1-1-DA27000-24204520 Solicitation.pdf

PDF 494 KB Posted

Attached to
DFCM Construction - Invitational - DNR/DWR - New Loa Fish Hatchery Egg Tray Incubators - 24204520
Solicitation number
DA27000
Issued by
Utah

About this file

This is a solicitation document for the State of Utah's Division of Facilities Construction and Management (DFCM) for the design and construction of vertical egg tray incubators at the new Loa Fish Hatchery under project number 24204520. The solicitation is an invitational bid process limited to four pre-selected contractors: Integrated Aqua Systems, Inc., MariSource (Legends Brands, Inc.), Oceans Design/Gemini Fiberglass, and Pentair/PR Aqua. A mandatory meeting is required for all bidders, and responses must be submitted according to the timeline specified in the solicitation documents. The project involves procuring and installing specialized equipment to support hatchery operations.

The construction cost estimate for this project is $100,000.00. As an invitational solicitation, only the four designated contractors are permitted to bid on this opportunity. Additional details regarding pricing terms, payment schedules, specific technical requirements, equipment specifications, delivery timelines, and project completion deadlines would be contained within the full solicitation documents and scope of work.

View the file

Other files

File Type Posted
2-2-DA27000-24204520 Specifications.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Division of Facilities Construction and Management Taylorsville State Office Building 4315 South 2700 West, 3rd Floor

Taylorsville, Utah 84129 dfcm.utah.gov | 801.957.7270

Invitational Low Bid Procurement for Construction Services

Project budgets up to $150,000

July 2, 2026

New Loa Fish Hatchery - Egg Tray Incubators Department of Natural Resources – Division of Wildlife Resources

Loa, Utah

DFCM Project #DA27000 U3P Reference # 24204520

Project design provided by Sunrise Engineering

DFCM Invitational Low Bid for Construction Services, 5.15.2026 2

Solicitation Summary The State of Utah Division of Facilities Construction and Management (DFCM) is requesting bids for Construction services for the project below. Only the Contractors listed below are invited to bid on this project. Bids submitted by Contractors not listed below will not be considered for award.

- Integrated Aqua Systems, Inc. - ryan@integrated-aqua.com

- MariSource (Legends Brands, Inc.) - salesorderdesk@legendbrands.net

- Oceans Design / Gemini Fiberglass - michael@oceansdesigninc.com

- Pentair / PR Aqua - ian.race@praqua.com

New Loa Fish Hatchery Egg Tray Incubators

DNR/DWR

Loa, Utah DFCM Project #24204520 | U3P Reference # DA27000

Communication during the selection process shall be directed to the DFCM Representatives below only.

DFCM Project Manager: Craig Mackay cmackay@utah.gov 385-831-5027 Brief Project Description: DWR is looking for a supplier/manufacturer to provide vertical egg tray incubators for the new Loa Hatchery.

Substantial Completion Date: January 29, 2027 Liquidated Damages: $500 per day Construction Budget: $100,000.00 Tax Exempt: Yes ☐ No ☒ Energy Incentives: Yes ☐ No ☒

Solicitation Schedule Event Date Time Location

Solicitation Posting Thursday, July 2, 2026 3:00 PM U3P

Mandatory Meeting Wednesday, July 15, 2026 12:00 PM ☒Virtual:

meet.google.com/mwd-ryyd-tci

Questions Deadline Monday, July 20, 2026 3:00 PM U3P

Addendum Deadline Thursday, July 23, 2026 3:00 PM U3P

Bid Deadline Tuesday, July 28, 2026 3:00 PM U3P

Subcontractor Lists Deadline Wednesday, July 29, 2026 3:00 PM Email to:

dfcmcontracts@utah.gov https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities mailto:dfcmcontracts@utah.gov

DFCM Invitational Low Bid for Construction Services, 5.15.2026 3

Project Details Detailed Project Description/Base Bid:

The Supplier shall be responsible for the manufacture, supply, and delivery of eighteen (18) twelve-tray vertical incubators. The selected Supplier is required to provide all specified equipment to the Loa Fish Hatchery between January 15, 2027 and January 29, 2027. The selected supplier will need to provide a submittal package to the Owner within six (6) weeks of the notice to proceed for review and approval. Upon delivery, the Owner's Contractor will be responsible for the assembly and physical installation of the incubators.

Equipment Scope & Specifications

• Vertical Egg Tray Incubators (Qty: 18): Twelve-tray vertical incubators that are equal to the basis of design, which is the Marisource 12-tray vertical incubator (model CPM5613).

• Required Components: The equipment package must include associated isolation panels, top panels, and drip trays.

• Physical Properties & Drainage: The drip tray must be configured so that the drain fittings discharge directly into the trench drains located on the front side of the incubator. Additionally, the incubator must slope 1/2" toward the drip tray discharge.

• Installation: The Owner's Contractor will be responsible for the actual assembly and installation of the incubators, following the manufacturer's recommendations and installation documents.

Additive Alternates:

N/A

Project Requirements:

- DFCM Approved Fabricator List

- DFCM Design Management Documents

- DFCM Roofing Design Requirements

- State of Utah High Performance Building Standard and all appendixes https://dfcm.utah.gov/construction-management/building-official/inspections-and-testing/ https://dfcm.utah.gov/construction-management/standard-documents/ https://dfcm.utah.gov/construction-management/roofing-program/ https://dfcm.utah.gov/construction-management/high-performance-building-program/

DFCM Invitational Low Bid for Construction Services, 5.15.2026 4

Solicitation Documents The solicitation documents consist of all documents listed below and referenced within this solicitation.

Solicitation Documents and Forms The following project specific documents and forms can be accessed in the U3P project for this solicitation.

Project specific documents:

- Invitational Low Bid Solicitation

- Approved Specifications

Standard documents and forms:

- DFCM Subcontractor List Form & Instructions

DFCM Construction Management Standard Reference Documents All DFCM standard documents referenced in this solicitation can be accessed by visiting the DFCM Construction Management – Standard Documents page of the DFCM website.

http://www.dfcm.utah.gov/

DFCM Invitational Low Bid for Construction Services, 5.15.2026 5

Procurement Process

1. Mandatory Meeting A mandatory meeting will be held on the date and time and at the location specified on the Solicitation Schedule. All prime Contractors wishing to bid on this project must attend and sign in. Contractors not in attendance at this meeting are ineligible to bid on this project. Subcontractors and suppliers are invited to attend this meeting, but it is not mandatory.

During the mandatory meeting, a presentation will be made describing the overall scope of work and intended project schedule. Interested Contractors may ask questions and request clarification about the project and the procurement process.

2. Requests for Information, Questions and Addendum All project related requests for information, clarifications, and questions must be submitted to DFCM via the U3P website no later than the time and date specified on the Solicitation Schedule. An addendum in response will be posted on the U3P website no later than the time and date specified on the Solicitation Schedule. All addenda issued shall become part of the solicitation, and any changes or additional requirements shall be incorporated into the Contractor’s proposal and/or bid.

a) Interpretation of Drawings and Specifications If any person or entity contemplating submitting a proposal or bid is in doubt as to the meaning of any part of the drawings, specifications or other contract documents, such person shall submit a request for an interpretation to DFCM via the U3P website no later than the time and date specified on the Solicitation Schedule. Any interpretation of the proposed documents will be made only by addenda posted on the U3P website. Neither DFCM nor A/E will be responsible for any other explanations or interpretations of the proposed documents. The A/E is deemed to be the architect or engineer hired by DFCM as the A/E or Consultant for the project.

b) Product Approvals Where reference is made to one or more proprietary products in the contract documents, but restrictive descriptive materials of one or more manufacturer(s) is referred to in the contract documents, the products of other manufacturers will be accepted, provided they equal or exceed the standards set forth in the drawings and specifications and are compatible with the intent and purpose of the design, subject to the written approval of the A/E. Such written approval must occur prior to the time and date specified on the Solicitation Schedule for the final addendum. The A/E’s written approval will be issued in an addendum. If the descriptive material is not restrictive, the products of other manufacturers specified will be accepted without prior approval provided they are compatible with the intent and purpose of the design as determined by the A/E.

3. Bidding, Bid Deadline, and Bid Bonds Bids must be submitted via the U3P website no later than the time and date specified on the Solicitation Schedule.

Contractors attempting to submit a bid through U3P website after the bid deadline has passed will not be successful and therefore disqualified from consideration of award of this project. It is the sole responsibility of the Contractor to confirm their bid is successfully submitted into U3P prior to the bid deadline.

Technical questions related to bidding in U3P should be directed to u3padmin@utah.gov.

After the bid deadline listed on the Solicitation Schedule has passed, the bid tabulation will be available within the following 24 hours in U3P and the Contract award will go to the Contractor submitting the lowest responsive and responsible bid.

Before submitting a bid, the Contractor shall carefully examine the solicitation; shall visit the site of the Work; shall fully inform themselves as to all existing conditions and limitations; and shall include in their bid the cost of all items required by the solicitation. If the Contractor observes that portions of the Contract Documents are at variance with applicable laws, building codes, rules, regulations or contain obvious erroneous or uncoordinated information, the Contractor shall promptly notify the DFCM Project Manager, and the necessary changes shall be accomplished by addendum.

https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities mailto:u3padmin@utah.gov

DFCM Invitational Low Bid for Construction Services, 5.15.2026 6

By submitting a bid, in any format, the Bidder / Offeror / Vendor certifies that: (1) no product to be supplied by the Bidder / Offeror / Vendor in connection with this Solicitation is a “forced labor product” as that term is defined in Utah Code 63G-6a-121; and (2) to the extent, if any, that this Solicitation involves technology, or technology services, networks or systems, the Bidder / Offeror / Vendor is not a “restricted foreign entity” as that term is defined in Utah Code 63G-6a-121.

a) Bid Bonds A bid bond properly signed by the Contractor and a qualified surety and submitted on the AIA Document A310 – 2010 Bid Bond form, or equivalent, in the amount of 5% of the bid, must accompany the bid submitted within U3P. If the bid bond is not provided with the bid, the bid is nonresponsive, and the Contractor may be disqualified from the selection process.

The bid bond must be submitted on the AIA document A310 – 2010 Bid Bond Form, or equivalent, to be accepted unless only one bid is received by DFCM, or the failure to comply with the bid bond requirements is determined by the Director of DFCM to be immaterial based on the following:

1. the bid bond is submitted on a form other than the AIA Document A310 – 2010 Bid Bond form, or equivalent, and the bid bond meets all other requirements including being issued by a surety firm authorized to do business in the State of Utah and be listed in the U.S. Department of the Treasury Circular 570, Companies Holding Certificates of Authority as Acceptable Securities on Federal Bonds and as Acceptable Reinsuring Companies for an amount not less than the amount of the bond to be issued. A co-surety may be utilized to satisfy this requirement; and

2. the Contractor provides a bid bond properly signed by a qualified surety and on the AIA Document A310 – 2010 Bid Bond form, or equivalent, by the close of business of the next business day after DFCM notifies the Contractor of the defective bid bond.

4. Termination and Debarment By submitting a bid, the Contractor certifies that neither it nor its principals, including project nor site managers, have been, or are under consideration for, debarment or suspension, or any action that would exclude such from participation in a construction Contract by any governmental department or agency. If the Contractor cannot certify this statement, provide a detailed written explanation to dfcmcontracts@utah.gov by the time and date specified as the bid deadline on the Solicitation Schedule. DFCM reserves the right to reject the Contractor’s explanation and disqualify them from the selection process.

5. Listing of Subcontractors All Contractors are required to submit their DFCM Subcontractors List Form to dfcmcontracts@utah.gov by the time and date specified on the Solicitation Schedule. The DFCM Subcontractors List Form & Instructions can be found on the DFCM website – Construction Management - Standard Documents page and is also posted in U3P.

If the DFCM Subcontractors List Form is not provided by the time and date specified on the Solicitation Schedule, the bid is nonresponsive, and the Contractor may be disqualified from the selection process.

DFCM retains the right to audit or take other steps necessary to confirm compliance with requirements for the listing and changing of subcontractors. Any Contractor who is found incompliant with these requirements is subject to a debarment hearing and may be debarred from consideration for award of DFCM contracts for a period not to exceed three years.

6. Withdrawal of Bids Bids may be withdrawn on written request received from bidder prior to the time fixed for opening. Negligence on the part of the bidder in preparing the bid confers no right for the withdrawal of the bid after it has been opened.

7. DFCM Reservation of Rights The Division of Facilities Construction and Management reserves the right to reject any or all proposals or bids or to waive any formality or technicality in any proposal or bid in the best interest of the State.

mailto:dfcmcontracts@utah.gov mailto:dfcmcontracts@utah.gov

DFCM Invitational Low Bid for Construction Services, 5.15.2026 7

8. Contract and Bonding Requirements DFCM intends to enter into a Short Form Construction Contract with the Contractor submitting the lowest responsive and responsible bid. A copy of the Short Construction Contract and the corresponding Contract Conditions can be found on the DFCM website – Construction Management - Standard Documents page.

9. Licensure The Contractor shall comply with and require all subcontractors to comply with the license laws as required by the State of Utah.

10. Financial Responsibility of Contractors, Subcontractors and Sub-subcontractors Contractors shall respond promptly to any inquiry in writing by DFCM to any concern of financial responsibility of the Contractor, Subcontractor or Sub-subcontractor.