About this opportunity
The City of Monroe, Louisiana is requesting sealed bids for replacement or repair of the sluice gate system at the Pine Street Flood Control Structure, with bids due October 15, 2026 at 1:45 p.m. and a pre-bid conference on October 1 at 2:00 p.m.
The scope addresses two inoperable sluice gates serving flood mitigation for the city. Work includes replacement of the entire sluice gate system or repair of all broken items if interchangeable; replacement of motors, stems, stem guides, and Limitorque control panels; repair or replacement of inoperable level control devices that display gate position to operators; and electrical system restoration within the existing Limitorque operator. The existing sluice gates will be inspected for damage and replaced if damaged or incompatible with new systems.
The facility is located off Riverside Drive within Monroe city limits. Sealed bids must be received at the City of Monroe Purchasing Division, 1014 Grammont Street, Monroe, Louisiana 71201, and will be opened and read aloud at 2:00 p.m. on October 15. Bidders may submit electronically through Quest CDN using Owner Number 2027-00000017 or deliver sealed bids in person. Electronic submission carries a $22.00 download fee and a $42.00 online bidding fee. Paper bidding documents are available from Volkert Engineering, 114 Venable Lane, Monroe, Louisiana 71203, for a $100.00 refundable deposit per set if returned within ten days after bid receipt. The design contact is Clinton Patrick at Volkert Engineering, 318-388-1422 or clinton.patrick@volkert.com. The pre-bid conference is held at the City Engineering Department Conference Room, 1401 Stubbs Avenue, Monroe, Louisiana 71201.
Opportunity text
The Pine Street Flood Control Structure is located off Riverside Drive within the city limits of the City of Monroe. The Pine Street Control Structure and Pump Station serve as an important device to help the City of Monroe control flooding. The existing Pine Street Flood Control Structure is in need of replacement of the two (2) existing sluice gates. One of the existing sluice gates has become inoperable because of a broken stem and stem collar. The existing level control devices have also become inoperable. These gate level control devices show the operator how much the gate is open or closed. The electrical system within the existing Limitorque operator has also become inoperable. The buttons used to lower and raise the existing gates do not work and other means are being used to operate the gate when the gate was functioning properly. The project would consist of replacing the entire sluice gate system or repairing all broken items if the items are interchangeable. This would include replacing the motor, Limitorque control panel, existing stems, and stem guides. The existing sluice gate would also be inspected for damage and replaced if damaged or if the new sluice gate system would not be compatible with the existing gate.
Files
| File | Type | Posted |
|---|---|---|
| city of monroe pine street flood control structure improvements.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity