The New Jersey Department of Transportation is soliciting technical proposals for two separate National Bridge Inspection Standards (NBIS) movable bridge inspection projects under a one-step procurement process, with proposals due September 24, 2026 by 10:00 a.m. and questions due September 17, 2026. Eligible firms must hold NJDOT prequalification in Discipline I-3, Level A as of the closing deadline; no federal or state certified firm utilization goals apply.
The scope encompasses initial and routine inspections of two groups: Group 13H7 (4 Monmouth County movable bridges) and Group M27A (14 State movable bridges, 12 NHPP-funded and 2 On-System). Work includes adherence to 23 CFR Part 650 Subpart C, the Specifications for the National Bridge Inventory (SNBI), and NJDOT Bridge Inspection Program Policy and Procedures (June 6, 2024, as revised). Consultants must perform structural evaluations using inspection procedures in the Bridge Inspector's Reference Manual; conduct mechanical and electrical inspections of movable structures; perform underwater inspections where required; determine physical and functional condition; and provide load ratings based on the 2018 AASHTO Manual for Bridge Evaluation, 3rd Edition. All SNBI and State inventory data must be refined, verified, and updated within three months of inspection completion (or by January 31 if inspections occur year-end). Deliverables include comprehensive Bridge Survey Reports with CAD drawings and database entries in CombIS, submitted as signed and sealed final documents within two months of agreement term end. The Project Manager must hold an ASCE Grade no higher than PVI and be a full-time employee; the Structural Team Leader must hold an ASCE Grade no higher than PV. Mandatory training includes NHI Bridge Inspection Refresher Training (NHI #130053) with National Bridge Element training and NHI #130055. Sub-consultants must be cost-basis approved by NJDOT by the closing deadline. The contract type is a Project Specific Agreement with fixed-price compensation, federal-funded through FHWA's NBIS program. No firm may be selected for more than two projects across all current solicitations. Anticipated selection is October 2026.
Opportunity text
The CONSULTANT shall: Adhere to the Code of Federal Regulations, Title 23, Part 650, Subpart C - National Bridge Inspection Standards (NBIS), Specifications for the National Bridge Inventory (SNBI), and State of New Jersey Bridge Inspection Program Policy and Procedures, dated June 6, 2024, with any subsequent revisions. The initial SNBI inventory data will be pre-populated by converting the data from 1995 Coding Guide to 2022 SNBI using the FHWA Transition Tool. The Consultant shall refine this inventory data, i.e. verify/revise all clean and partial transition data items, and code all new data items. The NJDOT State items need to be coded as well. The SNBI and State inventory data shall be updated within three (3) months of the inspection being completed. However, for inspections occurring near the end of the year, all data shall be inputted by January 31st. Contact the governing agencies or authorities prior to commencing any work under this Agreement. Obtain and provide the STATE with necessary letters and documents that grant approval for access, inspections of Structures, and other related activities. Perform a thorough assessment of each Structure utilizing one or more of the following inspection types: Initial, Routine, Underwater, Nonredundant Steel Tension Member (NSTM), Special/Interim, In-Depth, Damage, Scour Monitoring, and Service. Perform the required inspection of each Structure using the procedures and techniques noted in the Bridge Inspector's Reference Manual (BIRM) to determine the following: The physical and functional condition of the Structure utilizing observations and measurements. This may include special testing as required. The present live load capacity, or rating of the Structure, based on the current (2018) AASHTO Manual for Bridge Evaluation, 3rd Edition, and NJDOT Highway Bridge Load Rating Manual. Structures shall be load rated as soon as practical, but no later than 3 months after the Initial inspection or when a change is identified that warrants a re-rating such as, but not limited to, changes in condition, reconstruction, new construction, or changes in dead or live loads. Any decrease in the live load carrying capacity of a Structure that would require posting or a change in the existing posting should be brought, in writing, to the immediate attention of the STATE, County or any other governing agency. Any structural or safety related deficiency that requires immediate follow-up inspection or action to ensure public safety. All Critical Findings, as defined in the NBIS, must be reported immediately to the STATE, County or any other governing agency. The location and the redundancy of the members affected, and the extent and consequence of a deficiency should be considered when identifying a Critical Finding. Also, all priority repairs shall be identified in accordance with the Bridge Owners procedure. The streambed profile of the waterway channel along each fascia limit and longitudinal centerline (required if a bridge has four or more lanes of traffic, or if the bridge is on an abnormal skew). Perform sufficient soundings at each substructure element to determine the relationship of the foundation to the streambed. Review previous soundings and note any significant changes in the streambed. Plot plan view and elevation views of the waterway channel. The plan view shallinclude the general configuration of the waterway channel and its relationship to the bridge opening, the direction of flow, the orientation of the substructure elements, significant hydraulic related features such as areas of sedimentation, debris or scour countermeasures, and sounding data in a tabular form. The elevation views shall include the general configuration of the substructure elements, the elevations of the substructure foundations (if available), the streambed profiles to show long term changes (oldest available, previous, and current), and the water elevation at the time of inspection. The vertical clearances above and below the Structure and the lateral clearances to the left and right below the Structure. The structural and geometric adequacy of the Structure. The adequacy of the safety features such as, but not limited to, roadside hardware, approach guide rails and end treatments. The horizontal and vertical alignment of the bridge approaches. Perform Initial or Routine inspection of each Structure. An Initial inspection of each new, replaced (including each stage of stage construction), rehabilitated, or temporary bridge shall be performed as soon as practical, but within 3 months of the bridge opening to traffic. Perform Underwater inspection of the Structures in accordance with the New Jersey Department of Transportation Underwater Inspection and Evaluation of New Jersey Bridges Guidelines Manual, dated June 1994 with subsequent revisions. The Underwater inspection shall be performed by a qualified diver in accordance with the State of New Jersey Bridge Inspection Program Policy and Procedures, dated June 6, 2024. The inspection shall be from the mud line to the high-water line, inspecting all underwater components for deterioration including spalls, cracks, marine borer damage, rot, necking, and any other defects. Prepare and submit a stand-alone Underwater inspection report, according to NJDOT standards, for each Structure. Act upon all comments submitted relative to all reviews of the Underwater inspection report. Address or include all comments and convert the final report into a PDF, with format and file naming according to the current version of the NJDOT SDMS Contractors Specifications for Scanning, PDFing, and Electronic Deliverables, and submit both electronically and in hard copy. Perform hands-on inspection of all Nonredundant Steel Tension Member (NSTM). The NSTM inspection shall utilize visual methods that may be supplemented by nondestructive testing. A very detailed visual hands-on inspection is the primary method of detecting cracks. This may require that critical areas be specially cleaned prior to the inspection and additional lighting and magnification be used. Other nondestructive methods may be used at the discretion of the Bridge Owner. Identify and perform Special/Interim inspections of the Structures in accordance with the State of New Jersey Bridge Inspection Program Policy and Procedures, dated June 6, 2024. Special/Interim inspections may be conducted in lieu of reduced frequency inspection when localized deficiencies exist. Submit, within thirty (30) days of the completion of the Routine inspection of the Structures, a list of any additional Structures that may require Special/Interim inspections. The list will include a description of the structural component area requiring the Special/Interim inspection, structure number, name and recommended inspection interval. The Special/Interim inspection report shall be submitted to the STATE, County or governing agency within thirty (30) days of the Special/Interim inspection date. Perform only those Special/Interim inspections which can be accomplished within the time period for completion of work established by this Agreement and any Consultant Contract Modification hereto. Costs incurred for performing the Special/Interim inspections of Structures not previously identified shall be compensated as Additional Work/Extra Work through a Consultant Contract Modification. Perform In-Depth inspections, such as Pin & Hanger and In-Depth NSTM inspections, of the assigned Structures in accordance with their respective Scope of Work. Perform Mechanical & Electrical inspections of movable bridges in accordance with Movable Bridge Engineering Groups (MBEG) Scope of Work.
Files
| File | Type | Posted |
|---|---|---|
| njdot TP-857 A Solicitation.docx.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity