W912EF18R0004 Amendment 0002

Awarded Award Notice Posted

Solicitation number
W912EF18R0004
Agency
ENDIST Walla Walla US Army Corps of Engineers, Department of Defense
Awarded
to Koontz Electric Company, Incorporated
Set-aside
No set-aside

Opportunity facts

Contract number
W912EF18C0018 Federal contract award
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

6 versions

Update #6 · Latest ·

Added: Jun 07, 2018 9:07 pm Contract award W912EF18C0018

Update #5 ·

Added: Nov 20, 2017 12:55 pm Modified: Mar 26, 2018 7:21 pmTrack Changes
This is now a solicitation-see attached documents

Synopsis:

Solicitation No. W912EF18R0004 will be posted to the FBO website on or about mid to late January 2018. Solicitation is advertised as Unrestricted (Originally posted incorrectly as Small Business Set Aside). The solicitation is a Request for Proposal. The proposal due date will be contained in the solicitation and any solicitation amendments that may be issued.


The construction magnitude is estimated between $1,000,000 and $5,000,000. 100% performance and payment bonds will be required. NAICS code for this project is 238210.


Summary of Work


Manually-operated line disconnect switches and their respective ground switches will be replaced with new motor-operated disconnect switches and new motor-operated ground switches of the same ratings. A new 125VDC circuit will be extended to each new pair of disconnect/ground switch motor operators from the main unit auxiliary panels in the generator bays. Remote control of these line disconnect switches and grounding switches will be provided in the Control Room in a new control panel.


Three sets of bus potential transformers (PT's) for the BPA lines will be replaced with new PT's of the same class and ratings, including replacing their existing wiring to the SCR boards in the Control Room.


Three sets of surge arresters for the BPA lines are to be provided and connected to the 115kV bus sections, including Contractor-designed support structures for mounting the arresters on the Transformer Deck.


Modifications must be provided to one of the 115kV bus sections involving cutting out segments of the 3" tubular aluminum bus and fitting them with straight tube-to-tube connectors for reinstallation after sectionalizing switch has been replaced. This is to provide a present and future means to isolate a switch for replacement and maintenance while leaving Line 1 and station service energized.


All new switch motor-operators are to be operable from the switch operator as well as remotely operable from a new remote control panel to be provided in the Control Room SO5 board, including indication of switch position. Ground switches and line switches will be mechanically interlocked at the switch operators and at the remote control panel to prevent accidental grounding of an energized line.


All new power and control circuits for the new switch operators will be run in a new 9" cable trough to be provided in the Cable Gallery, running from Unit 6 to the Cable Spread Room.


General Contract Requirements


Complete all on-site work within a finite work windows constrained to August 2018 through December 2018.


Important Note: The FedBizOpps Response Date listed elsewhere in this synopsis is for FedBizOpps archive purposes only. It does not necessarily reflect the actual bid opening date. The bid opening date will be contained in the solicitation and any solicitation amendments that may be issued.


A site visit will be offered approximately 2 weeks after the solicitation is made available to bidders. See solicitation for details about the site visit.


ACCESS FOR FOREIGN NATIONALS: Security clearance for foreign nationals to attend a site visit requires approximately 5 weeks; therefore, clearance should be requested immediately. To request clearance, please submit the names of all foreign nationals proposed for site visit attendance, along with documentation to verify that he/she was legally admitted into the United States and has authority to work and/or go to school in the US. Such documentation may include a US passport, Certificate of US citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), foreign passport with I-551 stamp or attached INS Form I-94 indicating employment authorization, Alien Registration Receipt Card with photograph (INS Form I-151 or I-551), Temporary Resident Card (INS Form I-688), Employment Authorization Card (INS Form I-688A), Reentry Permit (INS Form I-327), Refugee Travel Document (INS Form I-571), Employment Authorization Document issued by the INS which contains a photograph (INS Form I-688B). Send this information by email to cynthia.h.jacobsen@usace.army.mil. Foreign nationals must have received clearance prior to being granted access to the project site.


When available, the solicitation documents for this project will be available via FedBizOpps.gov https://www.fbo.gov NO CD's OR HARD COPIES WILL BE AVAILABLE. Bidders are responsible for checking the referenced page for any update(s) to the Notice. The Government is not responsible for any loss of Internet connectivity or for an offeror's inability to access the document posted at the referenced website. To obtain automatic notifications of updates to this solicitation, you MUST log in to FedBizOpps.gov and add the solicitation to your Watchlist. If you would like to list your firm so others can see you are an interested vendor, you must click the "Add Me To Interested Vendors" button in the listing for this solicitation on FedBizOpps.gov.

Update #4 ·

Added: Mar 23, 2018 1:32 pm The current schedule for the solicitation to be posted is by the end of March 2018. The solicitation is going out as UNRESTRICTED

Update #3 ·

Added: Nov 20, 2017 12:55 pm Modified: Dec 29, 2017 10:54 amTrack Changes Synopsis:

Solicitation No. W912EF18R0004 will be posted to the FBO website on or about mid to late January 2018. Solicitation is advertised as Unrestricted (Originally posted incorrectly as Small Business Set Aside). The solicitation is a Request for Proposal. The proposal due date will be contained in the solicitation and any solicitation amendments that may be issued.


The construction magnitude is estimated between $1,000,000 and $5,000,000. 100% performance and payment bonds will be required. NAICS code for this project is 238210.


Summary of Work


Manually-operated line disconnect switches and their respective ground switches will be replaced with new motor-operated disconnect switches and new motor-operated ground switches of the same ratings. A new 125VDC circuit will be extended to each new pair of disconnect/ground switch motor operators from the main unit auxiliary panels in the generator bays. Remote control of these line disconnect switches and grounding switches will be provided in the Control Room in a new control panel.


Three sets of bus potential transformers (PT's) for the BPA lines will be replaced with new PT's of the same class and ratings, including replacing their existing wiring to the SCR boards in the Control Room.


Three sets of surge arresters for the BPA lines are to be provided and connected to the 115kV bus sections, including Contractor-designed support structures for mounting the arresters on the Transformer Deck.


Modifications must be provided to one of the 115kV bus sections involving cutting out segments of the 3" tubular aluminum bus and fitting them with straight tube-to-tube connectors for reinstallation after sectionalizing switch has been replaced. This is to provide a present and future means to isolate a switch for replacement and maintenance while leaving Line 1 and station service energized.


All new switch motor-operators are to be operable from the switch operator as well as remotely operable from a new remote control panel to be provided in the Control Room SO5 board, including indication of switch position. Ground switches and line switches will be mechanically interlocked at the switch operators and at the remote control panel to prevent accidental grounding of an energized line.


All new power and control circuits for the new switch operators will be run in a new 9" cable trough to be provided in the Cable Gallery, running from Unit 6 to the Cable Spread Room.


General Contract Requirements


Complete all on-site work within a finite work windows constrained to August 2018 through December 2018.


Important Note: The FedBizOpps Response Date listed elsewhere in this synopsis is for FedBizOpps archive purposes only. It does not necessarily reflect the actual bid opening date. The bid opening date will be contained in the solicitation and any solicitation amendments that may be issued.


A site visit will be offered approximately 2 weeks after the solicitation is made available to bidders. See solicitation for details about the site visit.


ACCESS FOR FOREIGN NATIONALS: Security clearance for foreign nationals to attend a site visit requires approximately 5 weeks; therefore, clearance should be requested immediately. To request clearance, please submit the names of all foreign nationals proposed for site visit attendance, along with documentation to verify that he/she was legally admitted into the United States and has authority to work and/or go to school in the US. Such documentation may include a US passport, Certificate of US citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), foreign passport with I-551 stamp or attached INS Form I-94 indicating employment authorization, Alien Registration Receipt Card with photograph (INS Form I-151 or I-551), Temporary Resident Card (INS Form I-688), Employment Authorization Card (INS Form I-688A), Reentry Permit (INS Form I-327), Refugee Travel Document (INS Form I-571), Employment Authorization Document issued by the INS which contains a photograph (INS Form I-688B). Send this information by email to cynthia.h.jacobsen@usace.army.mil. Foreign nationals must have received clearance prior to being granted access to the project site.


When available, the solicitation documents for this project will be available via FedBizOpps.gov https://www.fbo.gov NO CD's OR HARD COPIES WILL BE AVAILABLE. Bidders are responsible for checking the referenced page for any update(s) to the Notice. The Government is not responsible for any loss of Internet connectivity or for an offeror's inability to access the document posted at the referenced website. To obtain automatic notifications of updates to this solicitation, you MUST log in to FedBizOpps.gov and add the solicitation to your Watchlist. If you would like to list your firm so others can see you are an interested vendor, you must click the "Add Me To Interested Vendors" button in the listing for this solicitation on FedBizOpps.gov.

Update #2 ·

Added: Nov 20, 2017 12:55 pm Modified: Dec 29, 2017 10:43 amTrack Changes Synopsis:

Solicitation No. W912EF18R0004 will be posted to the FBO website on or about mid to late December 2017. Solicitation is advertised as Unrestricted. The solicitation is a Request for Proposal. The proposal due date will be contained in the solicitation and any solicitation amendments that may be issued.


The construction magnitude is estimated between $1,000,000 and $5,000,000. 100% performance and payment bonds will be required. NAICS code for this project is 238210.


Summary of Work


Manually-operated line disconnect switches and their respective ground switches will be replaced with new motor-operated disconnect switches and new motor-operated ground switches of the same ratings. A new 125VDC circuit will be extended to each new pair of disconnect/ground switch motor operators from the main unit auxiliary panels in the generator bays. Remote control of these line disconnect switches and grounding switches will be provided in the Control Room in a new control panel.


Three sets of bus potential transformers (PT's) for the BPA lines will be replaced with new PT's of the same class and ratings, including replacing their existing wiring to the SCR boards in the Control Room.


Three sets of surge arresters for the BPA lines are to be provided and connected to the 115kV bus sections, including Contractor-designed support structures for mounting the arresters on the Transformer Deck.


Modifications must be provided to one of the 115kV bus sections involving cutting out segments of the 3" tubular aluminum bus and fitting them with straight tube-to-tube connectors for reinstallation after sectionalizing switch has been replaced. This is to provide a present and future means to isolate a switch for replacement and maintenance while leaving Line 1 and station service energized.


All new switch motor-operators are to be operable from the switch operator as well as remotely operable from a new remote control panel to be provided in the Control Room SO5 board, including indication of switch position. Ground switches and line switches will be mechanically interlocked at the switch operators and at the remote control panel to prevent accidental grounding of an energized line.


All new power and control circuits for the new switch operators will be run in a new 9" cable trough to be provided in the Cable Gallery, running from Unit 6 to the Cable Spread Room.


General Contract Requirements


Complete all on-site work within a finite work windows constrained to August 2018 through December 2018.


Important Note: The FedBizOpps Response Date listed elsewhere in this synopsis is for FedBizOpps archive purposes only. It does not necessarily reflect the actual bid opening date. The bid opening date will be contained in the solicitation and any solicitation amendments that may be issued.


A site visit will be offered approximately 2 weeks after the solicitation is made available to bidders. See solicitation for details about the site visit.


ACCESS FOR FOREIGN NATIONALS: Security clearance for foreign nationals to attend a site visit requires approximately 5 weeks; therefore, clearance should be requested immediately. To request clearance, please submit the names of all foreign nationals proposed for site visit attendance, along with documentation to verify that he/she was legally admitted into the United States and has authority to work and/or go to school in the US. Such documentation may include a US passport, Certificate of US citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), foreign passport with I-551 stamp or attached INS Form I-94 indicating employment authorization, Alien Registration Receipt Card with photograph (INS Form I-151 or I-551), Temporary Resident Card (INS Form I-688), Employment Authorization Card (INS Form I-688A), Reentry Permit (INS Form I-327), Refugee Travel Document (INS Form I-571), Employment Authorization Document issued by the INS which contains a photograph (INS Form I-688B). Send this information by email to cynthia.h.jacobsen@usace.army.mil. Foreign nationals must have received clearance prior to being granted access to the project site.


When available, the solicitation documents for this project will be available via FedBizOpps.gov https://www.fbo.gov NO CD's OR HARD COPIES WILL BE AVAILABLE. Bidders are responsible for checking the referenced page for any update(s) to the Notice. The Government is not responsible for any loss of Internet connectivity or for an offeror's inability to access the document posted at the referenced website. To obtain automatic notifications of updates to this solicitation, you MUST log in to FedBizOpps.gov and add the solicitation to your Watchlist. If you would like to list your firm so others can see you are an interested vendor, you must click the "Add Me To Interested Vendors" button in the listing for this solicitation on FedBizOpps.gov.

Update #1 ·

Added: Nov 20, 2017 12:55 pm Synopsis:

Solicitation No. W912EF18R0004 will be posted to the FBO website on or about mid to late December 2017. Solicitation is advertised as Unrestricted. The solicitation is a Request for Proposal. The proposal due date will be contained in the solicitation and any solicitation amendments that may be issued.


The construction magnitude is estimated between $1,000,000 and $5,000,000. 100% performance and payment bonds will be required. NAICS code for this project is 238210, and the small business size standard is $15,000,000 average annual receipts.


Summary of Work


Manually-operated line disconnect switches and their respective ground switches will be replaced with new motor-operated disconnect switches and new motor-operated ground switches of the same ratings. A new 125VDC circuit will be extended to each new pair of disconnect/ground switch motor operators from the main unit auxiliary panels in the generator bays. Remote control of these line disconnect switches and grounding switches will be provided in the Control Room in a new control panel.


Three sets of bus potential transformers (PT's) for the BPA lines will be replaced with new PT's of the same class and ratings, including replacing their existing wiring to the SCR boards in the Control Room.


Three sets of surge arresters for the BPA lines are to be provided and connected to the 115kV bus sections, including Contractor-designed support structures for mounting the arresters on the Transformer Deck.


Modifications must be provided to one of the 115kV bus sections involving cutting out segments of the 3" tubular aluminum bus and fitting them with straight tube-to-tube connectors for reinstallation after sectionalizing switch has been replaced. This is to provide a present and future means to isolate a switch for replacement and maintenance while leaving Line 1 and station service energized.


All new switch motor-operators are to be operable from the switch operator as well as remotely operable from a new remote control panel to be provided in the Control Room SO5 board, including indication of switch position. Ground switches and line switches will be mechanically interlocked at the switch operators and at the remote control panel to prevent accidental grounding of an energized line.


All new power and control circuits for the new switch operators will be run in a new 9" cable trough to be provided in the Cable Gallery, running from Unit 6 to the Cable Spread Room.


General Contract Requirements


Complete all on-site work within a finite work windows constrained to August 2018 through December 2018.


Important Note: The FedBizOpps Response Date listed elsewhere in this synopsis is for FedBizOpps archive purposes only. It does not necessarily reflect the actual bid opening date. The bid opening date will be contained in the solicitation and any solicitation amendments that may be issued.


A site visit will be offered approximately 2 weeks after the solicitation is made available to bidders. See solicitation for details about the site visit.


ACCESS FOR FOREIGN NATIONALS: Security clearance for foreign nationals to attend a site visit requires approximately 5 weeks; therefore, clearance should be requested immediately. To request clearance, please submit the names of all foreign nationals proposed for site visit attendance, along with documentation to verify that he/she was legally admitted into the United States and has authority to work and/or go to school in the US. Such documentation may include a US passport, Certificate of US citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), foreign passport with I-551 stamp or attached INS Form I-94 indicating employment authorization, Alien Registration Receipt Card with photograph (INS Form I-151 or I-551), Temporary Resident Card (INS Form I-688), Employment Authorization Card (INS Form I-688A), Reentry Permit (INS Form I-327), Refugee Travel Document (INS Form I-571), Employment Authorization Document issued by the INS which contains a photograph (INS Form I-688B). Send this information by email to cynthia.h.jacobsen@usace.army.mil. Foreign nationals must have received clearance prior to being granted access to the project site.


When available, the solicitation documents for this project will be available via FedBizOpps.gov https://www.fbo.gov NO CD's OR HARD COPIES WILL BE AVAILABLE. Bidders are responsible for checking the referenced page for any update(s) to the Notice. The Government is not responsible for any loss of Internet connectivity or for an offeror's inability to access the document posted at the referenced website. To obtain automatic notifications of updates to this solicitation, you MUST log in to FedBizOpps.gov and add the solicitation to your Watchlist. If you would like to list your firm so others can see you are an interested vendor, you must click the "Add Me To Interested Vendors" button in the listing for this solicitation on FedBizOpps.gov.

Attachments

Files attached to this notice, newest first
File Type Posted
33_78_00.00_26_Amend_0004.pdf PDF
W912EF18R0004_Amend_0004.pdf PDF
W912EF18R0004_Amendment_0003.pdf PDF
Amendment_0003_Revised_33_78_00.00_26.pdf PDF
W912EF18R0004_Amendment_0002.pdf PDF
TechSpec_Amend_0002_18R0004.pdf PDF
18R0004_HLD_Surge_Arrester_Amend_0001.pdf PDF
Site_Visit_Attendees.pdf PDF
W912EF18R0004_TechSpec_Solicitation.pdf PDF
Solicitation_W912EF18R0004.pdf PDF
W912EF18R0004_Plans.pdf PDF
Show all 11

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity