Repair Trail Abutments Compartment 57

Closed Solicitation Posted

Solicitation number
12445122R0007
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Huntsville, Texas 77320, United States

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

This solicitation is amended for a second time to extend the proposal due date to 04/11/2022 at 1:00 pm CDT; provide questions from prospective contractors, and the government's answers to those questions; and change the anticipated period of performance to 5/16/2022 thru 11/15/2022 (based upon NTP issue date).

Project Title: Repair Trail Abutments Compartment 57

Original Set Aside: Total Small Business Set-Aside (FAR 19.5)

NAICS Code: 237310 Highway, Street, and Bridge Construction.  

PSC Code Z2LB – Repair or Alteration of Highways/Roads/Streets/Bridges/Railways.

This is a Request for Proposal (RFP) which will result in award of a firm-fixed price contract.  Award will be made to the Lowest Priced Technically Acceptable (LPTA) source selection process considering technical qualifications, past performance, and price.

Magnitude: In accordance with FAR 36.204, the magnitude of this project is: (b) Between $25,000 and $100,000. Location:

Project Name and Location: Repair Trail Abutments Compartment 57. The project is located approximately 500 yards southeast of the 900 block of Cherry Hills Drive, Elkins Lake, on the Sam Houston National Forest, Huntsville, Texas, in Walker County. Address of the Sam Houston National Forest office is 394 FM 1375 West, New Waverly, TX 77358, phone (936) 344-6205

Scope of Work:

Reconstruct and stabilize both abutments. The Contractor shall reference the Schedule of Items, Specifications and Drawings for a complete description of work items. Work includes, but is not limited to, the following major work items: 1. Provide material, equipment, and labor to reconstruct and stabilize both abutments to the Compartment 57 Bike Trail Bridge.

Dates:  

Site Visit/Pre-Bid Conf      03/02/2022                              

Last Day for Questions     03/09/2022

Proposals Due                Updated to: 04/11/2022 – 1300 CST

Period of Performance: anticipated Updated to 05/16/2022 to 11/15/2022 (based upon NTP issue date)

FUNDING NOTICE: this project is partially funded by the Great American Outdoors Act (GAOA).

Update #2 ·

This solicitation is amended to extend the proposal due date to 04/04/2022 at 1:00 pm CDT, in order to allow more time for the government to answer the received questions from prospective contractors.

Project Title: Repair Trail Abutments Compartment 57

Original Set Aside: Total Small Business Set-Aside (FAR 19.5)

NAICS Code: 237310 Highway, Street, and Bridge Construction.  

PSC Code Z2LB – Repair or Alteration of Highways/Roads/Streets/Bridges/Railways.

This is a Request for Proposal (RFP) which will result in award of a firm-fixed price contract.  Award will be made to the Lowest Priced Technically Acceptable (LPTA) source selection process considering technical qualifications, past performance, and price.

Magnitude: In accordance with FAR 36.204, the magnitude of this project is: (b) Between $25,000 and $100,000. Location:

Project Name and Location: Repair Trail Abutments Compartment 57. The project is located approximately 500 yards southeast of the 900 block of Cherry Hills Drive, Elkins Lake, on the Sam Houston National Forest, Huntsville, Texas, in Walker County. Address of the Sam Houston National Forest office is 394 FM 1375 West, New Waverly, TX 77358, phone (936) 344-6205

Scope of Work:

Reconstruct and stabilize both abutments. The Contractor shall reference the Schedule of Items, Specifications and Drawings for a complete description of work items. Work includes, but is not limited to, the following major work items: 1. Provide material, equipment, and labor to reconstruct and stabilize both abutments to the Compartment 57 Bike Trail Bridge.

Dates:  

Site Visit/Pre-Bid Conf      03/02/2022                              

Last Day for Questions     03/09/2022

Proposals Due                Updated to: 04/04/2022 – 1300 CST

Period of Performance: anticipated 04/15/2022 to 10/14/2022 (based upon NTP issue date)

FUNDING NOTICE: this project is partially funded by the Great American Outdoors Act (GAOA).

Update #1 ·

Project Title: Repair Trail Abutments Compartment 57

Original Set Aside: Total Small Business Set-Aside (FAR 19.5)

NAICS Code: 237310 Highway, Street, and Bridge Construction.  

PSC Code Z2LB – Repair or Alteration of Highways/Roads/Streets/Bridges/Railways.

This is a Request for Proposal (RFP) which will result in award of a firm-fixed price contract.  Award will be made to the Lowest Priced Technically Acceptable (LPTA) source selection process considering technical qualifications, past performance, and price.

Magnitude: In accordance with FAR 36.204, the magnitude of this project is: (b) Between $25,000 and $100,000. Location:

Project Name and Location: Repair Trail Abutments Compartment 57. The project is located approximately 500 yards southeast of the 900 block of Cherry Hills Drive, Elkins Lake, on the Sam Houston National Forest, Huntsville, Texas, in Walker County. Address of the Sam Houston National Forest office is 394 FM 1375 West, New Waverly, TX 77358, phone (936) 344-6205

Scope of Work:

Reconstruct and stabilize both abutments. The Contractor shall reference the Schedule of Items, Specifications and Drawings for a complete description of work items. Work includes, but is not limited to, the following major work items: 1. Provide material, equipment, and labor to reconstruct and stabilize both abutments to the Compartment 57 Bike Trail Bridge.

Dates:  

Site Visit/Pre-Bid Conf      03/02/2022                              

Last Day for Questions     03/09/2022

Proposals Due                03/21/2022 – 1300 CST

Period of Performance: anticipated 04/15/2022 to 10/14/2022 (based upon NTP issue date)

FUNDING NOTICE: this project is partially funded by the Great American Outdoors Act (GAOA).

Files

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
Repair Trail Abutments Compartment 57 Original Pre-Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity