0016067 Special Provision 108_08.pdf
PDF 97 KB Posted
- Solicitation number
- PE-66780-NONST-2026-000000043
- Issued by
- Gwinnett County, Georgia
About this file
This is a Special Provision document issued by the Georgia Department of Transportation for Gwinnett County Project Number 0016067, relating to the City of Norcross Greenway - LCI Shared Use Path Enhancement project. The project encompasses approximately 3.3 miles of shared-use pathway with a combination of on-street and off-street segments, including roadway improvements along Mitchell Road, Pinnacle Way, and Price Place, along with undeveloped sections featuring two bridges and boardwalk components extending from Mitchell Road to the existing Pinnacle Park Shared-Use Path. The contract is governed by the Georgia Department of Transportation Standard Specifications for Construction of Transportation Systems, 2021 Edition, along with applicable special provisions and supplemental specifications. Construction must comply with all referenced Georgia Standards.
The Special Provision establishes specific performance requirements and associated liquidated damages penalties for various construction activities. Failure to reopen travel lanes as specified results in damages of $1,000 per hour or portion thereof. Milled surfaces must be covered within one day or incur $1,000 daily penalties. Right-of-way and limited access fencing is restricted to no more than 0.5 miles down at any given time, with livestock security requirements within 1,000 feet of interchanges and seven calendar days for completion elsewhere, assessed at $1,000 per day for non-compliance. Logo signs removed during grading must be remounted within five calendar days at their permanent location or temporarily placed in an Engineer-approved location, with penalties of $500 per calendar day per sign for non-compliance. All penalty rates are cumulative and apply in addition to any other liquidated damages assessed for overall project completion delays.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
May 29, 2025
DEPARTMENT OF TRANSPORTATION
STATE OF GEORGIA
SPECIAL PROVISION
PROJECT NUMBER: N/A
GWINNETT COUNTY
P.I. No.: 0016067
SECTION 108 - PROSECUTION AND PROGRESS
Retain Sub-Section 108.08 as written and add the following:
108.08. Failure or Delay in Completing Work on Time
C: Restrictive Work Hours
1. Failure to re-open travel lanes as specified in Special Provision Section 150.6.A will result in the assessment of liquidated damages in the amount of $1,000.00 per hour or portion thereof.
D: Milled Surfaces
Failure to cover milled surfaces as specified in Special Provision Section 150.6 will result in the assessment of liquidated damages in the amount of $1,000.00 per day.
E: Fencing
Right of way or Limited Access fencing along the mainline proposed to be replaced during construction shall comply with the following restrictions:
1. No more than 0.5 miles of fence may be down at any given time.
2. Fence construction shall proceed in a manner that will prevent the escape of livestock.
3. Fence removal and new fence installation shall be scheduled so as to provide continuous security to livestock, residential areas, businesses, frontage road areas and within 1,000 feet of interchanges.
4. All other areas shall have fence replaced within seven (7) calendar days.
Failure to complete the replacement of Right of Way or Limited Access fence as specified shall result in the assessment of Liquidated Damages in the amount of $1,000.00 per calendar day. Removal of more than 0.5 miles of fence at any given time and failure to provide security to the areas noted above, shall result in the assessment of Liquidated Damages in the amount of $1,000.00 per calendar day.
F: Logo Signs
Logo signs along the mainline that will have to removed and remounted during grading shall have intermediate completion times. Each Logo sign shall not remain down for more than five (5) calendar days before being remounted to its permanent location. Once the Logo signs are remounted at their permanent locations, they shall not be removed again. If the Contractor is unable to remount Logo signs at their permanent locations within five (5) calendar days, he may elect to temporarily set the Logo signs in a location approved by the Engineer at no additional cost. If the Logo signs are temporarily set, they may remain so until such time that the construction in the area will allow for the Logo signs to be placed in their permanent location.
The Logo signs shall be placed in their permanent location per Georgia Standards 9054A, 9054B, and 9054C.
Failure to complete the removal and remounting of each Logo sign as specified shall result in the assessment of Liquidated Damages in the amount of $500 per calendar day, per Logo sign.
The above rates are cumulative and are in addition to any Liquidated Damages which may be assessed for failure to complete the overall project.
(City of Norcross)