Whitetail DAM reconstruction
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 140L3621R0001
- Agency
- Bureau of Land Management Department of the Interior
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Z2KA Repair Or Alteration Of Dams
- Place of performance
- Carter County Alzada Mt, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The Bureau of Land Management Montana State Office is soliciting proposals to repair Whitetail Dam located in Carter County, Montana. Work will include dewatering the reservoir, excavating portions of the existing dam, reconstructing the embankment with compacted fill and imported rock and concrete structures, constructing a new principal spillway and outlet works, installing a stilling basin and gravel surfacing, and performing final reclamation. Proposals will be evaluated using lowest priced technically acceptable procedures. Proposals are due by May 19, 2021, with an anticipated award date of June 16, 2021.
This procurement is set aside for total small businesses under NAICS code 237990, with a small business size standard of $39.5 million. The estimated price range for the work is $500,000 to $1,000,000. The successful contractor must commence work within 10 days of notice to proceed and complete all work within 167 calendar days at the Whitetail Dam site located approximately 27 miles northwest of Alzada, Montana.
Notice text
2 versions
Update #2 · Latest ·
The Department of Interior, Bureau of Land Management (BLM), Montana State Office is soliciting proposals for repair of Whitetail Dam located in Carter County approximately 27.4 miles northwest of Alzada, Montana. BLM will issue Solicitation Number 140L3621R0001 via https://beta.sam.gov/search?index=opp, at the link provided in this notice. The principal components of the work to be performed include the following tasks:
1. Dewater reservoir and construction area.
2. Excavate a portion of the existing dam embankment and foundation to remove existing outlet works pipe and construction of the new outlet works.
3. Reconstruct the dam embankment including:
a. Placement of compacted fill from onsite borrow sources,
b. Placement of imported rock for riprap slope protection along a portion of the upstream face,
c. Placement and compaction of imported sand and gravel for internal filter and drain features.
4. Construct precast concrete spillway riser for a new principal spillway.
5. Construct concrete encased, precast reinforced concrete pipe outlet conduit.
6. Construct precast concrete low-level inlet structure.
7. Construct grouted riprap stilling basin.
8. Place road gravel surfacing along the crest of the dam.
9. Reclaim all disturbed areas including staging areas and temporary roads. Reclamation consists of preparation of the soil for seeding but does not include seeding. Seeding of the reclaimed areas will be completed by Others.
Pursuant to Part 15 and Part 36 of the Federal Acquisition Regulations, BLM issued a Request for Proposal (RFP) on April 14, 2021. The estimated price range of this acquisition is between $500,000 and $1,000,000. BLM anticipates issuing the RFP under the total small business set-aside program. The applicable North American Industry Classification System (NAICS) Code is 237990 and the associated Small Business Size Standard is $39.5 Million.
Amendment Number 0001 was issued on May 6, 2021 and incorporated the following:
1. Revised Whitetail Dam Reconstruction Technical Drawings
2. Revised Past Performance Questionnaire
3. Whitetail Dam Site Tour Access Route
4. Site Visit Attendance Records
5. Questions received from interested offerors and the associated Answers provided by the Government.
This acquisition will utilize the Lowest Priced Technically Acceptable (LPTA) procedures to make a best value award. A firm-fixed priced contract is contemplated. Proposals are due on May 19, 2021 at BLM's Montana State Office, 5001 Southgate, Billings, Montana.
The Government anticipates award of this procurement on or around June 16, 2021. The successful contractor will be required to commence work within 10 calendar days after the date the Contractor receives the notice to proceed and complete the entire work ready for use within 167 calendar days. The time stated for completion shall include final cleanup of the premises.
For further information about the requirement, offerors should contact Christine Mundt at cmundt@blm.gov or at (406) 896-5030.
All prospective contractors must be registered in the System for Award Management (SAM) in order to be eligible for award. If you have not updated SAM since October of 2020, you are advised to update early to be sure you are in compliance with the expanded Section 889 prohibitions on not using certain covered technology products.
