pollutant that will be generated with potential to be discharged in stormwater from your site.

Examples: sediment, fertilizers, pesticides, paints, caulks, sealants, fluorescent light ballasts, contaminated substrates, solvents, fuels

Describe the construction support activities covered by this permit.

Examples: concrete or asphalt batch plants, equipment staging yards, material storage areas, excavated material disposal areas, borrow areas

Pollutant-Generating Activities (Part III.F.c.vii)

― List and describe all pollutant-generating activities. Indicate for each activity the type of pollutant that will be generated. Consider where potential spills and leaks could occur, and any known hazardous or toxic substances, such as PCBs or asbestos, which will be disturbed during construction.

Pollutant-Generating Activity

Excavating/Grading

Dewatering

Equipment fueling

Staging/Stockpiling Areas

Fertilizer Application

(e.g., paving operations; concrete, paint, and stucco washout and waste disposal; solid waste storage and disposal; and dewatering operations)

Pollutants or Pollutant Constituents

(e.g., sediment, fertilizers, pesticides, paints, caulks, sealants, fluorescent light ballasts, contaminated substrates, solvents, fuels)

Excavating/Grading Sediment/Nutrients

Dewatering Sediment/Nutrients

Equipment Fueling Fuel (Deisel/Gasoline), Oil

Staging/Stockpiling Areas Sediments/Fuels/Oils

Fertilizer Application Nutrients

Construction Support Activities (only provide if applicable)

Describe any construction support activities for the project.

(e.g., concrete or asphalt batch plants, equipment staging yards, material storage areas, excavated material disposal areas, borrow areas)

This project has two material stockpiles designated on site for Material Staging, Excavated

Material Storage, and/or Equipment Staging. Each has its own silt fence/diversion fence to protect the site/off site from sediment laden waters.

Contact information for construction support activity:

Name TBD

Telephone number

Email

Address

2.4 Sequence and Estimated Dates of Construction Activities (Part III.F.2.c.vi of the permit)

Phase I (Project is not phased)

In-channel work (excavation) and Floodplain grading

Estimated Start Date of Construction Activities for this

Phase August/September 2026

Estimated End Date of Construction Activities for this

Phase End date will be amended after the selected contractor provides a work schedule.

Estimated Date(s) of Application of Stabilization

Measures for Areas of the Site Required to be

Stabilized

Permanent stabilization of in-channel and floodplain areas will be same-day.

Estimated Date(s) when Stormwater Controls will be

Removed Winter 2027

Instructions – Describe the intended construction sequence and duration of major activities.

For each portion or phase of the construction site, include the following:

Commencement and duration of construction activities, including clearing and grubbing, mass grading, demolition activities, site preparation (i.e., excavating, cutting and filling), final grading, and creation of soil and vegetation stockpiles requiring stabilization

Temporary or permanent cessation of construction activities

Temporary or final stabilization of areas of exposed soil

Removal of temporary stormwater controls and construction equipment or vehicles, and cessation of any pollutant-generating activities

2.5 Authorized Non-Stormwater Discharges (Part III.F.2.e of the permit)

List of Authorized Non-Stormwater Discharges Present at the Site

Type of Authorized Non-Stormwater Discharge

You are required to identify the locations of these authorized non-stormwater discharges on your site map.

Present at the construction site?

Discharges from emergency fire-fighting activities ☐ Yes ☒ No

Landscape irrigation; ☐ Yes ☒ No

Water used to wash vehicles and equipment ☐ Yes ☒ No

Water used to control dust ☐ Yes ☒ No

Potable water including uncontaminated water line flushing (requires separate

“HT” permit) ☐ Yes ☒ No

External building washdown (soaps/solvents are not used, and external surfaces do not contain hazardous substances) ☐ Yes ☒ No

Pavement wash waters ☐ Yes ☒ No

Uncontaminated air conditioning or compressor condensate ☐ Yes ☒ No

Uncontaminated, non-turbid discharges of ground water or spring water ☒ Yes ☐ No

Construction dewatering water ☒ Yes ☐ No

Instructions - Identify all authorized sources of non-stormwater discharges.

a. Discharges from emergency fire-fighting activities;

b. Landscape irrigation;

c. Water used to wash vehicles and equipment, if there is no discharge of soaps, solvents, or detergents used for such purposes;

d. Water used to control dust;

e. External building washdown, provided soaps, solvents, and detergents are not used, and external surfaces do not contain hazardous substances (as defined in

Appendix A) (e.g., paint or caulk containing polychlorinated biphenyls (PCBs));

f. Pavement wash waters – if spills or leaks of toxic or hazardous substances have not occurred (unless all spill material has been removed) and where soaps, solvents, and detergents are not used. You are prohibited from directing pavement wash waters directly into any Waters of this State, storm drain inlet, or stormwater conveyance, unless the conveyance is connected to a sediment basin, sediment trap, or similarly effective control;

g. Uncontaminated air conditioning or compressor condensate;

h. Uncontaminated, non-turbid discharges of ground water or spring water;

i. Foundation or footing drains where flows are not contaminated with process materials such as solvents or contaminated ground water; and

j. Construction dewatering water discharged in accordance with Part III.A.4.

SECTION 3: DEWATERING AND USE OF CHEMICAL TREATMENT (Part III.F.2.c of the permit)

3.1 Dewatering Practices

General

Geotextile Filter bags (utilized for dewatering sump areas during active construction)

Clear Water Diversion/ Outlet Protection (utilized to stabilize flows from clean water pump-around)

Pipe Slope Drain (utilized for dewatering areas behind a dike or berm on a slope)

Turbidity Monitoring (utilized to ensure that flows entering the receiving waterway do not exceed allowable turbidity thresholds)

Specific Dewatering Practices

Nonwoven Geotextile Filter Bag (Dewatering)

Description: Geotextile filter bag at the terminus of a dewatering pipe

Installation August/September 2026

Maintenance

Requirements Filter bags will be placed on (and dewater to) a stabilized area/suitable base as described in detail F-4 from the 2011 Maryland Standards and

Specifications for Soil Erosion and Sediment Control. They will be inspected for clogging, rips, tears, punctures, and watertightness of the connected hose.

The filter bags will be replaced if damaged or clogged.

Outlet Protection (Clean Water Pump-around)

Description: Velocity Dissipator/Outlet Protection (rip rap or sandbags)

Installation August/September 2026

Maintenance

Requirements Outlet protection practices will be monitored to ensure that flow from the stream diversion pipe (clean water pump-around) is not causing channel erosion and/or creating turbid conditions greater than the allowable threshold.

Instructions – Describe any dewatering practices

Include a description of all dewatering practices that are installed and maintained at the construction site.

Excavations

Trenching

Foundations

Vaults or other similar points of accumulation

3.2 Chemical Treatment

Will this site use treatment chemicals? ☐ YES ☒ NO

Turbidity Monitoring

Description: Dewatering flow will be sampled for Turbidity

Installation August/September 2026

Maintenance

Requirements Dailly turbidity sampling will be conducted by a third-party contractor. Any and all discharge points for dewatering will be sampled for turbidity. The exact procedure will depend on equipment specifications, but the Maximum

Daily NTU is the datapoint that needs to be recorded. Sampling data will be tracked on the Turbidity Motoring Report Form, provided by MDE in the

20CP(Appendix D).

Calibration and/or verification of calibration for the monitoring equipment will occur prior to use each day. If the meter shows more than 2% difference from the calibration standards, calibration will be required. All calibration methods should be in accordance with manufacturer’s instructions.

In the event that the Average Daily Threshold was exceeded, the inspector will notify the contractor/responsible person as soon as possible in order to begin corrective actions to reduce sediment in flow from the site.

Instructions - If you are using treatment chemicals at your site, provide details in the tables below

Complete the tables with all applicable requested information.

Attach copies of applicable manufacturer’s specifications regarding the use of your specific treatment chemicals and/or chemical treatment systems.

Refer to the Maryland List of Pre-Approved Flocculants available on MDE’s website.

Receive approval from the Department prior to the use of Cationic Chemicals.

SECTION 4: POLLUTION PREVENTION STANDARDS (Part III.A.3 of the Permit)

4.1 Potential Sources of Pollution

Construction Site Pollutants

You must consider where potential spills and leaks could occur that contribute pollutants to stormwater discharges, and any known hazardous or toxic substances, such as PCBs and asbestos that will be disturbed or removed during construction.

Pollutant-Generating Activity

Pollutants or Pollutant

Constituents

(that could be discharged if exposed to stormwater)

Location on Site

(or reference SWPPP site map where this is shown)

Excavation/Grading Sediment Within LOD

Dewatering Sediment Within LOD at Filter bags/Outlet structures

Equipment Refueling Petroleum-based fuel/oil

Within LOD; not within one hundred feet of wetland, wetland buffer/floodplain

Fertilizer Application Chemical Nutrients Upland Meadow/Turfgrass

Establishment

Hauling Sediments Construction Entrances

Instructions – Describe all pollutant generating activities

Identify and describe all pollutant-generating activities at your site

Paving operations

Concrete

Paint

Stucco washout and waste disposal

Solid waste storage and disposal

For each pollutant generating activity, include an inventory of pollutants or pollutant constituents associated with that activity that may be exposed to rainfall or snowmelt.

Sediment

Fertilizers and/or pesticides

Paints

Solvents

Fuels

4.2 Spill Prevention and Response

Spill prevention and response procedures (see Part I.D.5 and Part III.A.3.c.iv of the permit). You must include the following:

o Procedures for expeditiously stopping, containing, and cleaning up spills, leaks, and other releases. Identify the name or position of the employee(s) responsible for detection and response of spills or leaks; and o Procedures for notification of appropriate facility personnel, emergency response agencies, and regulatory agencies where a leak, spill, or other release containing a hazardous substance or oil in an amount equal to or in excess of a reportable quantity consistent with Part III.A.3.f. and established under either 40 CFR 110, 40 CFR 117, or 40 CFR

302, occurs during a 24-hour period (see Part III.A.3.f). Contact information must be in locations that are readily accessible and available to all employees. You may also reference the existence of Spill Prevention Control and Countermeasure (SPCC) plans developed for the construction activity under Part 311 of the CWA, or spill control programs otherwise required by an NPDES permit for the construction activity, provided that you keep a copy of that other plan on site.

Spill Prevention:

1. Any individual handling hazardous materials on site should be familiar with the Material

Safety Data (MSD), should be aware of spill response procedures, and have access to spill response supplies/appropriate personal protective equipment (PPE).

In the event of a hazardous material spill:

Immediate Safety and Assessment:

1. Identify the material, source, and estimated quantity of the material. Reference MSD for more information, if needed.

2. Once it is determined that the area is safe to enter, provide first aid to any injured individuals. Call 911 if additional care is necessary.

3. Continue to evaluate fire/explosion potential and other immediate threats to the health and safety of other individuals.

Containment and Prevention:

1. If possible, attempt to contain the spill using methods/materials such as pads, oil absorbents, berms, and/or ditches to prevent the spill from spreading.

2. Prevent human/vehicle exposure by using barriers, posting warnings, or having personnel guard the area.

External Assistance and Cleanup:

1. If the spill volume exceeds the Reportable Quantity, immediately contact Emergency

Response Agencies.

2. Gather and organize trained individuals to further review the situation.

3. Identify all hazards the team may encounter and ensure that cleanup personnel are wearing appropriate PPE.

4. Ensure the procedure for cleanup, decontamination, and disposal of contaminated materials is done according to established procedures.

5. Equipment, such as shovels/brooms etc. should be decontaminated once cleanup effort is complete.

Discharge from the work site:

1. In accordance with Harford County’s Hazardous Materials Law Article 1, Section 146: Any release of hazardous materials into the environment or a release that has the potential to enter the environment, must immediately be reported to 911. Dispatchers are trained to respond depending on the unique details of the spill incident.

Within 14 calendar days, after a release which requires notification, the responsible person shall provide a written follow-up emergency notice or notices (if more information becomes available) to the Harford County Division of Emergency Operations (HCDEO).

2. In accordance with the requirements of 40 CFR 110, 40 CFR Part 117, and 40 CFR Part 302, any release of hazardous material from the work site in excess of the reportable quantities

(within a 24-hour period), must be reported to the National Response Center (NRC) immediately upon knowledge of the release at 1-800-424-8802.

3. Personnel must also notify Maryland Department of the Environment (MDE) as soon as they have knowledge of the discharge/release.

8AM and 5PM at 410-537-3510

All other hours at 866-633-4686

Within seven (7) calendar days of knowledge of the release, personnel must provide a description of the incident, the circumstances leading to the release, and the date of the release to MDE’s compliance program.

Responsible Personnel/ Emergency Contact/Operator:

Danielle Hankins

Lindsey Snyder

4.3 Fueling and Maintenance of Equipment or Vehicles (Part III.A.3.a in the Permit)

Spill response materials (Spill kits)

Equipment Fueling Restriction (Location)

Instructions – Describe fueling and maintenance practices

Describe equipment/vehicle fueling and maintenance practices that will be implemented to eliminate the discharge of spilled or leaked chemicals

Secondary containment

Spill berms

Decks

Spill containment pallets

Spill kits

Specific Pollution Prevention Practices

Spill Response Materials (Spill Kits)

Description: Spill Kit(s) will be available near the fueling area and/or in a vehicle on site that can be transported quickly to a spill.

Installation August/September 2026

Maintenance

Requirements Spill kits will be inspected regularly to ensure appropriate materials are on-hand. Materials will be replaced as necessary.

Fueling Location Restrictions

Description: Re-fueling activities will not occur within 100ft of MDE-regulated areas.

Installation August/September 2026

Maintenance

Requirements In order to ensure that fuels are not released into sensitive/regulated areas, all fueling activities will occur at least 100ft from wetlands, waterways, and regulated floodplains to the maximum extent practicable.

4.4 Washing of Equipment and Vehicles (Part III.A.3.b in the Permit)

Washing practices are not expected or approved on site for this project.

N/A

Description: None

Installation N/A

Instructions – Describe washing practices

Describe equipment/vehicle washing practices that will be used to minimize the discharge of pollutants from equipment and vehicle washing, wheel wash water, and other types of wash waters

Locate activities away from waters of this State and stormwater inlets or conveyances

Direct wash waters to a sediment basin or sediment trap

Use filtration devices filter bags or sand filters

Use other effective controls

Describe how you will prevent the discharge of soaps, detergents, or solvents

Plastic sheeting

Temporary roofs

Other method of design to prevent the discharge of pollutants from these areas

4.5 Storage, Handling, and Disposal

4.5.1 Building Products (Part III.A.3.c.i in the Permit)

All building materials (stone, common borrow, etc.) will be stored within an approved stockpile area. Stockpiles will be protected by timber matting and super silt fence.

Diversion Fence

Description: Trenched Chain Link Fence with Impermeable Sheeting (to divert runoff away from site/stockpile areas).

Installation August/September 2026

Maintenance

Requirements Fences will be inspected weekly for damage to geotextile, chain link, etc.

Personnel will ensure functionality of the practice and repair as needed.

4.5.2 Pesticides, Herbicides, Insecticides, Fertilizers, and Landscape Materials (Part III.A.3.c.ii in the Permit)

Fertilizer, herbicide, insecticide, and landscape materials will be covered and stored in a manner to prevent contact with stormwater. Landscape material will be stored on site during the planting phase of the project in the stockpile areas if necessary.

Instructions – Describe storage, handling, and disposal of building products, materials, and wastes

Asphalt sealants, copper flashing, roofing materials, adhesives, concrete admixtures, gravel and mulch stockpiles

Pesticides, herbicides, insecticides, fertilizers, and landscape materials

Diesel fuel, oil, hydraulic fluids, other petroleum products, and other chemicals

Hazardous or toxic waste, paints, solvents, petroleum-based products, wood preservatives, additives, curing compounds, acids

Construction and Domestic Waste, packaging materials, scrap construction materials, masonry products, timber, pipe and electrical cuttings, plastics, Styrofoam, concrete, and other trash or building materials

Sanitary waste

Describe used applicator and container washing

Paint, Concrete or Other Materials

Describe pollution prevention for the use of fertilizers

Describe any additional pollution prevention practices

Landscape Materials (containerized trees, shrubs, plugs, and live stakes) will be stored on site for a short duration prior to and during installation. All containers, tags, and flagging will be removed before project completion.

Description: None

Installation N/A

Maintenance

Requirements

4.5.3 Diesel Fuel, Oil, Hydraulic Fluids, Other Petroleum Products, and Other Chemicals (Part

III.A.3.c.iii in the Permit)

Any fuel, oil, other petroleum products, and other chemicals stored on site will be stored outside of the 100-year floodplain. Hydraulic fluid is stored off site and brought on site when required. Fuel is located at the construction entrance and may be protected with a concrete jersey barrier. A spill kit is located next to the tank. Fueling will only occur in the area around the construction entrance to help prevent contaminants from entering the stream.

Spill Kits

Description: Spill Kits and/or Containment Materials

Installation August/September 2026

Maintenance

Requirements Spill cleanup/containment supplies will be available near the fueling location(s) and/or in a vehicle on site that can be accessed in the event of a fuel/oil spill. Materials should be inspected and/or periodically restocked to ensure that they are available in the event of an emergency.

Enhanced Fuel Containment

Description: Secondary Containment on Fuel Tanks

Installation August/September 2026

Maintenance

Requirements Fuel tanks will have secondary containment built in by the manufacture. Tanks will be checked periodically for leaks and/other corrosion (rust), and to ensure that the pumping and/or shutoff mechanisms are functioning properly.

4.5.4 Hazardous or Toxic Waste (Part III.A.3.c.iv in the Permit)

No toxic chemicals will be stored on site. No hazardous waste will be generated from this site.

Description: None

4.5.5 Construction and Domestic Waste (Part III.A.3.c.v in the Permit)

No solid waste (construction or domestic) will be left on site after construction.

Domestic waste will be removed daily to prevent trash from entering the waterway.

Soils unsuitable for construction will be hauled off site to an approved disposal area.

Trash Collection Container

Description: A trash can or bag used to collect solid waste

Installation August/September 2026

Maintenance

Requirements Ensure that trash is collected (at least daily) and removed from the site. Trash bags should be sturdy and free from rips or tears. Trash cans should not be overflowing.

4.5.6 Sanitary Waste (Part III.A.3.c.vi in the Permit)

The contractor will provide a portable toilet for their personnel, to be placed outside the floodplain.

Portable Toilet

Description: Describe practice to be installed

Installation August/September 2026

Maintenance

Requirements Portable Toilets will be regularly maintained/ pumped to ensure proper utilization. The toilet will be placed on a flat, dry surface away from machinery to avoid tipping accidents. Toilets should be inspected regularly for any damage or leaking fluids.

4.5.7 Washing of Applicators and Containers used for Paint, Concrete or Other Materials (Part

III.A.3.d in the Permit)

No washing of Applicators/containers is expected or approved on site.

Description: None

4.5.8 Fertilizers (Part III.A.3.e in the Permit)

Fertilizers may be used for turfgrass establishment.

Restricted Fertilizer Application

Description: No Fertilizer application is approved for Riparian or Wetland Vegetation

Establishment

Installation August/September 2026

Maintenance

Requirements Fertilizer will be applied in accordance with the contract documents and will not be applied in excess.

4.5.9 Releases in Excess of Reportable Quantities. (Part III.A.3.f in the Permit)

Discharges of hazardous substances and oil resulting from on-site spills are not authorized by this permit. (Part I.D.5). In the event of a discharge resulting from a spill of hazardous substances or oil from a construction site (Parts III.A.3.c.iii and Part III.A.3.c.iv), where the release is an amount equal to or in excess of a reporting quantity established under either 40 CFR Part 110, 40 CFR Part

117, or 40 CFR Part 302, occurring during a 24 hour period:

i. You shall notify the National Response Center (NRC) as soon as you have knowledge of the discharge in accordance with the requirements of 40 CFR Part 110, 40 CFR Part 117, and 40 CFR

Part 302;

• 1-800-424-8802 or

• 202-267-2675 (in the Washington, DC metropolitan area)

ii. You shall notify the Maryland Department of the Environment as soon as you have knowledge of the discharge;

• Between 8AM and 5PM at 410-537-3510

• All other hours at (866) 633-4686

You must also, within seven (7) calendar days of knowledge of the release, provide a description of the release, the circumstances leading to the release, and the date of the release to the

Department’s compliance program. Local requirements may necessitate additional reporting of spills or discharges to local emergency response, public health, or drinking water supply agencies. No condition of this general permit shall release the permittee from any responsibility or requirements under other environmental statutes or regulations.

SECTION 5: INSPECTION, MAINTENANCE, AND CORRECTIVE ACTION

5.1 Inspection Personnel and Procedures (Part III.C of the Permit)

Personnel Responsible for Inspections

Name Mike Davies- Chief of Environmental Inspections

Certificate of attendance for a Responsible Personnel

Training Program ☒ Yes ☐ No ☐ N/A

4/29/2016

Has the Approval Authority waived the Certificate of

Training requirement?

☐ Yes ☐ No ☒ N/A

Inspection Schedule

Standard Frequency:

☐ Once every 4 business days

☒ Once each calendar week, and within 24 hours of a 0.25” rain or the occurrence of runoff from snowmelt sufficient to cause a discharge

Increased Frequency (if applicable):

For areas of sites discharging to sediment or nutrient-impaired waters or to waters designated as Tier

II.

☐ Twice each calendar week (Sunday to Saturday). Schedule within 24 hours of a 0.25” storm event or greater when reasonably possible.

Rain Gauge Location (if applicable)

TBD

Inspection Report Forms See Next Page

Instructions – Describe inspection procedures

Personnel Responsible

Inspection schedule

Record daily rainfall (See Appendix VI)

5.2 Corrective Action (Part III.D of the Permit)

The procedure for taking corrective action (in Harford County) is dependent on the type, duration, and severity of the activity that was out of compliance. Activities that have not resulted in excess sediment leaving the work site are issued a Minor Maintenance order that must be completed before the next inspection.

Maintenance Orders may be escalated to a Correction Notice if non-compliance continues or if the level of the non-compliance is substantial. If any part (or multiple parts) of the work site is determined to be out of compliance for a sustained period, a stop work order will be issued.

In the event that large quantities of sediment are observed leaving the site (due to contractor negligence) an immediate stop work order will be issued.

Personnel Responsible for Corrective Actions

Name and Title: Mike Davies, Chief Construction Inspector- Environmental

Telephone number: 410-638-3217 ext. 2434

Email: MTDavies@harfordcounytmd.gov

Area of site responsible for: All Limits of Disturbance and immediate area surrounding.

Corrective Action Forms

See Next Page

Instructions – Describe correction action

Describe the procedures for taking corrective action in compliance

SECTION 6: TRAINING (Part III.E of the Permit)

Documentation for Completion of Training

Name Describe Training Completion date

TBD TBD TBD

Instructions – Describe training

The following personnel, at a minimum, must receive training, and therefore should be listed individually in the table below:

Personnel who are responsible for the design, installation, maintenance, and repair of stormwater controls

Personnel responsible for the application and storage of treatment chemicals

Personnel who are responsible for conducting inspections

Personnel who are responsible for taking corrective actions

Personnel who are responsible for spill response

Personnel must be trained to understand the following if related to the scope of their job duties:

The permit deadlines associated with installation, maintenance, and removal of stormwater controls and with stabilization;

The location of all stormwater controls on the site required by this permit, and how they are to be maintained;

The proper procedures to follow with respect to the permit’s pollution prevention requirements; and

When and how to conduct inspections, record applicable findings, and take corrective actions.

Document all training.

SECTION 9: Appendices

9.1 Amendment Log

Use the table below to record any SWPPP Amendments.

No. Description of the Amendment Date of

Amendment

Amendment Prepared by

[Name(s) and Title]

9.2 Site Maps (Part III.F.2.d of the permit)

Instructions – Attach site maps

For most projects, a series of site maps is necessary and recommended.

The first should show the undeveloped site and its current features.

An additional map or maps should be created to show the developed site or, for more complicated sites, show the major phases of development.

Site maps must include the following features:

Boundaries of the property;

Locations where earth-disturbing activities will occur, noting any phasing of construction activities and any demolition activities;

Approximate slopes before and after major grading activities;

Note areas of steep slopes

Locations where sediment, soil, or other construction materials will be stockpiled;

Locations of any crossings of waters of this State;

Designated points where vehicles will exit onto paved roads;

Locations of structures and other impervious surfaces upon completion of construction; and

Locations of on-site and off-site construction support activity areas covered by this permit.

Locations of all waters of this State, including wetlands, on your site and within one mile downstream of the site’s discharge point.

Indicate which waterbodies are listed as impaired

Indicate which are identified as Tier II waters

Areas of federally listed critical habitat for endangered or threatened species within the site and/or at discharge locations.

Type and extent of pre-construction cover on the site

Examples: vegetative cover, forest, pasture, pavement, structures

Drainage pattern(s) of stormwater and authorized non-stormwater before and after major grading activities.

Stormwater and authorized non-stormwater discharge locations, including:

Locations where stormwater and/or authorized non-stormwater will be discharged to storm drain inlets; and

Locations where stormwater or allowable non-stormwater will be discharged to waters of this State (including wetlands).

Locations of all potential pollutant-generating activities.

Locations of stormwater controls, including natural buffer areas and any shared controls utilized to comply with the permit.

Locations where polymers, flocculants, or other treatment chemicals will be used and stored.

Site Maps

Responsive People | Creative Solutions www.rkk.com

Engineers | Construction Managers | Planners | Scientists

700 E. Pratt Street, Suite 500 | Baltimore, MD 21202

P: 410.728.2900

S C

A L

E i n c h H

C G

D W

G

I

N o

HARFORD COUNTY, MARYLAND

Drawn By :

Designed By :

Reviewed By :

Date :

e h a ig h t

B Y

FILE PATH:\\ad.rkk.com\fs\Cloud\Projects\2021\21155_HARCO\Task 025_Harford Community College Stream Restoration\CADD\60%\Plans\Impact Plates\pIP-0003_HCC.dgn

10/28/2025PLOTTED:

Drawing No. Sheet No.

Scale :

ofof

EH

B

B B

B

Scale :

STREAM RESTORATION

HARFORD COMMUNITY COLLEGE

KJH, AN

OCTOBER 2025

SCE

TAB

LEGENDLEGEND

20' 20'0 40'

SCALE: 1"=20'

LOG VANE

STAGING AND STOCKPILE AREA

TEMPORARY MULCH ACCESS ROAD

TEMPORARY ACCESS BRIDGE

STABILIZED CONSTRUCTION ENTRANCE (SCE) WETLANDS

WATERS OF THE U.S.

0 SF

FLOODPLAIN IMPACTS:

25' WETLAND BUFFER

IMPACT LEGEND

PROPOSED RIPRAP

PROPOSED CHANNEL

PROPOSED MINOR CONTOURS

PROPOSED MAJOR CONTOURS

25 FT. WETLAND BUFFER

WETLAND BOUNDARY

WATERS OF THE U.S.

EXISTING RIPRAP

EXISTING MINOR CONTOUR

EXISTING MAJOR CONTOUR

PROPERTY LINE

LIMIT OF DISTURBANCE (LOD)

F B

FB-3

1"=20'

IP-03IP-02

LOCATED WITHIN THE PROJECT STUDY AREA.

NOTE: THERE ARE NO 100-YEAR FEMA FLOODPLAIN

M A

TC

H

LIN

E

IP

-04

IMPACT PLATES

EH

0 SF

MDE PERMANENT

USACE PERMANENT/

MATCH LINE IP-01

TEMPORARY MULCH ACCESS ROAD

243 SF

MDE PERMANENT

873 SF

MDE TEMPORARY

WUS-D (INTERMITTENT)

WET-A (PEM)

WUS-A (PERENNIAL)

2822 SF/ 419 LF

MDE TEMPORARY

USACE PERMANENT/

SPRING HOUSE

FROM SPRING HOUSE

EXISTING 6" PIPE

355 TAB

Responsive People | Creative Solutions www.rkk.com

Engineers | Construction Managers | Planners | Scientists

700 E. Pratt Street, Suite 500 | Baltimore, MD 21202

P: 410.728.2900

S C

A L

E i n c h H

G

W

G

HARFORD COUNTY, MARYLAND

Drawn By :

Designed By :

Reviewed By :

Date :

e h a ig h t

B Y

FILE PATH:\\ad.rkk.com\fs\Cloud\Projects\2021\21155_HARCO\Task 025_Harford Community College Stream Restoration\CADD\60%\Plans\Impact Plates\pIP-0004_HCC.dgn

10/28/2025PLOTTED:

Drawing No. Sheet No.

Scale :

ofof

EH

B

B B

B

Scale :

STREAM RESTORATION

HARFORD COMMUNITY COLLEGE

KJH, AN

OCTOBER 2025

SCE

TAB

LEGENDLEGEND

20' 20'0 40'

SCALE: 1"=20'

LOG VANE

STAGING AND STOCKPILE AREA

TEMPORARY MULCH ACCESS ROAD

TEMPORARY ACCESS BRIDGE

STABILIZED CONSTRUCTION ENTRANCE (SCE) WETLANDS

WATERS OF THE U.S.

0 SF

FLOODPLAIN IMPACTS:

25' WETLAND BUFFER

IMPACT LEGEND

PROPOSED RIPRAP

PROPOSED CHANNEL

PROPOSED MINOR CONTOURS

PROPOSED MAJOR CONTOURS

25 FT. WETLAND BUFFER

WETLAND BOUNDARY

WATERS OF THE U.S.

EXISTING RIPRAP

EXISTING MINOR CONTOUR

EXISTING MAJOR CONTOUR

PROPERTY LINE

LIMIT OF DISTURBANCE (LOD)

FB-4

1"=20'

IP-03IP-03

G R A

D U

A T E

D

R

IV

E

2300 FACULTY COURT

KATHERINE E MULLIN

PATRICK J AND

M A T

H

L

IN

E

IP

LOCATED WITHIN THE PROJECT STUDY AREA.

NOTE: THERE IS NO FEMA 100-YEAR FLOODPLAIN

EH

TEMPORARY MULCH ACCESS ROAD

0 SF

MDE PERMANENT

USACE PERMANENT/

0 SF

MDE PERMANENT

0 SF

MDE PERMANENT

USACE PERMANENT/

0 SF

MDE PERMANENT

IMPACT PLATES

WUS-A (PERENNIAL)

WUS-F (INTERMITTENT)

5107 SF/ 646 LF

MDE TEMPORARY

USACE PERMANENT/

0 SF

MDE TEMPORARY

335 33

TAB

9.3 Sample Subcontractor Certifications/Agreements

You may use the sample below as a template to record any subcontractor agreements.

SUBCONTRACTOR CERTIFICATION

STORMWATER POLLUTION PREVENTION PLAN

Project Number:

Project Title:

Operator(s):

As a subcontractor, you are required to comply with the Stormwater Pollution Prevention Plan

(SWPPP) for any work that you perform on-site. Any person or group who violates any condition of the SWPPP may be subject to substantial penalties or loss of contract. You are encouraged to advise each of your employees working on this project of the requirements of the SWPPP. A copy of the SWPPP is available for your review at the office trailer.

Each subcontractor engaged in activities at the construction site that could impact stormwater must be identified and sign the following certification statement:

I certify under the penalty of law that I have read and understand the terms and conditions of the SWPPP for the above designated project and agree to follow the practices described in the

SWPPP.

This certification is hereby signed in reference to the above-named project:

Company:

Address:

Telephone Number:

Type of construction service to be provided:

Signature:

Title:

Date:

9.4 Cationic Chemical Treatment Approval Form

Use the form found on the construction website for approval for the use of Cationic Chemical

Additives: https://mde.maryland.gov/programs/water/wwp/Pages/gp_construction.aspx

When submitting for the approval of Cationic Chemical Additives, the form must be accompanied with the information contained in section 4.12 of the SWPPP. The approval authority may request additional information.

Remember that final approval from the appropriate authority must be received prior to the use of Cationic Chemical Additives.

9.5 Grading and Stabilization Activities Log

Use the table below to record any grading/stabilization activities.

Date

Grading

Activity

Initiated

Description of Grading Activity Description of

Stabilization Measure and Location

Date Grading

Activity Ceased

(Temporary or

Permanent)

Date When

Stabilization

Measures

Initiated

Date Date

☐ Temporary

☐ Permanent

Date

Date Date

☐ Temporary

☐ Permanent

Date

Date Date

☐ Temporary

☐ Permanent

Date

Date Date

☐ Temporary

☐ Permanent

Date

9.6 Rainfall Log

Use the table below to record the rainfall gauge readings at the beginning and end of each workday.

Month/Year Month/Year Month/Year

Day Start time End time Day Start time End time Day Start time End time

1 1 1

2 2 2

3 3 3

4 4 4

5 5 5

6 6 6

7 7 7

8 8 8

9 9 9

10 10 10

11 11 11

12 12 12

13 13 13

14 14 14

15 15 15

16 16 16

17 17 17

18 18 18

19 19 19

20 20 20

21 21 21

22 22 22

23 23 23

24 24 24

Month/Year Month/Year Month/Year

Day Start time End time Day Start time End time Day Start time End time

25 25 25

26 26 26

27 27 27

28 28 28

29 29 29

30 30 30

31 31 31

9.7 SWPPP Training Log

You may use the sample below as a template to record specific personnel training.

Stormwater Pollution Prevention Training Log

Project Name:

Project Location:

Instructor’s Name(s):

Instructor’s Title(s):

Course Location Date

Course

Length

(hours)

Stormwater Training Topic: (check as appropriate)

☐ Sediment and Erosion Controls ☐ Emergency Procedures

☐ Stabilization Controls ☐ Inspections/Corrective Actions

☐ Pollution Prevention Measures ☐ Other: ________________________

Specific Training Objective:

Attendee Roster:

No. Name of Attendee Company

(attach additional pages as necessary)