00010023 Exhibit 1 Specifications.pdf
PDF 473 KB Posted
- Attached to
- ESB US101 MP 51. 84 Culvert Replacement Project
- Solicitation number
- S-73000-00010023
- Issued by
- Tillamook County, Oregon
About this file
This document contains specifications for the ESB US101 MP 51.84 Culvert Replacement Project in Marion County, Oregon. The project, managed by the Oregon Department of Transportation (ODOT), involves removing an existing 12-inch concrete culvert and installing a new 18-inch HDPE culvert along US101 in Rockaway Beach. The work includes providing traffic control, temporary water management, erosion and sediment control, and other related tasks as described in the technical specifications. The project must be completed during the in-water work window of July 1 to September 15. ODOT is seeking a single ESB-certified contractor to perform the work.
The contract will be awarded as a lump sum, and payment will cover furnishing all materials, equipment, labor, and incidentals necessary to complete the work. Contractors must submit a Temporary Water Management Plan and Traffic Control Plan for approval prior to beginning work. This project is funded by the state and no set-aside requirements are mentioned. ODOT will be responsible for trench repair paving and striping after the culvert installation is complete.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00010023 RFCQ_Attachments_US101 Culvert.pdf | ||
| 00010023 Preliminary Bid Results.xlsx | XLSX spreadsheet | |
| Attachment B - REVISED Bid Pricing Form.xlsx | XLSX spreadsheet | |
| 00010023 Exhibit 2 Standard Drawings~1.pdf | ||
| 00010023 RFCQ_US101 Culvert.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
i
Exhibit 1 - SPECIFICATIONS
ESB US101 MP 51.84 Culvert Replacement Project
1. SILENCE OF SPECIFICATIONS: The apparent silence of the specifications as to any detail, or the apparent omission of a detailed description concerning any point, shall be regarded as meaning that only the best commercial practice is to prevail and that only materials and workmanship of first quality are to be used.
2. PROJECT MANAGER:
Daniel Weber Transportation Operations and Maintenance Manger 308 Evergreen Dr
Tillamook OR 97141 Cell: 503-801-0066
Daniel.A.WEBER@odot.oregon.gov
3. SCOPE OF WORK
The work to be done under this Contract, on US101 (Oregon Coast Highway) consists of supplying the materials, equipment, labor and incidentals required to perform the following tasks as described below and in the Contract specifications:
• Provide Work Zone Traffic Control at the work location from the Oregon Temporary Traffic Control Handbook (OTTCH 2011)
• Remove the existing 12” CONC pipe, 58’ length, 5.5’ depth.
• Install a new 18” HDPE pipe at the same grade and skew. (Grade may be minorly adjusted in the field as directed. Possibly raised max of 6” to improve flow)
• Construction means and methods are up to the contractor, but it is anticipated that the work will be completed in half sections over two nights.
• Utilities are expected to be in the area. The Contractor should contact 811 and plan work accordingly.
• In late summer this crossing carries no flow but may still contain damp soils. In the event there is water present, bid item 3 is included as a contingency item to pay for some sump pumps in the even they’re needed.
• The project must be completed in the dry and during the In Water Work Window of July 1 – September 15.
• Meet with the Agency Biologist, Resource Representative, Engineer, and inspector on site, before moving equipment on-site or beginning any work, to ensure that all parties understand the locations of sensitive biological sites and the measures that are required to be taken to protect them.
• Pipe installation is expected to follow standard drawing RD300 for pipe excavation and backfill. Trench backfill to be Class “B” and extend flush to wearing surface grade. The Agency will perform trench repair paving and striping.
• Perform additional and incidental work as called for by the Contract plans and specifications and as directed.
mailto:Daniel.A.WEBER@odot.oregon.gov ii
The locations are as follows:
• US101 at mile point 51.84, just north of S. Minnehaha St. in south Rockaway Beach
4. APPLICABLE STANDARD SPECIFICATIONS AND SPECIAL PROVISIONS
2024 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION: The 2024 Oregon Standard Specifications for Construction (“Standard Specifications”) include detailed technical specifications in Parts 00200 through 03000 inclusive (“Technical Specifications”) that apply to this ITB and the resulting Contract. Some sections of the Technical Specifications are identified and modified in the Special Provisions below. Sections of the Technical Specifications not modified by the Special Provisions or Plans remain applicable to this ITB and resulting Contract according to their original terms. Unless they are identified herein, Specifications, sections of the Standard Specifications in Part 00100 (General Conditions) are not applicable to this ITB and resulting Contract. However, if a section in Part 00100 that has been identified as being applicable references another section in Part 00100, or if a Technical Specification references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the specification that referenced it. The Standard Specifications are available online at:
https://www.oregon.gov/odot/Business/Specs/2024_STANDARD_SPECIFICATIONS.pdf https://www.oregon.gov/odot/Business/Specs/2024_STANDARD_SPECIFICATIONS.pdf iii
PROFESSIONAL OF RECORD CERTIFICATION
The following special provisions were prepared and/or reviewed by the Engineer whose professional seal appears below. These specifications are not valid unless the appropriate signed seal appears below and shall not be modified without the approval of the Engineer.
OREGON DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISIONS
FOR
PROFESSIONAL OF RECORD CERTIFICATION(s):
Seal w/signature
I certify the Special Provision Section(s) listed below are applicable to the design for the subject project.
Modified Special Provisions were prepared by me or under my supervision.
SECTIONS: 00210, 00220, 00221, 00222,
00245, 00280, 00290, 00310, 00445, 00640
Date Signed: 3/13/2024
6/30/2024 iv
TABLE OF CONTENTS FOR SPECIAL PROVISIONS
SECTION 00210 – MOBILIZATION
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL
SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS
SECTION 00245 - TEMPORARY WATER MANAGEMENT
SECTION 00280 - EROSION AND SEDIMENT CONTROL
SECTION 00290 - ENVIRONMENTAL PROTECTION
SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS
SECTION 00445 - SANITARY, STORM, CULVERT, SIPHON, AND IRRIGATION PIPE
SECTION 00640 - AGGREGATE BASE AND SHOULDERS
SECTION 00210 – MOBILIZATION
Comply with Section 00210 of the Standard Specifications.
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
Comply with Section 00220 of the Standard Specifications modified as follows:
00220.02(a) General Requirements - Add the following bullets to the end of the bullet list:
• When performing trench excavation or other excavation across or adjacent to a Traffic Lane on a Roadway, backfill the excavation with aggregate base to adjacent grade, and open the Roadway to traffic by the end of each work shift. Install a "BUMP" (W8-1-48) sign approximately 100 feet before the backfilled area and a "ROUGH ROAD" (W8-8-48) sign approximately 500 feet ahead of the "BUMP" sign. If this requirement is not met, maintain all necessary lane or shoulder closures and provide additional TCM, including flagging, at no additional cost to the Agency. Do not use temporary steel plating to reopen the Roadway.
00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:
Traffic Lanes may be closed on the Oregon Coast Highway US101 when allowed, shown, or directed during the following periods of time:
Single Lane Closures – One Traffic Lane on the Oregon Coast Highway US101 may be closed during the following times:
• Nightly, Sunday night through Friday morning, between 6 p.m. and 7 a.m.
SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL
Comply with Section 00221 of the Standard Specifications modified as follows:
00221.06 Traffic Control Plan - Replace this subsection with the following subsection:
00221.06 Traffic Control Plan and Tourist-Oriented Directional and Business Logo Signs –
(a) Traffic Control Plan - Submit one of the following, 5 Calendar Days before the preconstruction conference:
(1) Agency Traffic Control Plan - If the Contractor intends to use the Agency TCP without modification, a written notification indicating that the Agency TCP will be used without modification.
(2) Contractor-Modified Traffic Control Plan - The Contractor may request to use a Contractor-modified Agency TCP, or a TCP developed by the Contractor. Do not use a modified TCP, or a TCP developed by the Contractor, unless approved by the Engineer. Use the Agency TCP unless a modified TCP, or a TCP developed by the Contractor is accepted.
The Engineer is not obligated to consider any modified Agency TCP or a TCP developed by the Contractor.
The Agency will not be liable to the Contractor for failure to accept or act upon any request for a modified Agency TCP or a TCP developed by the Contractor.
To conserve time and funds, the Contractor may first submit a written request for a preliminary review by the Engineer. The request should contain a description of the proposal together with a rough estimate of anticipated dollar and time impacts. The Engineer will, within a reasonable time, respond to the Contractor in writing whether or not the request would be considered by the Agency.
If requesting a Contractor-modified Agency TCP, or a TCP developed by the Contractor, at a minimum the request shall meet all requirements of the Contract documents and comply with the Project transportation management plan (TMP). Provide the following information:
• Stamped Working Drawings according to 00150.35 that include the proposed TCP showing all TCM and quantities of TCD.
• A TPAR plan that includes:
• Details and features used to provide pedestrian accessibility.
• Pedestrian staging Plans at a scale no smaller than 1 inch = 50 feet.
• Temporary alternate facilities or detour routes for pedestrian traffic.
• Staging sequences and details for Work affecting vehicular, pedestrian, and bicycle traffic.
• Proposed order and duration of the TCM.
• A detailed temporary striping plan.
If the Contractor’s request to use a Contractor-modified Agency TCP, or a TCP developed by the Contractor is approved in whole or in part, acceptance will be made by a Change Order.
The Engineer will establish prices that represent a fair measure of the value of Work to be added, changed, or deleted as a result of any accepted modifications to the Agency TCP or an accepted TCP developed by the Contractor.
Once a TCP has been accepted by the Engineer, any additional modifications must be submitted by the Contractor for Agency review following the procedure described above. The Engineer is not obligated to consider additional modifications to a previously approved TCP.
(b) Tourist-Oriented Directional and Business Logo Signs - Submit one of the following for approval, at least 5 Calendar Days before the preconstruction conference:
(1) No Signs - If there are no tourist-oriented directional (TOD) or business logo signs on the Project, a written notification that no TOD or business logo signs exist within the Project limits or
(2) Signs - Submit one copy of a sketch map of the Project showing all existing TOD and business logo signs and a written narrative describing how these signs will be kept in service and protected throughout all the construction stages. If modifications are necessary, submit updated information to the Engineer for approval at least 21 Calendar Days before the change is needed.
SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS
Comply with Section 00222 of the Standard Specifications modified as follows:
00222.45(b) Portable Changeable Message Signs - Add the following bullets to the end of this subsection:
• At least seven Calendar Days before the highway closure, place one PCMS in each traffic direction (north and south bound) displaying the following message as shown, or as directed:
Panel 1 Panel 2 Panel 3
NIGHT US101 AT CLOSURE
WORK MINNE ST (Time Frame) CLOSURE (Time Frame)
SECTION 00245 - TEMPORARY WATER MANAGEMENT
Section 00245, which is not a Standard Specification, is included in this Project by Special Provision.
Description
00245.00 Scope - This Work consists of furnishing, installing, operating, maintaining, and removing temporary water management facilities in regulated Work areas.
00245.01 Abbreviations:
TWM - Temporary Water Management TWMF - Temporary Water Management Facility TWMP - Temporary Water Management Plan
00245.02 Definitions:
Temporary Water Management Facility - A TWMF that conveys water around or through Work areas, removes water from Work areas, and treats and discharges water at locations outside Work areas.
00245.03 Temporary Water Management Plan - The Agency TWMP is a concept plan. 28 Calendar Days before beginning Work in regulated Work areas, submit stamped Working Drawings of a Contractor-developed TWMP, according to 00150.35, based on either the Agency’s concept plan or an independent plan that meets water quality and environmental guideline requirements and does not negatively affect neighboring properties or water rights.
Include the following minimum information in the TWMP:
• The sequence and schedule for dewatering and re-watering. This sequence and schedule must include when to contact the Engineer prior to dewatering and re-watering.
• How the Work area is isolated from the active stream flow upstream, through, and downstream.
• How the stream flow is routed and conveyed around or through the isolated Work area.
• How fish passage is provided around the Work area, if required.
• How the isolated Work area is de-watered.
• How the pumped water is treated, if necessary, before it is discharged downstream.
• Description of all construction stages, including appropriate contact points for each stage.
• A list of on-site backup Materials and Equipment.
• Provide the name of the TWM Subcontractor (if applicable) and Contractor’s superintendent, and their
24-hour contact phone number 10 Days before the pre-Work meeting. If changes in the appointment of the TWM Subcontractor or Contractor’s superintendent occur during the term of the Contract, provide written notice to the Engineer within 5 Calendar Days of the change.
• Calculations of water withdraw pump’s capacity.
• Details of the proposed water intake screen used to isolate in-water Work area and how it meets the requirements of 00290.34(c)(3).
Any change to the TWMP during construction requires approval prior to implementation.
Obtain the Engineer's written approval before beginning Work in in-water Work areas.
00245.04 Pre-Work Meeting - Before beginning any TWM Work, attend a pre-work meeting at the Project Site with the Engineer no more than 8 Calendar Days prior to implementation of TWM. Required meeting attendees include:
• Engineer
• Contractor
• TWM Subcontractor (if applicable)
• Agency Environmental Coordinator or their appointed representative
The pre-Work meeting agenda typically includes the method of TWM, the TWMP, fish salvage plan and strategy, describe environmental risks, turbidity monitoring, energy dissipation, dewatering and re-watering plan and strategy, site clean-up expectations, and the circumstances under which contacting the Engineer is required.
Materials
00245.10 Materials - Furnish Materials meeting the following requirements:
Pipe ........................................................................ 00445.11 Plastic Sheeting .................................................. 00280.14(a) Sandbags ............................................................ 00280.15(a) Water Intake Screening ..................................... 00290.34(c)
Furnish pumps that are:
• Self-priming.
• Equipped with a variable speed governor.
• Equipped with a power source.
• Able to pump water that contains soft and hard solid.
Construction
00245.40 Fish Removal - Qualified Agency, ODFW, or ODOT consultant biologists will remove fish and other aquatic organisms from the isolation Work areas. Coordinate fish removal with the Engineer at least 28 Calendar Days before beginning Work in regulated Work areas. Allow access into the isolation Work areas before, during and after installation of the TWMF to perform the specified tasks as follows:
• Before Installation of TWMF - Before any in-water Work, including installing TWMF, qualified personnel will remove fish and other native aquatic organisms from within the proposed isolated Work area.
• After Installation of TWMF - After installing TWMF and the reduction of the water level through the isolated Work area has begun, qualified personnel will remove all fish and aquatic organisms as the water level is reduced. Do not completely de-water the isolation area until all fish and aquatic organisms have been removed.
00245.41 Installation - During installation of the temporary water management facility, maintain a downstream water flow rate of at least 50 percent of the upstream water flow rate.
00245.42 Operation - Operate temporary water management as follows:
• Protect fish and fish habitat according to 00290.34.
• Maintain and control water flow downstream of the isolated Work area for the duration of the diversion to prevent downstream de-watering.
• Clean, maintain and repair water intake screening to ensure adequate flows and protection of aquatic organisms.
• In the event of containment failure immediately notify the Engineer so arrangements can be made to remove fish and aquatic organisms from the isolation Work areas prior to the continuation of Work within the ordinary high water limits.
• When using a pump for bypassing water during temporary water management, physically monitor the pump in-person and maintain the pump at all times including non-work hours. Provide a back-up pump on-site and ready for use as necessary. Provide the Engineer with a daily report documenting monitoring activities.
Maintenance
00245.60 Maintenance - Monitor water turbidity according to 00290.30(a)(8).
Finishing and Cleaning Up
00245.70 Removal - Prior to removal of the TWMF, obtain approval from the Engineer after completion of all Work within ordinary high water limits. Remove the TWMF and re-water and restore the stream flow.
Maintain downstream water flow during removal of the facility. Staged or metered re-watering may be required and will be determined by the Engineer.
Measurement
00245.80 Measurement - No measurement of quantities will be made for temporary water management facilities.
Turbidity monitoring will be measured according to 00290.80.
Payment
00245.90 Payment - The accepted quantities of temporary water management facilities will be paid for at the Contract lump sum amount for the item "Temporary Water Management Facility".
The location of the facility will be inserted in the blank.
Payment will be payment in full for furnishing and placing all Materials, and for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.
Turbidity monitoring will be paid for according to 00290.90.
No separate or additional payment will be made for TWMP, maintaining, operating, monitoring, moving, or removing the facility.
SECTION 00280 - EROSION AND SEDIMENT CONTROL
Comply with Section 00280 of the Standard Specifications modified as follows:
00280.00 Scope - Replace the paragraph that begins "This Work also consists of providing temporary …" with the following paragraph:
This Work also consists of providing temporary erosion and sediment control (ESC) measures and furnishing, installing, moving, operating, maintaining, inspecting, and removing ESC throughout the Project area according to the Standard Drawings, the erosion and sediment control plan (ESCP), the Specifications, or as directed, until the site is permanently stabilized. Included also is the monitoring of weather, of stormwater and receiving waters, the reporting of monitoring observations, the reporting of corrective actions (when necessary) and the updates and revisions of the ESCP, including ESCP cover sheet, necessary to keep it representative of current site conditions and compliant with the 1200-CA permit if applicable.
Delete the paragraph that begins “When contaminants, pollutants or hazardous materials…”.
Add the following paragraph to the end of this subsection:
The Agency’s NPDES 1200-CA permit is not applicable to this Project. Comply with all applicable conditions of this Section.
00280.04 Erosion and Sediment Control Plan on Agency Controlled Lands - Replace the bullet that begins “Information required under 1200-CA…” with the following bullet:
• Information required under 1200-CA permit, if applicable.
00280.06 Erosion and Sediment Control Manager - Delete this subsection.
00280.16(k) Active Treatment System – Add the following sentence to the end of this subsection:
Obtain approval of the active treatment system from DEQ prior to use.
00280.41(f) Hauling Material – Replace this subsection, except for the subsection number and title, with the following:
Cover loads carrying soil or sediment which may generate dust. Haul saturated loads in watertight beds or drain saturated loads prior to leaving the Project Site.
00280.41(g) Underground Injection Controls (UIC) – Replace this subsection, except for the subsection number and title, with the following:
Do not allow storm water from work area to enter Underground Injection Control (UIC) inlets, UIC catch basins or UIC wells.
00280.62 Inspecting and Monitoring – Delete the paragraph that begins “Inspect the Project Site…”.
00280.62(a) Inspection - Replace the paragraph that begins "Perform site inspection, complete…" with the following paragraph:
Inspect the Project Site and all ESC devices for Effective Function and potential erosion or sediment movement and complete all applicable parts of the ODOT Erosion Control Monitoring Form, and submit the form to the Agency as follows:
00280.64(a) Corrective Action Timelines – Delete the bullet that begins “If completion of corrective action is not feasible…”
Delete the bullet that begins “Provide a schedule for clean-up and corrective actions…”
Delete the bullet that begins “Provide all corrective action documentation and photographs…”
SECTION 00290 - ENVIRONMENTAL PROTECTION
Comply with Section 00290 of the Standard Specifications modified as follows:
Add the following subsection:
00290.30(a)(7) Water Quality:
• Do not discharge contaminated or sediment-laden water, including drilling fluids and waste, or water contained within a work area isolation, directly into any waters of the State or U.S. until it has been satisfactorily treated (using a best management practice such as a filter, settlement pond, bio-bag, dirt-bag, or pumping to a vegetated upland location).
• Do not use permanent stormwater quality treatment facilities to treat construction runoff unless prescribed by an ESCP approved under Section 00280.
• If construction discharge water is released using an outfall or diffuser port, do not exceed velocities more than 4 feet per second, and do not exceed an aperture size of 1 inch.
• Do not use explosives under water.
• Implement containment measures adequate to prevent pollutants or construction and demolition materials, such as waste spoils, fuel or petroleum products, concrete cure water, silt, welding slag and grindings, concrete sawcutting by-products and sandblasting abrasives, from entering waters of the State or U.S.
• Implement containment measures adequate to prevent flowing stream water from coming into contact with concrete or grout within the first 24 hours after placement.
• Do not end-dump riprap into the waters of the State or U.S. Place riprap from above the ordinary high water line.
• Cease Project operations under high flow conditions that may result in inundation of the Project area, except for efforts to avoid or minimize resource damage.
• The Engineer retains the authority to temporarily halt or modify the Work in case of excessive turbidity or damage to natural resources.
• If Work activities violate permit conditions or any requirement of this subsection, stop all in-water work activities and notify the Engineer.
• Do not cause a visible sediment plume in waters of the State or U.S.
00290.34 Protection of Fish and Fish Habitat - Add the following paragraph:
Meet with the Agency Biologist, Resource Representative, Engineer, and inspector on site, before moving equipment on-site or beginning any work, to ensure that all parties understand the locations of sensitive biological sites and the measures that are required to be taken to protect them.
00290.34(a) Regulated Work Areas - Add the following to the end of this subsection:
The regulated work area is defined as the area at or below the ordinary high water (OHW) elevation. The Engineer will identify and mark the regulated work area.
Perform work within the regulated work area only during the in-water work period. The in-water work period is from July 1 to September 15.
00290.34(c) Aquatic Species Protection Measures Required by Environmental Permits:
(1) General Requirements:
• Do not install fish ladders (for example: pool and weirs, vertical slots, fishways) or fish trapping systems.
• Do not apply surface fertilizer within 50 feet of any stream channel.
Use heavy equipment as follows:
• Choice of equipment must have the least adverse effects on the environment (for example: minimally sized, low ground pressure).
• Secure absorbent material around all stationary power equipment (for example: generators, cranes, drilling equipment) operated within 150 feet of wetlands, waters of the State, waters of the U. S., drainage ditches, or water quality facilities to prevent leaks, unless suitable containment is provided to prevent spills from entering waters of the State or waters of the U.S.
• Do not cross directly through a stream for construction access, unless shown or approved. If shown or approved, cross perpendicular to the stream and do not block stream flow. When a crossing is no longer needed, completely remove the crossing and restore the soils and vegetation to the original condition.
• Store fuel and maintain all equipment in staging areas that are at least 150 feet away from any waters of the State, waters of the U.S., or storm inlet or on an impervious surface that is isolated from any waters of the State, waters of the U.S., or storm inlet.
• If temporary access roads are needed within 150 feet of any body of water, use existing routes unless new routes are shown or approved.
• Before beginning work on temporary access routes that are not shown, submit a proposal to the Engineer for approval.
(2) Work Area Isolation - Provide work isolation according to Section 00245. Provide safe passage around or through the isolated work area for adult and juvenile migratory fish unless passage did not previously exist.
(3) Water Intake Screening - Install, operate, and maintain fish screens on each water intake used for project construction, including pumps used to isolate an in-water work area. When drawing or pumping water from any stream, protect fish by equipping intakes with screens having a minimum 27 percent open area and meeting the following requirements:
• Perforated plate openings shall be 3/32 inch or smaller.
• Mesh or woven wire screen openings shall be 3/32 inch or smaller in the narrowest direction.
• Profile bar screen or wedge wire openings shall be 1/16 inch or smaller in the narrow direction.
Choose size and position of screens to meet the following criteria in Table 00290-1:
Table 00290-1
Type Approach Velocity 1 (Ft./Sec.)
Sweeping Velocity 2 (Ft./Sec.)
Wetted Area of Screen (Sq. Ft.)
Comments
Ditch Screen ≤ 0.4 Shall exceed approach velocity
Divide max.
water flow rate (cfs) by
0.4 fps
If screen is longer than 4 feet, angle 45° or less to stream flow
Screen with proven self-cleaning system
≤ 0.4 –
Divide max.
water flow rate (cfs) by
0.4 fps
Screen with no cleaning system other than manual
≤ 0.2 –
Divide max.
water flow rate (cfs) by
0.2 fps
Pump rate 1 cfs or less
1 Velocity perpendicular to screen face at a distance of approximately 3 inches 2 Velocity parallel to screen
Provide ditch screens with a bypass system to transport fish safely and rapidly back to the stream.
(9) Treated Wood - Treated wood includes any wood treated with any pesticide or wood preservatives. Do not use lumber, pilings, or other wood products that are treated or preserved with pesticidal compounds below the ordinary high water (OHW) or as part of an in-water or over-water structure, except as described below:
• Store treated wood shipped to the Project out of contact with standing water and wet soil, and protected from precipitation.
• Visually inspect each load and piece of treated wood. Reject for use in or above aquatic environments if visible residues, bleeding of preservative, preservative-saturated sawdust, contaminated soil, or other matter is present.
• Use pre-fabrication to the extent feasible. When field fabrication is necessary, all cutting and drilling of treated wood, and field preservative treatment of wood exposed by cutting and drilling, shall occur above the OHW. Use tarps, plastic tubs, or similar devices to contain the bulk of any fabrication debris, and wipe off any excess field preservative.
• All treated wood structures, including pilings, shall have design features to avoid or minimize impacts and abrasion by livestock, pedestrians, vehicles, vessels, and floats.
• Treated wood may be used to construct a bridge, over-water structure or an in-water structure, with the exception of the work containment system, provided that all surfaces exposed to leaching by precipitation, overtopping waves, or submersion are coated with a water-proof seal or barrier are maintained. Apply and contain coatings and paint-on field treatment to prevent contamination.
Surfaces that are not exposed to precipitation or wave attack, such as parts of a timber bridge completely covered by the bridge deck, are exempt from this requirement.
• During demolition of treated wood, ensure that no treated wood debris falls into the water. If treated wood debris does fall into the water, remove it immediately.
• Store removed treated wood debris in appropriate dry storage areas, at least 150 feet away from the regulated work area.
SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS
Comply with Section 00310 of the Standard Specifications.
SECTION 00445 - SANITARY, STORM, CULVERT, SIPHON, AND IRRIGATION PIPE
Comply with Section 00445 of the Standard Specifications.
SECTION 00640 - AGGREGATE BASE AND SHOULDERS
Comply with Section 00640 of the Standard Specification
| SECTION 00210 – MOBILIZATION |
| SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC |
| SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL |
| SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS |
| SECTION 00245 - TEMPORARY WATER MANAGEMENT |
| Description |
| Materials |
| Construction |
| Maintenance |
| Finishing and Cleaning Up |
| Measurement |
| Payment |
| SECTION 00280 - EROSION AND SEDIMENT CONTROL |
| SECTION 00290 - ENVIRONMENTAL PROTECTION |
| SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS |
| SECTION 00445 - SANITARY, STORM, CULVERT, SIPHON, AND IRRIGATION PIPE |
| SECTION 00640 - AGGREGATE BASE AND SHOULDERS |
File details come from the government source that posted it. Updated .