About this opportunity

The City of Clearwater is soliciting bids for the Edgewater Drive Park Renovation project, a construction contract with a proposal due date of July 29, 2026 and substantial completion required by March 2027.

The scope includes demolition and removal of existing asphalt pavement in the parking area and concrete sidewalk along Edgewater Drive; construction of an expanded parking facility to accommodate additional vehicular spaces; reconstruction and widening of the existing 6-foot concrete sidewalk to 10 feet to meet accessibility and pedestrian circulation requirements; installation of a stormwater pond; site furnishings including benches, waste receptacles, drinking fountains, and bike repair station; landscaping; regulatory and informational signage as specified in construction plans; and adjustments to existing utility structures to match proposed finish grades and elevations. All utility adjustments shall comply with applicable standards and be coordinated with respective utility owners. The contractor shall provide one fixed or portable project sign per contract documents.

The contract period is six months or 150 consecutive calendar days. All work is unit-price based per the Contract Documents. The city is not obligated to purchase any minimum or maximum amount during the contract life; all quantities are estimates only. The contractor shall coordinate all work per Section III, Section 11.3, Unit Price Work, of the Contract Documents.

Two government files have been posted: Edgewater_Drive_Park_Renovation.pdf (229 KB) and Edgewater_Drive_Park_Renovations_-CE_Bid_Set-SS(1)_(1).pdf (47 MB, posted June 4, 2026).

Opportunity text

2 versions

Update #2 · Latest ·

The Scope of Work for the Edgewater Drive Park Renovations Project includes the demolition and removal of existing asphalt pavement within the current parking area, as well as the removal of the adjacent concrete sidewalk along Edgewater Drive. The proposed improvements consist of the construction of an expanded parking facility to accommodate additional vehicular spaces. The existing 6-foot-wide concrete sidewalk will be reconstructed and widened to 10 feet to meet updated accessibility and pedestrian circulation requirements. Site improvements also include the installation of a stormwater pond, site furnishings such as benches, waste receptacles, drinking fountain(s), bike repair station, landscaping and regulatory/informational signage as specified in the construction plans. Adjustments to existing utility structures shall be performed as necessary to match the proposed finish grades and elevations indicated in the construction documents. All adjustments shall comply with applicable standards and be coordinated with the respective utility owners.

The intent of this bid is to obtain competitive prices to establish a contract for construction services. All quantities are estimates only and the city of Clearwater (city) is not obligated to purchase any minimum or maximum amount during the life of the contract. All the work is to be administered per Section III, Section 11.3, Unit Price Work, of the Contract Documents. The Contractor shall provide one (1) [Fixed/Portable] project sign as described in Section III, Section 23 of the Contract Documents.

Contract Period: 4.5 months or 136 consecutive calendar days from November 15, 2026 - March 31, 2027 with substantial completion of the project by March 31, 2027

Update #1 ·

The Scope of Work for the Edgewater Drive Park Renovations Project includes the demolition and removal of existing asphalt pavement within the current parking area, as well as the removal of the adjacent concrete sidewalk along Edgewater Drive. The proposed improvements consist of the construction of an expanded parking facility to accommodate additional vehicular spaces. The existing 6-foot-wide concrete sidewalk will be reconstructed and widened to 10 feet to meet updated accessibility and pedestrian circulation requirements. Site improvements also include the installation of a stormwater pond, site furnishings such as benches, waste receptacles, drinking fountain(s), bike repair station, landscaping and regulatory/informational signage as specified in the construction plans. Adjustments to existing utility structures shall be performed as necessary to match the proposed finish grades and elevations indicated in the construction documents. All adjustments shall comply with applicable standards and be coordinated with the respective utility owners.

The intent of this bid is to obtain competitive prices to establish a contract for construction services. All quantities are estimates only and the city of Clearwater (city) is not obligated to purchase any minimum or maximum amount during the life of the contract. All the work is to be administered per Section III, Section 11.3, Unit Price Work, of the Contract Documents. The Contractor shall provide one (1) [Fixed/Portable] project sign as described in Section III, Section 23 of the Contract Documents.

Contract Period: 6 months or 150 Consecutive Calendar Days with substantial completion by March 2027.