Amendment_1_Attachment_V_Solicitation_70Z02318QPD500100_Q_&_A_V1.doc
DOC document 24 KB Posted
- Attached to
- Two 12'x56' Trailers for Temporary Usage
- Solicitation number
- 070Z2318QPD500100
About this file
Response to Questions
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_1_Attachment_I_Statement_of_Work_(v3).docx | DOCX document | |
| Amendment_1_Attachment_IV_Solicitation_Provisions_(v3).docx | DOCX document | |
| Amendment_1_Summary_of_Changes_70Z02318QPD500100_(v2).pdf | ||
| Amendment_1_Attachment_II_Pricing_Schedule_v2.xlsx | XLSX spreadsheet | |
| 5_Attachment_II_Pricing_Schedule.xlsx | XLSX spreadsheet | |
| 6_Attachment_III_Clauses.docx | DOCX document | |
| 4_Attachment_IB_Instalation_location_USCG_Yard_Map_1.jpg | JPG image | |
| 7_Attachment_IV_Solicitation_Provisions_(v2).docx | DOCX document | |
| 3_Attachment_IA_design.docx | DOCX document | |
| 2_Attachment_I_Statement_of_Work_(v2).docx | DOCX document | |
| 1_Cover_Letter_70Z02318QPD500100_v3.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ 70Z02318QPD500100
Amendment 1
Solicitation 70Z02318QPD500100 Trailers for CG Yard
Responses to Questions (Q&A)
1) What type of plug outlet are we plugging in to?
The trailer's electric will be supplied via a hard-wired cable--no plugs involved. My understanding is last time they setup a dedicated transformer, then a main breaker, then wired directly to the trailer's power panel. The Contractor will be required to provide the required length/gauge of cable.
2) Since we're providing buildings with restrooms, are we also to provide portable holding tanks or can we just tie in to the waste system on site? If we're tying into the onsite system, how long is the hookup from the building location.
The holding tanks should be supplied and serviced by the vendor. We cannot tie into yard sewage.
3) Will you accept one restroom lieu of two?
Yes – The statement of work has been updated to reflect that we will accept one restroom as a minimum requirement.
4) Will you accept two offices one on each end?
Yes, please provide a floor plan.
5) Will you accept the electrical service panel 240 volt, 100 amp, single phase power for each building?
Yes
6) How long will you need the trailers?
One trailer will be needed from 22JAN18 – 30AUG18 (7 Months)
Second trailer will be needed from 22JAN18 – 30APR18 (3 Months)