This is a Bid Tab document for the City of Brighton, Colorado, detailing the 18th Avenue Sanitary Sewer Rerouting Construction project. The bid schedule outlines 22 line items for construction work, including traffic control, mobilization, erosion control, pavement removal and replacement, sanitary line installation, manhole construction, and restoration activities. The project involves constructing sanitary sewer collection system improvements along South 18th Avenue, with specific quantities including 537 linear feet of 8" PVC sanitary line, 4 sanitary manholes, and various surface restoration elements. A contingency line item of $45,000 is included for minor contract revisions.
The bid tab shows unit pricing for each construction activity, with a total project scope focused on infrastructure replacement and improvement. While specific unit prices are not filled in, the document provides a comprehensive breakdown of expected work activities and quantities. The contingency amount of $45,000 suggests the city is preparing for potential unexpected project modifications. The bid appears to be a competitive solicitation for comprehensive sanitary sewer infrastructure work, with detailed specifications for pavement, sidewalk, and utility system modifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
25-009037
| INVITATION TO BID | |||||
| 25-009037 | |||||
| 18th Ave Sanitary Sewer Rerouting Construction | |||||
| FEE SCHEDULE | |||||
| Item No. | Description | Quantity | UOM | Unit Price | Total Price |
| 1 | Traffic Control | 1 | LS | $ - 0 | |
| 2 | Mobilization | 1 | LS | $ - 0 | |
| 3 | Erosion and Sediment Control | 1 | LS | $ - 0 | |
| 4 | Sawcut & Remove Existing Asphalt Pavement (Full Depth) | 356 | SY | $ - 0 | |
| 5 | Mill Existing Asphalt Pavement (2") | 622 | SY | $ - 0 | |
| 6 | Sawcut & Remove Existing Concrete Sidewalk | 50 | SF | $ - 0 | |
| 7 | Sawcut & Remove Existing Curb & Gutter | 10 | LF | $ - 0 | |
| 8 | Remove Existing Sanitary Line | 65 | LF | $ - 0 | |
| 9 | Abandon Existing Sanitary Line in Place | 20 | LF | $ - 0 | |
| 10 | 8" PVC (SDR 35) Sanitary Line including Trenching & Backfill | 537 | LF | $ - 0 | |
| 11 | 48" Dia. Sanitary Manhole | 4 | EA | $ - 0 | |
| 12 | Connect to Existing Sanitary Manhole | 1 | LS | $ - 0 | |
| 13 | Plug Existing Manhole | 1 | LS | $ - 0 | |
| 14 | Pavement Replacement (6" AC on 8" AB) | 356 | SY | $ - 0 | |
| 15 | Overlay Asphalt Pavement (2") | 622 | SY | $ - 0 | |
| 16 | Miscellaneous Restriping | 1 | LS | $ - 0 | |
| 17 | Concrete Sidewalk Replacement | 50 | SF | $ - 0 | |
| 18 | Curb & Gutter Replacement | 10 | LF | $ - 0 | |
| 19 | Landscaping Restoration | 300 | SF | $ - 0 | |
| 20 | Testing and Camera | 1 | LS | $ - 0 | |
| 21 | Surveying (Construction and Asbuilts) | 1 | LS | $ - 0 | |
| 22 | Minor Contract Revisions/Contingency | 1 | F/A | $ 45,000.00 | $ 45,000.00 |
| TOTAL PRICE | $ - 0 |