BPA interim mechanical maintenance

Ended Blanket Purchase Agreement Awarded Last action

Contract number
GS02P17PWA0003
Awardee
Awarding agency
Task orders
32 $2,410,988 obligated

Award facts

Combined order value
$2,410,988 Current and potential, with all options
Last date to order 100% complete
Award type
Single award
Who can order
Only the awarding agency
NAICS code
561210 Facilities Support Services
Set-aside
No set-aside
Pricing
Firm Fixed Price
Legislative mandates

Award details come from SAM.gov/FPDS.

Task orders

Task order Ordering agency Obligated Awarded
Replace the water closets, toilets and urinals throughout the binghamton federal office building and courthouse as… 47PC0419F0066 Region 2 (PBS) $23,270
Binghamton advance metering 47PC1518F0046 Region 2 (PBS) $24,626
Syracuse technical support building automation system 47PC0418F0084 Region 2 (PBS) $5,060
Syracuse panic hardware installation south tower contractor shall provide all labor, materials, equipment and… 47PC0418F0075 Region 2 (PBS) $16,629
Install new VFD for a/c supply fan and VAV controllers hanley FB & usch syracuse NY. 47PC1518F0039 Region 2 (PBS) $11,469
Utica flush radiators 47PC1518F0037 Region 2 (PBS) $16,588
Exterior door repair and upgrade line 28 47PC1518F0036 Region 2 (PBS) $18,543
Steam coil RM 229 repair, pirnie FB & usch utica NY. 47PC1518F0034 Region 2 (PBS) $4,543
Install split AC units at the binghamton federal office building and courthouse located at 15 henry street, binghamton 47PC0418F0065 Region 2 (PBS) $7,117
Repair post indicator valve - pirnie FB & usch utica NY. 47PC1518F0033 Region 2 (PBS) $18,400
Duct modification in conference room hanley FB & usch syracuse NY. 47PC1518F0031 Region 2 (PBS) $16,178
Exterior door repairs binghamton FB & usch, binghamton NY. 47PC1518F0032 Region 2 (PBS) $22,915
Utica condensate tank 47PC0418F0064 Region 2 (PBS) $94,300
Utica rehab paint exterior light fixtures 47PC0418F0055 Region 2 (PBS) $10,328
Syracuse panic hardware annex courthouse 47PC0418F0052 Region 2 (PBS) $11,202
Repair chiller oil separator heaters binghamton usch & FB binghamton NY. 47PC1518F0027 Region 2 (PBS) $2,991
Repair childcare fencing hanley FB & usch syracuse NY. 47PC1518F0025 Region 2 (PBS) $21,614
Binghamton federal office building and courthouse - replace drinking fountains throughout the common areas of the… 47PC0418F0035 Region 2 (PBS) $3,789
Replace defective fans in AC-2 47PC1518F0009 Region 2 (PBS) $4,040
Standpipe repair, pirnie FB & usch utica, NY. 47PC1518F0002 Region 2 (PBS) $4,555
A/c repair for pirnie federal building, utica, NY 47PC1118F0008 Region 2 (PBS) $5,320
Replace oven for hanley federal building, syracuse, NY 47PC1118F0006 Region 2 (PBS) $12,592
Boiler repair for pernie federal building, utica, NY 47PC1118F0005 Region 2 (PBS) $12,700
Retube boiler at the binghamton federal building and courthouse, binghamton, NY 47PC1118F0004 Region 2 (PBS) $15,631
AC compressor replacement 47PC0417F0026 Region 2 (PBS) $13,800
Sidewalk repair binghamton FB & usch binghamton NY. 47PC1517F0016 Region 2 (PBS) $16,560
Binghamton underground storage tank cover 47PC1517F0015 Region 2 (PBS) $4,665
Fire alarm inspection deficiencies repairs, hanley FB & usch syracuse NY. 47PC1517F0014 Region 2 (PBS) $14,433
Repair vfds for garage exhaust, hanley FB & usch syracuse NY. 47PC1517F0012 Region 2 (PBS) $9,407
Repair VFD's - AC1 and AC2 return fans, hanley FB & usch syracuse NY. 47PC1517F0010 Region 2 (PBS) $10,906
Installation of panic hardware on stairwell doors at hanley FB & usch syracuse NY. 47PC1517F0002 Region 2 (PBS) $16,629
BPA call for interim mechanical maintenance upstate NY GSP0217PW0020 Region 2 (PBS) $1,940,190
Show all 32

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS06 · BPA for interim upstate o & m contract - MOD to incorporate section 889 part b $0
Other Administrative Action PA05 · Upstate interim mechanical maintenance BPA - change completion date from 5/1/2020 to 10/31/2020 to allow for task order completion $0
Supplemental Agreement for work within scope PS04 · Emergency upstate o & m MOD to include section 889 $0
Other Administrative Action PA03 · No cost time EXT on iterim upsate o & m contract to allow for close out of open task orders (from 8/31/2019 to 4/30/2020) $0
Change Order PC02 · Interim mechanical maintenance contract - BPA this modification changes the completion date from october 31, 2018 to august 31, 2019 to allow for completion… $0
Change Order PC01 · Interim mech maint 4 month time extension $0
Original award $0

Quick answers

Who was awarded contract GS02P17PWA0003?

GS02P17PWA0003 was awarded to Ben Fitzgerald Real Estate Services, L.L.C. by Region 2 (Public Buildings Service) on June 1, 2017.

How much is contract GS02P17PWA0003 worth?

Orders under GS02P17PWA0003 have obligated $2,410,988.

How many orders have been placed under contract GS02P17PWA0003?

32 orders have been placed under GS02P17PWA0003, the latest on May 7, 2019.

Who can order from contract GS02P17PWA0003?

GS02P17PWA0003 is a single award blanket purchase agreement. Only the awarding agency can place orders on it.

On GovTribe

See this IDV's full record

  • Every order and transaction
  • The awardee's other awards and teaming partners
  • Similar IDVs and recompete opportunities
  • Ask GovTribe AI about this IDV