The successful contractor shall electronically submit all payment requests for the anticipated contract through the U.S. Department of the Treasury's Invoice Processing Platform (IPP). If the contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the contractor must submit a waiver request in writing to the Contracting Officer with its offer.
Update #1 ·
The Department of Interior, Bureau of Land Management (BLM), Montana State Office is soliciting proposals for repair of Whitetail Dam located in Carter County approximately 27.4 miles northwest of Alzada, Montana. BLM will issue Solicitation Number 140L3621R0001 via https://beta.sam.gov/search?index=opp, at the link provided in this notice. The principal components of the work to be performed include the following tasks:
1. Dewater reservoir and construction area.
2. Excavate a portion of the existing dam embankment and foundation to remove existing outlet works pipe and construction of the new outlet works.
3. Reconstruct the dam embankment including:
a. Placement of compacted fill from onsite borrow sources,
b. Placement of imported rock for riprap slope protection along a portion of the upstream face,
c. Placement and compaction of imported sand and gravel for internal filter and drain features.
4. Construct precast concrete spillway riser for a new principal spillway.
5. Construct concrete encased, precast reinforced concrete pipe outlet conduit.
6. Construct precast concrete low-level inlet structure.
7. Construct grouted riprap stilling basin.
8. Place road gravel surfacing along the crest of the dam.
9. Reclaim all disturbed areas including staging areas and temporary roads. Reclamation consists of preparation of the soil for seeding but does not include seeding. Seeding of the reclaimed areas will be completed by Others.
Pursuant to Part 15 and Part 36 of the Federal Acquisition Regulations, BLM issued a Request for Proposal (RFP) on April 14, 2021. The estimated price range of this acquisition is between $500,000 and $1,000,000. BLM anticipates issuing the RFP under the total small business set-aside program. The applicable North American Industry Classification System (NAICS) Code is 237990 and the associated Small Business Size Standard is $39.5 Million.
This acquisition will utilize the Lowest Priced Technically Acceptable (LPTA) procedures to make a best value award. A firm-fixed priced contract is contemplated. Proposals will be due on May 19, 2021 at BLM's Montana State Office, 5001 Southgate, Billings, Montana.
The Government anticipates award of this procurement on or around June 16, 2021. The successful contractor will be required to commence work within 10 calendar days after the date the Contractor receives the notice to proceed and complete the entire work ready for use within 167 calendar days. The time stated for completion shall include final cleanup of the premises.
For further information about the requirement, offerors should contact Christine Mundt at cmundt@blm.gov or at (406) 896-5030.
All prospective contractors must be registered in the System for Award Management (SAM) in order to be eligible for award. If you have not updated SAM since October of 2020, you are advised to update early to be sure you are in compliance with the expanded Section 889 prohibitions on not using certain covered technology products.
The successful contractor shall electronically submit all payment requests for the anticipated contract through the U.S. Department of the Treasury's Invoice Processing Platform (IPP). If the contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the contractor must submit a waiver request in writing to the Contracting Officer with its offer.
Attachments
| File | Type | Posted |
|---|---|---|
| WhitetailDam_Drawings_Final_R1_0001.pdf | ||
| Sol_140L3621R0001_Amd_0001.pdf | ||
| Site Tour Access Map_0001.pdf | ||
| Site Tour Notes 4-28-21 - Typed_0001.pdf | ||
| 13E - Past Performance Questionnaire_0001.pdf | ||
| Questions and Answers_0001.pdf | ||
| Sol_140L3621R0001.pdf | ||
| 140L3621R0001 Solicitation Package (Issued).pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Award Notice - Whitetail Dam Reconstruction | Award Notice | |
| Whitetail DAM reconstruction | Solicitation | |
| Whitetail Dam Reconstruction | Pre-Solicitation |