09_City of Brighton Standard General Conditions for Construction Contracts_10.11.2024.pdf
PDF 509 KB Posted
- Solicitation number
- 25-009037
- Issued by
- Adams County, Colorado
About this file
This document is the Standard General Conditions for Construction Contracts for the City of Brighton, Colorado, dated 10.11.2024. The document outlines the comprehensive legal and procedural framework governing construction contracts, specifically for the 18th Avenue Sanitary Sewer Rerouting Construction project. It provides detailed definitions, guidelines, and expectations for contractors, covering aspects such as contract initiation, work performance, payments, changes, inspections, and potential termination. The document establishes the roles and responsibilities of the City, the Design Professional, and the Contractor throughout the construction process, including preconstruction requirements, progress schedules, submittals, and quality control measures.
The contract terms include provisions for contract price adjustments, payment procedures, and conditions for potential work modifications. The document specifies that contractors must provide detailed documentation, maintain work quality, and adhere to specified timelines and regulatory requirements. Financial arrangements include progress payments based on completed work, with provisions for retainage, final payment conditions, and potential claims resolution. The contract also addresses potential delays, work suspensions, and termination scenarios, providing a comprehensive risk management framework for both the City and the contracted construction entity. The Standard General Conditions serve as a critical governance document to ensure clear expectations, minimize disputes, and establish a structured approach to managing the construction project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
10.11.2024
STANDARD GENERAL CONDITIONS OF THE
CONSTRUCTION CONTRACT
Standard General Conditions of the Construction Contract
STANDARD GENERAL CONDITIONS OF THE
CONSTRUCTION CONTRACT
TABLE OF CONTENTS
ARTICLE 1- DEFINITIONS
ARTICLE 2 - PRELIMINARY MATTERS
2.1. Before Starting Construction or Work
2.2. Preconstruction Conference
2.3. Initially Acceptable Schedules
ARTICLE 3 - CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE
3.1. Intent
3.2. Reference to Standards and Specifications of Technical Societies; Reporting and
Resolving Discrepancies
3.3. Review or Judgement of Design Professional
3.4. Amending Contract Documents
3.5. Supplementing Contract Documents
3.6. Reuse of Documents
ARTICLE 4 - AVAILABILITY OF LANDS;
SUBSURFACE AND PHYSICAL CONDITIONS; REFERENCE POINT
4.1. Availability of Lands
4.2. Subsurface and Physical Conditions
4.3. Physical Conditions—Underground Facilities
4.4. Reference Points
4.5. Asbestos, PCBs, Petroleum, Hazardous Waste or Radioactive Material
ARTICLE 5 - CONTRACTOR'S RESPONSIBILITIES
5.1. Supervision and Superintendence
5.2. Labor, Materials and Equipment
5.3. Progress Schedule
5.4. Substitutes and “Or-Equal” Items
5.5. Concerning Subcontractors, Suppliers and Others
5.6. Patent Fees and Royalties
5.7. Permits
5.8. Laws and Regulations:
5.9. Taxes
5.10. Use of Premises
5.11. Record Documents
5.12. Safety and Protection
5.13. Safety Representative
5.14. Hazard Communication Programs
5.15. Emergencies
5.16. Shop Drawings and Samples
5.17. Submittal Procedures
5.18. Continuing the Work
5.19. Contractor's General Warranty and Guarantee
5.20. Indemnification
ARTICLE 6 - OTHER WORK
6.1. Related Work at Site
6.2. Coordination
ARTICLE 7 - CITY'S RESPONSIBILITIES
7.1. Communications
7.2. Substitute Design Professional
7.3. Lands
7.4. Change Orders
7.5. Inspections, Tests, Approvals
7.6. Limitations on City's Authority and Responsiblities
7.7. Contaminants
7.8. Financial Arragements
ARTICLE 8 - DESIGN PROFESSIONAL'S STATUS DURING CONSTRUCTION
9.1. City’s Representative:
9.2 Visits to Site
9.3 Project Representative
9.4 Clarifications and Interpretations
9.5 Authorized Variations in Work
9.6 Rejecting Defective Work
9.7. Shop Drawings, Change Orders and Payments
9.8. Determinations for Unit Prices
9.9. Decisions on Disputes
9.10. Limitations on Design Professional's Authority and Responsibilities
ARTICLE 9 - CHANGES IN THE WORK
9.1. Authority to Approve Changes
9.2 City may Order Changes
9.3 Limits on Increases in Price or Time
9.4 Change Orders
9.5 Notice to Surety
9.6 Limitations on Change Orders, Generally
9.10. Limitations on ENGINEER’s Authority and Responsibilities
ARTICLE 10 - CHANGES IN THE CONTRACT PRICE
10.1. Contract Price
10.2. Claim for Change
10.3. Determination of Value Work
10.4. Cost of the Work
10.5. Cost of the Work Not to Include
10.6. Contractor's Fee
10.7. Cost Records
10.8. Cash Allowance
10.9. Unit Price Work
ARTICLE 11 - CHNAGES OF CONTRACT TIMES
11.1. Claim for Change to the Contract Times
11.2. Time of the Essence
11.3. Delay
11.4. Sole Remedy …………………………………………………………………………………………………………………………….
ARTICLE 12 - TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR
ACCEPTANCE OF DEFECTIVE WORK
12.1. Notice of Defects
12.2. Access to the Work
12.3. Tests and Inspections
12.4. Uncovering Work
12.5. City May Stop the Work
12.6. Correction or Removal of Defective Work
12.7. Correction Period
12.8. Acceptance of Defective Work
12.9. City May Correct Defective Work
ARTICLE 13 - PAYMENTS TO CONTRACTORS AND COMPLETION
13.1. Schedule of Values
13.2. Application for Progress Payment
13.3. Contractor's Warranty of Title
13.4. Review of Applications for Progress Payment
13.5. Substantial Completion
13.6. Partial Utilization
13.7. Final Inspection
13.8. Final Application for Payment
13.9. Final Payment and Acceptance
ARTICLE 14 - SUSPENSION OF WORK AND TERMINATION
14.1. City May Suspend Work
14.2. City May Terminate
14.3. Contractor May Stop Work or Terminate
ARTICLE 1 - DEFINITIONS
Wherever used in these General Conditions or in the other Contract Documents the following terms have the meanings indicated which are applicable to both the singular and plural thereof:
1.1. Addenda—Written or graphic instruments issued prior to the opening of Bids that clarify, correct or change the Bidding Requirements or the Contract Documents.
1.2. Contract—The written document between City and Contractor covering the Work to be performed; other Contract Documents are attached to the Contract and incorporated therein by reference.
1.3. Application for Payment—The City approved form accepted by Design
Professional that is to be used by Contractor in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the Contract Documents.
1.4. Asbestos—Any material that contains more than one percent (1%) asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the
United States Occupational Safety and Health Administration.
1.5. Bid—The offer or proposal of the bidder submitted on the prescribed form setting forth the prices for the Work to be performed.
1.6. Bidding Documents—The advertisement or invitation to Bid, instructions to bidders, the Bid form, and the proposed Contract Documents (including all Addenda issued prior to receipt of Bids).
1.7. Bidding Requirements—The advertisement or invitation to Bid, instructions to bidders, and the Bid form.
1.8. Bonds—A form of financial surety as defined in solicitation. Performance and Payment bonds and other instruments of security.
1.9. Change Order—A document, submitted by any party, requesting an addition, deletion, or revision in the Work, or an adjustment in the Contract Price or the Contract Term, issued on or after the Effective Date of the Contract.
1.10. City—The City of Brighton
1.11. Contract Documents—The Agreement, Addenda (that pertain to the Contract
Documents), Solicitation, Detailed Scope, Contractor's Bid (including documentation accompanying the Bid and any post Bid documentation submitted prior to the Notice of Award) when attached as an exhibit to the Contract, the Notice to Proceed, the Bonds, these General Conditions, the
Supplementary Conditions, the Specifications and the Drawings as the same are more specifically identified in the Contract, together with all Written Amendments, Change Orders, Work Change Directives, Field Orders and Design Professional's written interpretations and clarifications issued pursuant to paragraphs
3.4., 3.5.1., and 3.5.3. on or after the Effective Date of the Contract. Shop Drawing submittals approved pursuant to paragraphs 5.17.4. and 5.17.5. and the reports and drawings referred to in paragraphs 4.2.1.1. and 4.2.1.2. are not Contract Documents.
1.12. Contract Price— The price payable to the successful/selected bidder as specified in the Contract, subject to such additions and adjustments thereto or deductions there from, as may be made pursuant to the Contract (subject to the provisions of paragraph 10.9.1. in the case of Unit
Price Work.
1.13. Contract Term—The numbers of days or the dates stated in the Contract to achieve
Substantial Completion.
1.14. Contractor—The person, firm or corporation with whom City has entered into the
Contract.
1.15. Defective—An adjective that when modifying the word Work refers to Work that is unsatisfactory, faulty or deficient; Work that does not conform to the Contract Documents; Work that does not meet the requirements of any inspection, reference standard, test or approval referred to in the Contract Documents; or Work that has been damaged prior to Design Professional's recommendation of final payment (unless responsibility for the protection thereof has been assumed by City at Substantial Completion in accordance with paragraph 13.5. or 13.6.).
1.16. Design Professional—The person, firm or corporation named as such in the
1.17. Design Professional's Consultant—A person, firm or corporation having a contract with Design Professional to furnish services as Design Professional's independent professional associate or consultant with respect to the Project and who is identified as such in the
Supplementary Conditions.
1.18. Drawings—The drawings, which are synonymous with construction plans, that show the scope, extent and character of the Work to be furnished and performed by Contractor and that have been prepared or approved by Design Professional and are referred to in the Contract
Documents. Shop drawings are not Drawings as so defined.
1.19. Effective Date of the Contract—The date indicated in the Contract on which it becomes effective, but if no such date is indicated it means the date on which the Contract is signed and delivered by the last of the two parties to sign and deliver.
1.20. Field Order—A written order issued by Design Professional that orders minor changes in the Work in accordance with paragraph 8.5. but that does not involve a change in the
Contract Price or the Contract Term.
1.21. Hazardous Waste—The term Hazardous Waste shall have the meaning provided in
Section 1004 of the Solid Waste Disposal Act (42 USC Section 6903) as amended from time to time.
1.22. Laws and Regulations; Laws or Regulations—Any and all applicable laws, rules, regulations, ordinances, codes and orders of any and all governmental bodies, agencies, authorities and courts having jurisdiction.
1.23. Liens—Liens, charges, security interests or encumbrances upon real property or personal property.
1.24. Milestone—A principal event specified in the Contract Documents relating to an intermediate completion date or time prior to Substantial Completion of all the Work.
1.25. Notice of Award—The written notice by City to the apparent successful bidder stating that upon compliance by the apparent successful bidder with the conditions precedent enumerated therein, within the time specified, City will sign and deliver the Contract.
1.26. Notice to Proceed—A written notice given by City to Contractor (with a copy to
Design Professional) fixing the date on which the Contract Term will commence to run and on which Contractor shall start to perform Contractor's obligations under the Contract Documents.
1.27. Official Holidays— New Year’s Day, Martin Luther King Day, President’s Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, Day after
Thanksgiving Day, Christmas Eve Day, Christmas Day.
1.28. Partial Utilization—Use by City of a substantially completed part of the Work for the purpose for which it is intended (or a related purpose) prior to Substantial Completion of all the Work.
1.29. PCBs—Polychlorinated biphenyls.
1.30. Petroleum—Petroleum, including crude oil or any fraction thereof which is liquid at standard conditions of temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square inch absolute), such as oil, petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene, and oil mixed with other non-Hazardous Wastes and crude oils.
1.31. Project—The total construction of which the Work to be provided under the Contract Documents may be the whole, or a part as indicated elsewhere in the Contract Documents.
1.32. Radioactive Material—Source, special nuclear, or byproduct material as defined by the Atomic Energy Act of 1954 (42 USC Section 2011 et seq.) as amended from time to time.
1.33. Regular Working Hours— The authorized working hours to be defined by City’s project manager.
1.34. Resident Project Representative—The authorized representative of Design
Professional who may be assigned to the site or any part thereof.
1.35. Samples—Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and that establish the standards by which such portion of the Work will be judged.
1.36. Shop Drawings—All drawings, diagrams, illustrations, schedules and other data or information that are specifically prepared or assembled by or for Contractor and submitted by
Contractor to illustrate some portion of the Work.
1.37. Specifications—Those portions of the Contract Documents consisting of written technical descriptions of materials, equipment, construction systems, standards and workmanship as applied to the Work and certain administrative details applicable thereto.
1.38. Subcontractor—An individual, firm or corporation having a direct contract with
Contractor or with any other Subcontractor for the performance of a part of the Work at the site.
1.39. Substantial Completion—The Work (or a specified part thereof) has progressed to the point where, in the opinion of Design Professional as evidenced by Design Professional's definitive certificate of Substantial Completion, it is sufficiently complete, in accordance with the
Contract Documents, so that the Work (or specified part) can be utilized for the purposes for which it is intended; or if no such certificate is issued, when the Work is complete and ready for final payment as evidenced by Design Professional's written recommendation of final payment in accordance with paragraph 13.9.1. The terms "substantially complete" and "substantially completed" as applied to all or part of the Work refer to Substantial Completion thereof.
1.40. Supplementary Conditions—The part of the Contract Documents that amends or supplements these General Conditions.
1.41. Supplier—A manufacturer, fabricator, supplier, distributor, materialman or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or any Subcontractor.
1.42. Underground Facilities—All pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels or other such facilities or attachments, and any encasements containing such facilities that have been installed underground to furnish any of the following services or materials:
electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, sewage and drainage removal, traffic or other control systems or water.
1.43. Unit Price Work—Work to be paid for on the basis of unit prices.
1.44. Work—The entire completed construction or the various separately unidentifiable parts thereof required to be furnished under the Contract Documents. Work includes and is the result of performing or furnishing labor and furnishing and incorporating materials and equipment into the construction, and performing or furnishing services and furnishing documents, all as required by the Contract Documents.
1.45. Work Change Directive—A written directive to Contractor, issued on or after the
Effective Date of the Contract and approved by City and recommended by Design Professional, ordering an addition, deletion or revision in the Work, or responding to differing or unforeseen physical conditions under which the Work is to be performed as provided in paragraph 4.2. or 4.3.
or to emergencies under paragraph 5.15. A Work Change Directive will not change the Contract
Price or the Contract Term, but is evidence that the parties expect that the change directed or documented by a Work Change Directive will be incorporated in a subsequently issued Change
Order following negotiations by the parties as to its effect, if any, on the Contract Price or Contract
Term as provided in paragraph 9.5.
1.46. Contract Amendment—A written amendment of the Contract Documents, signed by City and Contractor on or after the Effective Date of the Contract and normally dealing with the non-engineering or non-technical rather than strictly construction-related aspects of the
Contract Documents.
ARTICLE 2 - PRELIMINARY MATTERS
2.1. Before Starting Construction or Work:
2.1.1. Before undertaking the Work, Contractor shall carefully study and compare the Contract Documents and check and verify pertinent figures shown thereon and all applicable field measurements. Contractor shall promptly report in writing to Design
Professional any conflict, error, ambiguity or discrepancy which Contractor may discover and shall obtain a written interpretation or clarification from Design Professional before proceeding with any Work affected thereby; however, Contractor shall not be liable to City or Design Professional for failure to report any conflict, error, ambiguity or discrepancy in the Contract Documents, unless Contractor knew or reasonably should have known thereof.
2.1.2. Contractor shall submit to Design Professional and the City for review:
2.1.2.1. a preliminary progress schedule indicating the times (numbers of days or dates) for starting and completing the various stages of the Work, including any Milestones specified in the Contract Documents;
2.1.2.2. a preliminary schedule of Shop Drawing and Sample submittals that will list each required submittal and the times for submitting, reviewing and processing such submittal;
2.1.2.3. a preliminary schedule of values for all of the Work that will include quantities and prices of items aggregating the Contract Price and will subdivide the Work into component parts in sufficient detail to serve as the basis for progress payments during construction. Such prices will include an appropriate amount of overhead and profit applicable to each item of Work;
2.1.2.4 a cash flow distribution schedule to be approved by City and Design Professional.
2.1.3. Before any Work at the site is started, Contractor shall deliver to City, with copies to each additional insured identified in the Supplementary Conditions, certificates of insurance that Contractor is required to purchase and maintain in accordance with paragraph 5.3.
2.2. Preconstruction Conference: Within twenty days after the Contract Times start to run, but before any Work at the site is started, a conference attended by Contractor, Design
Professional and others as appropriate will be held to establish a working understanding among the parties as to the Work and to discuss the schedules referred to in paragraph 2.1.2., procedures for handling Shop Drawings and other submittals, processing Applications for Payment and maintaining required records.
2.3. Initially Acceptable Schedules: Unless otherwise provided in the Contract
Documents, at least ten days before submission of the first Application for Payment a conference attended by Contractor, Design Professional and others as appropriate will be held to review for acceptability to Design Professional as provided below the schedules submitted in accordance with paragraph 2.1.2. Contractor shall have an additional ten days to make corrections and adjustments and to complete and resubmit the schedules. No progress payment shall be made to Contractor until the schedules are submitted to and acceptable to Design Professional as provided below. The progress schedule will be acceptable to Design Professional as providing an orderly progression of the Work to completion within any specified Milestones and the Contract Term, but such acceptance will neither impose on Design Professional responsibility for the sequencing, scheduling or progress of the Work nor interfere with or relieve Contractor from Contractor's full responsibility therefor. Contractor's schedule of Shop Drawing and Sample submissions will be acceptable to Design Professional as providing a workable arrangement for reviewing and processing the required submittals. Contractor's schedule of values will be acceptable to Design
Professional as to form and substance.
ARTICLE 3 - CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE
3.1. Intent:
3.1.1. The Contract Documents comprise the entire Contract between City and
Contractor concerning the Work. The Contract Documents are complementary; what is called for by one is as binding as if called for by all. The Contract Documents will be construed in accordance with the laws of the State of Colorado.
3.1.2. It is the intent of the Contract Documents to describe a functionally complete Project (or part thereof) to be constructed in accordance with the Contract
Documents. Any Work, materials or equipment that may reasonably be inferred from the
Contract Documents or from prevailing custom or trade usage as being required to produce the intended result will be furnished and performed whether or not specifically called for.
When words or phrases that have a well-known technical or construction industry or trade meaning are used to describe Work, materials or equipment, such words or phrases shall be interpreted in accordance with that meaning. Clarifications and interpretations of the Contract Documents shall be issued by Design Professional as provided in paragraph 8.4.
3.2. Reference to Standards and Specifications of Technical Societies; Reporting and
Resolving Discrepancies:
3.2.1. Reference to standards, specifications, manuals or codes of any technical society, organization or association, or to the Laws or Regulations of any governmental authority, whether such reference be specific or by implication, shall mean the latest standard, specification, manual, code or Laws or Regulations in effect at the time of opening of Bids (or, on the Effective Date of the Contract if there were no Bids), except as may be otherwise specifically stated in the Contract Documents.
3.2.2. If, during the performance of the Work, Contractor discovers any conflict, error, ambiguity or discrepancy within the Contract Documents or between the Contract
Documents and any provision of any such Law or Regulation applicable to the performance of the Work or of any such standard, specification, manual or code or of any instruction of any Supplier referred to in paragraph 5.2.3., Contractor shall report it to Design
Professional and City in writing at once, and, Contractor shall not proceed with the Work affected thereby (except in an emergency as authorized by paragraph 5.15.) until an amendment or supplement to the Contract Documents has been issued by one of the methods indicated in paragraph 3.4. or 3.5.; provided, however, that Contractor shall not be liable to City or Design Professional for failure to report any such conflict, error, ambiguity or discrepancy unless Contractor knew or reasonably should have known thereof.
3.2.3. The provisions of the Construction Contract shall supersede any conflicting provisions of any other Contract Document. The provisions of the Specifications and
Drawings, if any, shall supersede any conflicting provisions of any other Contract
Document except the Construction Contract. The provisions of the Supplementary
Conditions shall supersede any conflicting provisions of any other Contract Document, except the provisions of the Construction Contract or the Specifications and Drawings.
3.2.4. Except as otherwise specifically stated in the Contract Documents or as may be provided by amendment or supplement thereto issued by one of the methods indicated in paragraph 3.4. or 3.5. the provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity or discrepancy between the provisions of the
Contract Documents and:
3.2.4.1. the provisions of any such standard, specification, manual, code or instruction (whether or not specifically incorporated by reference in the Contract
Documents); or
3.2.4.2. the provisions of any such Laws or Regulations applicable to the performance of the Work (unless such an interpretation of the provisions of the
Contract Documents would result in violation of such Law or Regulation).
No provision of any such standard, specification, manual, code or instruction shall be effective to change the duties and responsibilities of City, Contractor, or Design
Professional, or any of their subcontractors, consultants, agents, or employees from those set forth in the Contract Documents, nor shall it be effective to assign to City, Design
Professional or any of Design Professional's Consultants, agents or employees any duty or authority to supervise or direct the furnishing or performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of paragraph 8.10 or any other provision of the Contract Documents.
3.3. Review or Judgment of Design Professional:
Whenever in the Contract Documents the terms "as ordered," "as directed," "as required," "as allowed," "as approved" or terms of like effect or import are used, or the adjectives "reasonable,"
"suitable," "acceptable," "proper" or "satisfactory" or adjectives of like effect or import are used to describe a requirement, direction, review or judgment of Design Professional as to the Work, it is intended that such requirement, direction, review or judgment will be solely to evaluate, in general, the completed Work for compliance with the requirements of and information in the
Contract Documents and conformance with the design concept of the completed Project as a functioning whole as shown or indicated in the Contract Documents (unless there is a specific statement indicating otherwise). The use of any such term or adjective shall not be effective to assign to Design Professional any duty or authority to supervise or direct the furnishing or performance of the Work or any duty or authority to undertake responsibility contrary to the provisions of paragraph 9.10 or any other provision of the Contract Documents.
3.4. Amending Contract Documents: The Contract Documents may be amended to provide for additions, deletions and revisions in the Work or to modify the terms and conditions thereof in one or more of the following ways:
3.4.1. a formal Written Amendment,
3.4.2. a Change Order (pursuant to paragraph 9.4), or
3.4.3. a Work Change Directive (pursuant to paragraph 9.2).
3.5. Supplementing Contract Documents: In addition, the requirements of the Contract
Documents may be supplemented, and minor variations and deviations in the Work may be authorized, in one or more of the following ways:
3.5.1. a Field Order (pursuant to paragraph 8.5),
3.5.2. Design Professional's approval of a Shop Drawing or Sample (pursuant to paragraphs 5.17.4. and 5.17.5.), or
3.5.3. Design Professional's written interpretation or clarification (pursuant to paragraph 9.4).
3.6. Reuse of Documents: Contractor, and any Subcontractor or Supplier or other person or organization performing or furnishing any of the Work under a direct or indirect contract with
City (i) shall not have or acquire any title to or Ownership rights in any of the Drawings, Specifications or other documents (or copies of any thereof) prepared by or bearing the seal of
Design Professional or Design Professional's Consultant, and (ii) shall not reuse any of such
Drawings, Specifications, other documents or copies on extensions of the Project or any other project without written consent of City and Design Professional and specific written verification or adaption by Design Professional.
ARTICLE 4 - AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL
CONDITIONS; REFERENCE POINTS
4.1. Availability of Lands: City shall furnish, as indicated in the Contract Documents, the lands upon which the Work is to be performed, rights-of-way and easements for access thereto, and such other lands that are designated for the use of Contractor. City shall identify any encumbrances or restrictions not of general application but specifically related to use of lands so furnished with which Contractor will have to comply in performing the Work. Easements for permanent structures or permanent changes in existing facilities will be obtained and paid for by
City, unless otherwise provided in the Contract Documents. If Contractor and City are unable to agree on entitlement to or the amount or extent of any adjustments in the Contract Price or the
Contract Term as a result of any delay in City's furnishing these lands, rights-of-way or easements, Contractor may make a claim therefor as provided in Articles 10 and 11., shall provide for all additional lands and access thereto that may be required for temporary construction facilities or storage of materials and equipment.
4.2. Subsurface and Physical Conditions:
4.2.1. Reports and Drawings: Reference is made to the Supplementary Conditions for identification of:
4.2.1.1. Subsurface Conditions: Those reports of explorations and tests of subsurface conditions at or contiguous to the site that have been utilized by Design
Professional in preparing the Contract Documents; and
4.2.1.2. Physical Conditions: Those drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the site
(except Underground Facilities) that have been utilized by Design Professional in preparing the Contract Documents.
4.2.2. Limited Reliance by Contractor Authorized; Technical Data: Contractor may rely upon the general accuracy of the “technical data” contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such “technical data” is identified in the Supplementary Conditions. Except for such reliance on such
“technical data,” Contractor may not rely upon or make any claim against City, Design Professional or any of Design Professional's Consultants with respect to:
4.2.2.1. the completeness of such reports and drawings for Contractor's purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences and procedures of construction to be employed by
Contractor and safety precautions and programs incident thereto, or
4.2.2.2. other data, interpretations, opinions and information contained in such reports or shown or indicated in such drawings, or
4.2.2.3. any Contractor interpretation of or conclusion drawn from any
"technical data" or any such data, interpretations, opinions or information.
4.2.3. Notice of Differing Subsurface or Physical Conditions: If Contractor believes that any subsurface or physical condition at or contiguous to the site that is uncovered or revealed either:
4.2.3.1. is of such a nature as to establish that any “technical data” on which Contractor is entitled to rely as provided in paragraphs 4.2.1. and 4.2.2. is materially inaccurate, or
4.2.3.2. is of such a nature as to require a change in the Contract
Documents, or
4.2.3.3. differs materially from that shown or indicated in the Contract
Documents, or
4.2.3.4. is of an unusual nature, and differs materially from conditions ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents, then
Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency as permitted by paragraph 5.15.), notify City and Design Professional in writing about such condition. Contractor shall not further disturb such conditions or perform any
Work in connection therewith (except as aforesaid) until receipt of written order to do so.
4.2.4. Design Professional's Review: Design Professional will review the pertinent conditions, determine the necessity of City's obtaining additional exploration or tests with respect thereto and advise City in writing (with a copy to Contractor) of Design
Professional's findings and conclusions.
4.2.5. Possible Contract Documents Change: If the City concludes that a change in the Contract Documents is required as a result of a condition that meets one or more of the categories in paragraph 4.2.3, a Work Change Directive or a Change Order will be issued as provided in Article 10 to reflect and document the consequences of such change.
4.2.6. Possible Price and Times Adjustments: An equitable adjustment in the
Contract Price or in the Contract Term, or both, may be allowed to the extent that the existence of such uncovered or revealed condition causes an increase or decrease in
Contractor's cost of, or time required for performance of, the Work; subject, however, to the following:
4.2.6.1. such condition must meet any one or more of the categories described in paragraphs 4.2.3.1. through 4.2.3.4., inclusive;
4.2.6.2. a change in the Contract Documents pursuant to paragraph 4.2.5 will not be an automatic authorization of nor a condition precedent to entitlement to any such adjustment;
4.2.6.3 a change in the Contract Price, Contract Terms, or Period of
Performance must be approved by the City, and City Council if necessary, before work can proceed;
4.2.6.4. with respect to Work that is paid for on a Unit Price Basis, any adjustment in Contract Price will be subject to the provisions of paragraphs 8.8. and
10.9.; and
4.2.6.5. Contractor shall not be entitled to any adjustment in the Contract Price or Times if;
4.2.6.5.1. Contractor knew of the existence of such conditions at the time Contractor made a final commitment to City in respect of Contract
Price and Contract Term by the submission of a bid or becoming bound under a negotiated contract; or
4.2.6.5.2. the existence of such condition could reasonably have been discovered or revealed as a result of any examination, investigation, exploration, test or study of the site and contiguous areas required by the
Bidding Requirements or Contract Documents to be conducted by or for
Contractor prior to Contractor's making such final commitment; or
4.2.6.5.3. Contractor failed to give the written notice within the time and as required by paragraph 4.2.3.
4.3. Physical Conditions—Underground Facilities:
4.3.1. Shown or Indicated: The information and data shown or indicated in the Contract Documents with respect to existing Underground Facilities at or contiguous to the site is based on information and data furnished to City or Design Professional by the owners of such Underground Facilities or by others. Unless it is otherwise expressly provided in the Supplementary Conditions:
4.3.1.1. City and Design Professional shall not be responsible for the accuracy or completeness of any such information or data; and
4.3.1.2. The cost of all of the following will be included in the Contract
Price and Contractor shall have full responsibility for: (i) reviewing and checking all such information and data, (ii) locating all Underground Facilities shown or indicated in the Contract Documents, (iii) coordination of the Work with the owners of such Underground Facilities during construction, and (iv) the safety and protection of all such Underground Facilities as provided in paragraph 5.12. and repairing any damage thereto resulting from the Work.
4.3.2. Not Shown or Indicated: If an Underground Facility is uncovered or revealed at or contiguous to the site that was not shown or indicated in the Contract
Documents, Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith
(except in an emergency as required by paragraph 5.15.), identify the owner of such
Underground Facility and give written notice to that owner and to City and Design
Professional. Design Professional will promptly review the Underground Facility and determine the extent, if any, to which a change is required in the Contract Documents to reflect and document the consequences of the existence of the Underground Facility. If
Design Professional concludes that a change in the Contract Documents is required, a Work
Change Directive or a Change Order will be issued as provided in Article 9 to reflect and document such consequences. During such time, Contractor shall be responsible for the safety and protection of such Underground Facility as provided in paragraph 5.12.
Contractor may be allowed to request an increase in the Contract Price or an extension of the Contract Times, or both, to the extent that they are attributable to the existence of any
Underground Facility that was not shown or indicated in the Contract Documents and that
Contractor did not know of and could not reasonably have been expected to be aware of or to have anticipated. Contractor may make a claim therefor as provided in Articles 11 and
12. However, City, Design Professional and Design Professional's Consultants shall not be liable to Contractor for any claims, costs, losses or damages incurred or sustained by
Contractor on or in connection with any other project or anticipated project.
4.4. Reference Points: City shall provide engineering surveys to establish reference points for construction which in Design Professional's judgment are necessary to enable Contractor to proceed with the Work. Contractor shall be responsible for laying out the Work, shall protect and preserve the established reference points and shall make no changes or relocations without the prior written approval of City. Contractor shall report to Design Professional whenever any reference point is lost or destroyed or requires relocation because of necessary changes in grades or locations, and shall be responsible for the accurate replacement or relocation of such reference points by professionally qualified personnel.
4.5. Asbestos, PCBs, Petroleum, Hazardous Waste or Radioactive Material:
4.5.1. City shall be responsible for any Asbestos, PCBs, Petroleum, Hazardous
Waste or Radioactive Material uncovered or revealed at the site that was not shown or indicated in Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work and that may present a substantial danger to persons or property exposed thereto in connection with the Work at the site. City shall not be responsible for any such materials brought to the site by Contractor, Subcontractor, Suppliers or anyone else for whom Contractor is responsible.
4.5.2. Contractor shall immediately: (i) stop all Work in connection with such hazardous condition and in any area affected thereby (except in an emergency as required by paragraph 6.15.), and (ii) notify City and Design Professional (and thereafter confirm such notice in writing). City shall promptly consult with Design Professional concerning the necessity for City to retain a qualified expert to evaluate such hazardous condition or take corrective action, if any. Contractor shall not be required to resume Work in connection with such hazardous condition or in any such affected area until after City has obtained any required permits related thereto and delivered to Contractor special written notice: (i) specifying that such condition and any affected area is or has been rendered safe for the resumption of Work, or (ii) specifying any special conditions under which such
Work may be resumed safely. If City and Contractor cannot agree as to entitlement to or the amount or extent of an adjustment, if any, in Contract Price or Contract Term as a result of such Work stoppage or such special conditions under which Work is agreed by
Contractor to be resumed, either party may make a claim therefor as provided in Articles
10 and 11.
4.5.3. If after receipt of such special written notice Contractor does not agree to resume such Work based on a reasonable belief it is unsafe, or does not agree to resume such Work under such special conditions, then City may order such portion of the Work that is in connection with such hazardous condition or in such affected area to be deleted from the Work. If City and Contractor cannot agree as to entitlement to or the amount or extent of an adjustment, if any, in Contract Price or Contract Term as a result of deleting such portion of the Work, then either party may make a claim therefor as provided in
Articles 10 and 11. City may have such deleted portion of the Work performed by City's own forces or others in accordance with Article 7.
4.5.4. To the extent permitted by Colorado law, City shall indemnify and hold harmless Contractor, Subcontractors, Design Professional, Design Professional's
Consultants and the officers, directors, employees, agents, other consultants and
Subcontractors of each and any of them from and against all claims, costs, losses and damages arising out of or resulting from such hazardous condition, provided that: (i) any such claim, cost, loss or damage is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself), including the loss of use resulting therefrom, and (ii) such claim, cost, loss or damage is caused in whole or in part, or is claimed to be caused in whole or in part by the negligence or willful misconduct of City, its officers or employees. Nothing contained in the Contract
Documents shall constitute any waiver by City of any rights, immunities, and protections provided by the Colorado Governmental Immunity Act, C.R.S. § 24-10-101, et seq., as amended, or otherwise available to City, its officers, or its employees.
4.5.5. The provisions of paragraphs 4.2. and 4.3. are not intended to apply to
Asbestos, PCBs, Petroleum, Hazardous Waste or Radioactive Material uncovered or revealed at the site.
ARTICLE 5 - CONTRACTOR’S RESPONSIBILITIES
5.1. Supervision and Superintendence:
5.1.1. Contractor shall supervise, inspect and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Documents. Contractor shall be solely responsible for the means, methods, techniques, sequences and procedures of construction, but Contractor shall not be responsible for the negligence of others in the
Design or specification of a specific means, method, technique, sequence or procedure of construction that is shown or indicated in and expressly required by the Contract
Documents. Contractor shall be responsible to see that the completed Work complies accurately with the Contract Documents.
5.1.2. Contractor shall keep on the Work at all times during its progress a competent resident superintendent who is capable of verbal communications with City representatives, who shall not be replaced without written notice to City and Design
Professional except under extraordinary circumstances. The superintendent will be
Contractor’s representative at the site and shall have authority to act on behalf of
Contractor. All communications to the superintendent shall be as binding as if given to
Contractor.
5.2. Labor, Materials and Equipment:
5.2.1. Contractor shall provide competent, suitably qualified personnel to survey, lay out and construct the Work as required by the Contract Documents. Contractor shall at all times maintain good discipline and order at the site. Except as otherwise required for the safety or protection of persons or the Work or property at the site or adjacent thereto, and except as otherwise indicated in the Contract Documents, all Work at the site shall be performed during Regular Working Hours and Contractor will not permit overtime work or the performance of Work on Saturday, Sunday or any Official Holiday without City’s written consent given after prior written notice to Design Professional.
5.2.2. Unless otherwise specified in the Contract Documents, Contractor shall furnish and assume full responsibility for all materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities and all other facilities and incidentals necessary for the furnishing, performance, testing, start-up and completion of the Work.
5.2.3. All materials and equipment shall be of good quality and new, except as otherwise provided in the Contract Documents. All warranties and guarantees specifically called for by the Specifications shall expressly run to the benefit of City. If required by
Design Professional, Contractor shall furnish satisfactory evidence (including reports of required tests) as to the kind and quality of materials and equipment. All materials and equipment shall be applied, installed, connected, erected, used, cleaned and conditioned in accordance with instructions of the applicable Supplier, except as otherwise provided in the Contract Documents.
5.3. Progress Schedule; Updates and Proposed Adjustments: Contractor shall adhere to the progress schedule established as it may be adjusted from time to time as provided below:
5.3.1. With each Application for Payment submitted to Design Professional and the City (per Article 13 of these General Conditions), Contractor shall submit an updated progress schedule providing an updated schedule of progression of the Work remaining to completion of the Project as of the date of the Application for Payment.
5.3.2. Proposed adjustments in the progress schedule that will not change the
Contract Term (or Milestones) shall be reviewed by the City and Design Professional for acceptance.
5.3.3 Proposed adjustments in the progress schedule that will change the Contract
Term (or Milestones) shall be submitted in accordance with the requirements of paragraph
12.1. Such adjustments may only be made by a Change Order or Written Amendment in accordance with Article 11.
5.4. Substitutes and “Or-Equal” Items:
5.4.1. Whenever an item of material or equipment is specified or described in the
Contract Documents by using the name of a proprietary item or the name of a particular
Supplier, the specification or description is intended to establish the type, function and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent or “or-equal” item or no substitution is permitted, other items of material or equipment or material or equipment of other suppliers may be accepted by the City and Design Professional under the following circumstances:
5.4.1.1. “Or Equal”: If in the City and Design Professional’s discretion an item of material or equipment proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by the City and Design Professional as an “or-equal” item, in which case review and approval of the proposed item may, in the City and Design
Professional’s discretion, be accomplished without compliance with some or all of the requirements for acceptance of proposed substitute items.
5.4.1.2. Substitute Items: If in the City and Design Professional’s discretion an item of material or equipment proposed by Contractor does not qualify as an “or-equal” item under subparagraph 5.4.1.1., it will be considered a proposed substitute item. Contractor shall submit sufficient information as provided below to allow the City and Design Professional to determine that the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. The procedure for review by the City and Design Professional will include the following as supplemented in the Specifications and as the City and
Design Professional may decide is appropriate under the circumstances. Requests for review of proposed substitute items of material or equipment will not be accepted by the City and Design Professional from anyone other than Contractor.
If Contractor wished to furnish or use a substitute item of material or equipment, Contractor shall first make written application to the City and Design Professional for acceptance thereof, certifying that the proposed substitute will perform adequately the functions and achieve the results called for by the general Design, be similar in substance to that specified and be suited to the same use as that specified. The application will state the extent, if any, to which the evaluation and acceptance of the proposed substitute will prejudice Contractor’s achievement of
Substantial Completion on time, whether or not acceptance of the substitute for use in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with City for work on the Project) to adapt the Design to the proposed substitute and whether or not incorporation or use of the substitute in connection with the Work is subject to payment of any license fee or royalty. All variations of the proposed substitute from that specified will be identified in the application and available maintenance, repair and replacement service will be indicated. The application will also contain an itemized estimate of all costs or credits that will result directly or indirectly from acceptance of such substitute, including costs of redesign and claims of other Contractors affected by the resulting change, all of which will be considered by the City and Design
Professional in evaluating the proposed substitute. The City and Design
Professional may require Contractor to furnish additional data about the proposed substitute.
5.4.1.3. Contractor’s Expense: All data to be provided by Contractor in support of any proposed “or equal” or substitute item will be at Contractor’s expense.
5.4.2. Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence or procedure of construction is shown or indicated in and expressly required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, technique, sequence or procedure of construction acceptable to
Design Professional. Contractor shall submit sufficient information to allow the City and
Design Professional, in their discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. The procedure for review by the City and Design Professional will be similar to that provided in subparagraph 5.4.1.2.
5.4.3 Design Professional’s Evaluation: Design Professional will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to paragraphs 5.4.1.2. and 5.4.2. Design Professional and City will judge acceptability. No
“or-equal” or substitute will be ordered, installed, or utilized without Design Professional’s and City’s prior written acceptance which will be evidenced by either a Change Order or an approved Shop Drawing. City may require Contractor to furnish, at Contractor’s expense, a special performance guarantee or other surety with respect to any “or-equal” or substitute. Design Professional will record time required by Design Professional and
Design Professional’s Consultants in evaluating substitutes proposed…