Phase 1 of Chiller Upgrade

Closed Solicitation Posted

This opportunity was awarded. See its 2 award notices in the notice history.

Solicitation number
12405B22Q0200
Agency
Southeast Area Field Research Implementation and Information Delivery, Department of Agriculture
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
238220 Plumbing, Heating, and Air-Conditioning Contractors
PSC
N041 Installation Of Equipment- Refrigeration, Air Conditioning, And Air Circulating Equipment
Place of performance
Athens, Georgia 30605, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This combined synopsis and solicitation seeks fixed-price proposals to complete Phase 1 of a chiller upgrade at the USDA Agricultural Research Service facility located in Athens, Georgia. Phase 1 involves replacing the cooling tower, condenser water piping, relocating and replacing condenser water pumps, and preparing for a future phase. Proposals are due no later than July 29, 2022 and must include a breakdown of pricing for each element as well as literature demonstrating compliance with the statement of work and specifications. Questions regarding this solicitation are due by July 22, with answers to be posted as an amendment. The anticipated award is a firm fixed-price contract.

This requirement has a total small business set-aside designation. The associated NAICS code is 238220 for plumbing, heating, and air conditioning contractors, with a small business size standard of $16.5 million. Proposals must be submitted electronically to the point of contact and are due by July 29, 2022 at 4:00 PM Central Time. The place of performance is 950 College Station Rd, Athens, Georgia 30605. Contractors must be registered in SAM.gov, including having a UEI number, to be eligible for award. The work must be completed by May 29, 2023 following a notice to proceed.

Notice text

11 versions

Update #11 · Latest ·

This solicitation has been extended until Wednesday the 10th.

Please provide any questions no later than Thursday the 4th.

Questions and Answers added as an amendment.

The Wage Determination document was not showing the actual rates. A new document that will show the rates on the wage determination has been added.

The Facility controlscompany is Automated Logic in Georgia, Good contact is Tricia Smith at 1975 Vaughn Road, Suite 100 Kennesaw, GA 30144.

A second site visit date and time have been set for Friday July 29, 2022 at 9:00 AM EST. Please ensure that you provide your attendance request with the company name and name of attendees to lynn.hults@usda.gov by the close of business Thursday 28th, 3:00 PM CST.

Extending solicitation until the 5th of Aug.

Questions & Answers

Q1:  Are the Condensing Water Pumps 50% pumps or 100% redundant?  

A1:  The final configuration after all future phases is for 100% redundant pumps with 800 ton chillers.  At the completion of phase 1, the pumps will be operating with 2 existing 400 ton chillers 50%.

Q2:  What is the allowable time frame for an electrical outage? 

A2:  All outages will be minimized and scheduled with the COR.  Total building outage for work in the main switchgear will be after hours (10pm-5am) or on weekend afternoon (after 5pm).

Q3:  What is the allowable, or preferred, time for the chilled water outage? 

A3:  Time is to minimized and scheduled with the COR.  Time of year affects the availability but during most seasons, depending on duration of the outage it will also be weekend or weekdays after 5pm.

Q4:  What are the 2 electrical boxes mounted on top of the MCC?  Are these to be relocated?

A4:  These are abandoned motor starters, no relocation required.

In accordance with FAR 28.102-1, Performance and Payment Bonds, Policy on Use, the requirement of bid guarantee for solicitation 12405B22Q0200, for Phase 1 of Upgrade Chiller in Athens, GA will be required.

In accordance with FAR 36.204 Disclosure of the Magnitude of Construction Projects, the magnitude of this contract project is between $1,000,000 and $5,000,000. 

The site visit date and time have changed. The new date and time will be Wednesday July 13, 2022 at 1:00 PM. Please ensure that you provide your attendance request with the company name and name of attendees to lynn.hults@usda.gov by the close of business the day prior.

The site visit on the 8th has been canceled due to unforeseen circumstances. A new site visit will be scheduled early next week.

A site visit has been set for this project. It will be set for Friday July 8th at 9am EST.

The site visit will be at the below location.

Provide license to the gaurd and inform them what you are there for.

Please provide me the name and company of each person you are requesting to attend this site visit at lynn.hults@usda.gov.

I will forward this list to the locations representative.

This is a Combined Synopsis/Solicitation. Solicitation Number 12405B22Q0200. The Associated NAICS code is 238220 (Plumping, Heating, and Air-Conditioning Contractors), with a small business size standard of $16.5 Million.

USDA, ARS, CGBR

950 College Station Rd

Athens, GA 30605

Needs Phase 1 of the Chiller Upgrade fits the associated Statement of Work and Specifications.

The Government anticipates award of a Firm Fixed Price contract.
Each offer must show a breakdown giving price of each element, provide descriptive literature or information showing that the offered service meets all parts of the Statement of Work and Specifications.

Electronic submissions are preferred. Please email all quotes to lynn.hults@usda.gov. NO LATE QUOTES WILL BE ACCEPTED.

To be eligible for an award, all contractors must be registered in the System for Award Management (SAM). A contractor can contact SAM by calling 1-866-606-8220 or e-mail at www.sam.gov. NO EXCEPTIONS. A UEI (Unique Entity ID) number is required in order to register. All invoices shall be submitted and paid electronically.
Quotes must be received no later than Friday July 29, 2022, 4:00pm Central Standard Time.

Questions regarding this combined synopsis/solicitation are due no later than 3:00 PM CST on Friday July 22, 2022. Answers to any questions received by that time will be posted as an amendment to this combined synopsis/solicitation.

Update #10 ·

Questions and Answers added as an amendment.

The Wage Determination document was not showing the actual rates. A new document that will show the rates on the wage determination has been added.

The Facility controlscompany is Automated Logic in Georgia, Good contact is Tricia Smith at 1975 Vaughn Road, Suite 100 Kennesaw, GA 30144.

A second site visit date and time have been set for Friday July 29, 2022 at 9:00 AM EST. Please ensure that you provide your attendance request with the company name and name of attendees to lynn.hults@usda.gov by the close of business Thursday 28th, 3:00 PM CST.

Extending solicitation until the 5th of Aug.

Questions & Answers

Q1:  Are the Condensing Water Pumps 50% pumps or 100% redundant?  

A1:  The final configuration after all future phases is for 100% redundant pumps with 800 ton chillers.  At the completion of phase 1, the pumps will be operating with 2 existing 400 ton chillers 50%.

Q2:  What is the allowable time frame for an electrical outage? 

A2:  All outages will be minimized and scheduled with the COR.  Total building outage for work in the main switchgear will be after hours (10pm-5am) or on weekend afternoon (after 5pm).

Q3:  What is the allowable, or preferred, time for the chilled water outage? 

A3:  Time is to minimized and scheduled with the COR.  Time of year affects the availability but during most seasons, depending on duration of the outage it will also be weekend or weekdays after 5pm.

Q4:  What are the 2 electrical boxes mounted on top of the MCC?  Are these to be relocated?

A4:  These are abandoned motor starters, no relocation required.

In accordance with FAR 28.102-1, Performance and Payment Bonds, Policy on Use, the requirement of bid guarantee for solicitation 12405B22Q0200, for Phase 1 of Upgrade Chiller in Athens, GA will be required.

In accordance with FAR 36.204 Disclosure of the Magnitude of Construction Projects, the magnitude of this contract project is between $1,000,000 and $5,000,000. 

The site visit date and time have changed. The new date and time will be Wednesday July 13, 2022 at 1:00 PM. Please ensure that you provide your attendance request with the company name and name of attendees to lynn.hults@usda.gov by the close of business the day prior.

The site visit on the 8th has been canceled due to unforeseen circumstances. A new site visit will be scheduled early next week.

A site visit has been set for this project. It will be set for Friday July 8th at 9am EST.

The site visit will be at the below location.

Provide license to the gaurd and inform them what you are there for.

Please provide me the name and company of each person you are requesting to attend this site visit at lynn.hults@usda.gov.

I will forward this list to the locations representative.

This is a Combined Synopsis/Solicitation. Solicitation Number 12405B22Q0200. The Associated NAICS code is 238220 (Plumping, Heating, and Air-Conditioning Contractors), with a small business size standard of $16.5 Million.

USDA, ARS, CGBR

950 College Station Rd

Athens, GA 30605

Needs Phase 1 of the Chiller Upgrade fits the associated Statement of Work and Specifications.

The Government anticipates award of a Firm Fixed Price contract.
Each offer must show a breakdown giving price of each element, provide descriptive literature or information showing that the offered service meets all parts of the Statement of Work and Specifications.

Electronic submissions are preferred. Please email all quotes to lynn.hults@usda.gov. NO LATE QUOTES WILL BE ACCEPTED.

To be eligible for an award, all contractors must be registered in the System for Award Management (SAM). A contractor can contact SAM by calling 1-866-606-8220 or e-mail at www.sam.gov. NO EXCEPTIONS. A UEI (Unique Entity ID) number is required in order to register. All invoices shall be submitted and paid electronically.
Quotes must be received no later than Friday July 29, 2022, 4:00pm Central Standard Time.

Questions regarding this combined synopsis/solicitation are due no later than 3:00 PM CST on Friday July 22, 2022. Answers to any questions received by that time will be posted as an amendment to this combined synopsis/solicitation.

Update #9 ·

The Wage Determination document was not showing the actual rates. A new document that will show the rates on the wage determination has been added.

The Facility controlscompany is Automated Logic in Georgia, Good contact is Tricia Smith at 1975 Vaughn Road, Suite 100 Kennesaw, GA 30144.

A second site visit date and time have been set for Friday July 29, 2022 at 9:00 AM EST. Please ensure that you provide your attendance request with the company name and name of attendees to lynn.hults@usda.gov by the close of business Thursday 28th, 3:00 PM CST.

Extending solicitation until the 5th of Aug.

Questions & Answers

Q1:  Are the Condensing Water Pumps 50% pumps or 100% redundant?  

A1:  The final configuration after all future phases is for 100% redundant pumps with 800 ton chillers.  At the completion of phase 1, the pumps will be operating with 2 existing 400 ton chillers 50%.

Q2:  What is the allowable time frame for an electrical outage? 

A2:  All outages will be minimized and scheduled with the COR.  Total building outage for work in the main switchgear will be after hours (10pm-5am) or on weekend afternoon (after 5pm).

Q3:  What is the allowable, or preferred, time for the chilled water outage? 

A3:  Time is to minimized and scheduled with the COR.  Time of year affects the availability but during most seasons, depending on duration of the outage it will also be weekend or weekdays after 5pm.

Q4:  What are the 2 electrical boxes mounted on top of the MCC?  Are these to be relocated?

A4:  These are abandoned motor starters, no relocation required.

In accordance with FAR 28.102-1, Performance and Payment Bonds, Policy on Use, the requirement of bid guarantee for solicitation 12405B22Q0200, for Phase 1 of Upgrade Chiller in Athens, GA will be required.

In accordance with FAR 36.204 Disclosure of the Magnitude of Construction Projects, the magnitude of this contract project is between $1,000,000 and $5,000,000. 

The site visit date and time have changed. The new date and time will be Wednesday July 13, 2022 at 1:00 PM. Please ensure that you provide your attendance request with the company name and name of attendees to lynn.hults@usda.gov by the close of business the day prior.

The site visit on the 8th has been canceled due to unforeseen circumstances. A new site visit will be scheduled early next week.

A site visit has been set for this project. It will be set for Friday July 8th at 9am EST.

The site visit will be at the below location.

Provide license to the gaurd and inform them what you are there for.

Please provide me the name and company of each person you are requesting to attend this site visit at lynn.hults@usda.gov.

I will forward this list to the locations representative.

This is a Combined Synopsis/Solicitation. Solicitation Number 12405B22Q0200. The Associated NAICS code is 238220 (Plumping, Heating, and Air-Conditioning Contractors), with a small business size standard of $16.5 Million.

USDA, ARS, CGBR

950 College Station Rd

Athens, GA 30605

Needs Phase 1 of the Chiller Upgrade fits the associated Statement of Work and Specifications.

The Government anticipates award of a Firm Fixed Price contract.
Each offer must show a breakdown giving price of each element, provide descriptive literature or information showing that the offered service meets all parts of the Statement of Work and Specifications.

Electronic submissions are preferred. Please email all quotes to lynn.hults@usda.gov. NO LATE QUOTES WILL BE ACCEPTED.

To be eligible for an award, all contractors must be registered in the System for Award Management (SAM). A contractor can contact SAM by calling 1-866-606-8220 or e-mail at www.sam.gov. NO EXCEPTIONS. A UEI (Unique Entity ID) number is required in order to register. All invoices shall be submitted and paid electronically.
Quotes must be received no later than Friday July 29, 2022, 4:00pm Central Standard Time.

Questions regarding this combined synopsis/solicitation are due no later than 3:00 PM CST on Friday July 22, 2022. Answers to any questions received by that time will be posted as an amendment to this combined synopsis/solicitation.

Update #8 ·

The Facility controlscompany is Automated Logic in Georgia, Good contact is Tricia Smith at 1975 Vaughn Road, Suite 100 Kennesaw, GA 30144.

A second site visit date and time have been set for Friday July 29, 2022 at 9:00 AM EST. Please ensure that you provide your attendance request with the company name and name of attendees to lynn.hults@usda.gov by the close of business Thursday 28th, 3:00 PM CST.

Extending solicitation until the 5th of Aug.

Questions & Answers

Q1:  Are the Condensing Water Pumps 50% pumps or 100% redundant?  

A1:  The final configuration after all future phases is for 100% redundant pumps with 800 ton chillers.  At the completion of phase 1, the pumps will be operating with 2 existing 400 ton chillers 50%.

Q2:  What is the allowable time frame for an electrical outage? 

A2:  All outages will be minimized and scheduled with the COR.  Total building outage for work in the main switchgear will be after hours (10pm-5am) or on weekend afternoon (after 5pm).

Q3:  What is the allowable, or preferred, time for the chilled water outage? 

A3:  Time is to minimized and scheduled with the COR.  Time of year affects the availability but during most seasons, depending on duration of the outage it will also be weekend or weekdays after 5pm.

Q4:  What are the 2 electrical boxes mounted on top of the MCC?  Are these to be relocated?

A4:  These are abandoned motor starters, no relocation required.

In accordance with FAR 28.102-1, Performance and Payment Bonds, Policy on Use, the requirement of bid guarantee for solicitation 12405B22Q0200, for Phase 1 of Upgrade Chiller in Athens, GA will be required.

In accordance with FAR 36.204 Disclosure of the Magnitude of Construction Projects, the magnitude of this contract project is between $1,000,000 and $5,000,000. 

The site visit date and time have changed. The new date and time will be Wednesday July 13, 2022 at 1:00 PM. Please ensure that you provide your attendance request with the company name and name of attendees to lynn.hults@usda.gov by the close of business the day prior.

The site visit on the 8th has been canceled due to unforeseen circumstances. A new site visit will be scheduled early next week.

A site visit has been set for this project. It will be set for Friday July 8th at 9am EST.

The site visit will be at the below location.

Provide license to the gaurd and inform them what you are there for.

Please provide me the name and company of each person you are requesting to attend this site visit at lynn.hults@usda.gov.

I will forward this list to the locations representative.

This is a Combined Synopsis/Solicitation. Solicitation Number 12405B22Q0200. The Associated NAICS code is 238220 (Plumping, Heating, and Air-Conditioning Contractors), with a small business size standard of $16.5 Million.

USDA, ARS, CGBR

950 College Station Rd

Athens, GA 30605

Needs Phase 1 of the Chiller Upgrade fits the associated Statement of Work and Specifications.

The Government anticipates award of a Firm Fixed Price contract.
Each offer must show a breakdown giving price of each element, provide descriptive literature or information showing that the offered service meets all parts of the Statement of Work and Specifications.

Electronic submissions are preferred. Please email all quotes to lynn.hults@usda.gov. NO LATE QUOTES WILL BE ACCEPTED.

To be eligible for an award, all contractors must be registered in the System for Award Management (SAM). A contractor can contact SAM by calling 1-866-606-8220 or e-mail at www.sam.gov. NO EXCEPTIONS. A UEI (Unique Entity ID) number is required in order to register. All invoices shall be submitted and paid electronically.
Quotes must be received no later than Friday July 29, 2022, 4:00pm Central Standard Time.

Questions regarding this combined synopsis/solicitation are due no later than 3:00 PM CST on Friday July 22, 2022. Answers to any questions received by that time will be posted as an amendment to this combined synopsis/solicitation.

Update #7 ·

A second site visit date and time have been set for Friday July 29, 2022 at 9:00 AM EST. Please ensure that you provide your attendance request with the company name and name of attendees to lynn.hults@usda.gov by the close of business Thursday 28th, 3:00 PM CST.

Extending solicitation until the 5th of Aug.

Questions & Answers

Q1:  Are the Condensing Water Pumps 50% pumps or 100% redundant?  

A1:  The final configuration after all future phases is for 100% redundant pumps with 800 ton chillers.  At the completion of phase 1, the pumps will be operating with 2 existing 400 ton chillers 50%.

Q2:  What is the allowable time frame for an electrical outage? 

A2:  All outages will be minimized and scheduled with the COR.  Total building outage for work in the main switchgear will be after hours (10pm-5am) or on weekend afternoon (after 5pm).

Q3:  What is the allowable, or preferred, time for the chilled water outage? 

A3:  Time is to minimized and scheduled with the COR.  Time of year affects the availability but during most seasons, depending on duration of the outage it will also be weekend or weekdays after 5pm.

Q4:  What are the 2 electrical boxes mounted on top of the MCC?  Are these to be relocated?

A4:  These are abandoned motor starters, no relocation required.

In accordance with FAR 28.102-1, Performance and Payment Bonds, Policy on Use, the requirement of bid guarantee for solicitation 12405B22Q0200, for Phase 1 of Upgrade Chiller in Athens, GA will be required.

In accordance with FAR 36.204 Disclosure of the Magnitude of Construction Projects, the magnitude of this contract project is between $1,000,000 and $5,000,000. 

The site visit date and time have changed. The new date and time will be Wednesday July 13, 2022 at 1:00 PM. Please ensure that you provide your attendance request with the company name and name of attendees to lynn.hults@usda.gov by the close of business the day prior.

The site visit on the 8th has been canceled due to unforeseen circumstances. A new site visit will be scheduled early next week.

A site visit has been set for this project. It will be set for Friday July 8th at 9am EST.

The site visit will be at the below location.

Provide license to the gaurd and inform them what you are there for.

Please provide me the name and company of each person you are requesting to attend this site visit at lynn.hults@usda.gov.

I will forward this list to the locations representative.

This is a Combined Synopsis/Solicitation. Solicitation Number 12405B22Q0200. The Associated NAICS code is 238220 (Plumping, Heating, and Air-Conditioning Contractors), with a small business size standard of $16.5 Million.

USDA, ARS, CGBR

950 College Station Rd

Athens, GA 30605

Needs Phase 1 of the Chiller Upgrade fits the associated Statement of Work and Specifications.

The Government anticipates award of a Firm Fixed Price contract.
Each offer must show a breakdown giving price of each element, provide descriptive literature or information showing that the offered service meets all parts of the Statement of Work and Specifications.

Electronic submissions are preferred. Please email all quotes to lynn.hults@usda.gov. NO LATE QUOTES WILL BE ACCEPTED.

To be eligible for an award, all contractors must be registered in the System for Award Management (SAM). A contractor can contact SAM by calling 1-866-606-8220 or e-mail at www.sam.gov. NO EXCEPTIONS. A UEI (Unique Entity ID) number is required in order to register. All invoices shall be submitted and paid electronically.
Quotes must be received no later than Friday July 29, 2022, 4:00pm Central Standard Time.

Questions regarding this combined synopsis/solicitation are due no later than 3:00 PM CST on Friday July 22, 2022. Answers to any questions received by that time will be posted as an amendment to this combined synopsis/solicitation.

Update #6 ·

Extending solicitation until the 5th of Aug.

Questions & Answers

Q1:  Are the Condensing Water Pumps 50% pumps or 100% redundant?  

A1:  The final configuration after all future phases is for 100% redundant pumps with 800 ton chillers.  At the completion of phase 1, the pumps will be operating with 2 existing 400 ton chillers 50%.

Q2:  What is the allowable time frame for an electrical outage? 

A2:  All outages will be minimized and scheduled with the COR.  Total building outage for work in the main switchgear will be after hours (10pm-5am) or on weekend afternoon (after 5pm).

Q3:  What is the allowable, or preferred, time for the chilled water outage? 

A3:  Time is to minimized and scheduled with the COR.  Time of year affects the availability but during most seasons, depending on duration of the outage it will also be weekend or weekdays after 5pm.

Q4:  What are the 2 electrical boxes mounted on top of the MCC?  Are these to be relocated?

A4:  These are abandoned motor starters, no relocation required.

In accordance with FAR 28.102-1, Performance and Payment Bonds, Policy on Use, the requirement of bid guarantee for solicitation 12405B22Q0200, for Phase 1 of Upgrade Chiller in Athens, GA will be required.

In accordance with FAR 36.204 Disclosure of the Magnitude of Construction Projects, the magnitude of this contract project is between $1,000,000 and $5,000,000. 

The site visit date and time have changed. The new date and time will be Wednesday July 13, 2022 at 1:00 PM. Please ensure that you provide your attendance request with the company name and name of attendees to lynn.hults@usda.gov by the close of business the day prior.

The site visit on the 8th has been canceled due to unforeseen circumstances. A new site visit will be scheduled early next week.

A site visit has been set for this project. It will be set for Friday July 8th at 9am EST.

The site visit will be at the below location.

Provide license to the gaurd and inform them what you are there for.

Please provide me the name and company of each person you are requesting to attend this site visit at lynn.hults@usda.gov.

I will forward this list to the locations representative.

This is a Combined Synopsis/Solicitation. Solicitation Number 12405B22Q0200. The Associated NAICS code is 238220 (Plumping, Heating, and Air-Conditioning Contractors), with a small business size standard of $16.5 Million.

USDA, ARS, CGBR

950 College Station Rd

Athens, GA 30605

Needs Phase 1 of the Chiller Upgrade fits the associated Statement of Work and Specifications.

The Government anticipates award of a Firm Fixed Price contract.
Each offer must show a breakdown giving price of each element, provide descriptive literature or information showing that the offered service meets all parts of the Statement of Work and Specifications.

Electronic submissions are preferred. Please email all quotes to lynn.hults@usda.gov. NO LATE QUOTES WILL BE ACCEPTED.

To be eligible for an award, all contractors must be registered in the System for Award Management (SAM). A contractor can contact SAM by calling 1-866-606-8220 or e-mail at www.sam.gov. NO EXCEPTIONS. A UEI (Unique Entity ID) number is required in order to register. All invoices shall be submitted and paid electronically.
Quotes must be received no later than Friday July 29, 2022, 4:00pm Central Standard Time.

Questions regarding this combined synopsis/solicitation are due no later than 3:00 PM CST on Friday July 22, 2022. Answers to any questions received by that time will be posted as an amendment to this combined synopsis/solicitation.

Update #5 ·

In accordance with FAR 28.102-1, Performance and Payment Bonds, Policy on Use, the requirement of bid guarantee for solicitation 12405B22Q0200, for Phase 1 of Upgrade Chiller in Athens, GA will be required.

In accordance with FAR 36.204 Disclosure of the Magnitude of Construction Projects, the magnitude of this contract project is between $1,000,000 and $5,000,000. 

The site visit date and time have changed. The new date and time will be Wednesday July 13, 2022 at 1:00 PM. Please ensure that you provide your attendance request with the company name and name of attendees to lynn.hults@usda.gov by the close of business the day prior.

The site visit on the 8th has been canceled due to unforeseen circumstances. A new site visit will be scheduled early next week.

A site visit has been set for this project. It will be set for Friday July 8th at 9am EST.

The site visit will be at the below location.

Provide license to the gaurd and inform them what you are there for.

Please provide me the name and company of each person you are requesting to attend this site visit at lynn.hults@usda.gov.

I will forward this list to the locations representative.

This is a Combined Synopsis/Solicitation. Solicitation Number 12405B22Q0200. The Associated NAICS code is 238220 (Plumping, Heating, and Air-Conditioning Contractors), with a small business size standard of $16.5 Million.

USDA, ARS, CGBR

950 College Station Rd

Athens, GA 30605

Needs Phase 1 of the Chiller Upgrade fits the associated Statement of Work and Specifications.

The Government anticipates award of a Firm Fixed Price contract.
Each offer must show a breakdown giving price of each element, provide descriptive literature or information showing that the offered service meets all parts of the Statement of Work and Specifications.

Electronic submissions are preferred. Please email all quotes to lynn.hults@usda.gov. NO LATE QUOTES WILL BE ACCEPTED.

To be eligible for an award, all contractors must be registered in the System for Award Management (SAM). A contractor can contact SAM by calling 1-866-606-8220 or e-mail at www.sam.gov. NO EXCEPTIONS. A UEI (Unique Entity ID) number is required in order to register. All invoices shall be submitted and paid electronically.
Quotes must be received no later than Friday July 29, 2022, 4:00pm Central Standard Time.

Questions regarding this combined synopsis/solicitation are due no later than 3:00 PM CST on Friday July 22, 2022. Answers to any questions received by that time will be posted as an amendment to this combined synopsis/solicitation.

Update #4 ·

The site visit date and time have changed. The new date and time will be Wednesday July 13, 2022 at 1:00 PM. Please ensure that you provide your attendance request with the company name and name of attendees to lynn.hults@usda.gov by the close of business the day prior.

The site visit on the 8th has been canceled due to unforeseen circumstances. A new site visit will be scheduled early next week.

A site visit has been set for this project. It will be set for Friday July 8th at 9am EST.

The site visit will be at the below location.

Provide license to the gaurd and inform them what you are there for.

Please provide me the name and company of each person you are requesting to attend this site visit at lynn.hults@usda.gov.

I will forward this list to the locations representative.

This is a Combined Synopsis/Solicitation. Solicitation Number 12405B22Q0200. The Associated NAICS code is 238220 (Plumping, Heating, and Air-Conditioning Contractors), with a small business size standard of $16.5 Million.

USDA, ARS, CGBR

950 College Station Rd

Athens, GA 30605

Needs Phase 1 of the Chiller Upgrade fits the associated Statement of Work and Specifications.

The Government anticipates award of a Firm Fixed Price contract.
Each offer must show a breakdown giving price of each element, provide descriptive literature or information showing that the offered service meets all parts of the Statement of Work and Specifications.

Electronic submissions are preferred. Please email all quotes to lynn.hults@usda.gov. NO LATE QUOTES WILL BE ACCEPTED.

To be eligible for an award, all contractors must be registered in the System for Award Management (SAM). A contractor can contact SAM by calling 1-866-606-8220 or e-mail at www.sam.gov. NO EXCEPTIONS. A UEI (Unique Entity ID) number is required in order to register. All invoices shall be submitted and paid electronically.
Quotes must be received no later than Friday July 29, 2022, 4:00pm Central Standard Time.

Questions regarding this combined synopsis/solicitation are due no later than 3:00 PM CST on Friday July 22, 2022. Answers to any questions received by that time will be posted as an amendment to this combined synopsis/solicitation.

Update #3 ·

The site visit on the 8th has been canceled due to unforeseen circumstances. A new site visit will be scheduled early next week.

A site visit has been set for this project. It will be set for Friday July 8th at 9am EST.

The site visit will be at the below location.

Provide license to the gaurd and inform them what you are there for.

Please provide me the name and company of each person you are requesting to attend this site visit at lynn.hults@usda.gov.

I will forward this list to the locations representative.

This is a Combined Synopsis/Solicitation. Solicitation Number 12405B22Q0200. The Associated NAICS code is 238220 (Plumping, Heating, and Air-Conditioning Contractors), with a small business size standard of $16.5 Million.

USDA, ARS, CGBR

950 College Station Rd

Athens, GA 30605

Needs Phase 1 of the Chiller Upgrade fits the associated Statement of Work and Specifications.

The Government anticipates award of a Firm Fixed Price contract.
Each offer must show a breakdown giving price of each element, provide descriptive literature or information showing that the offered service meets all parts of the Statement of Work and Specifications.

Electronic submissions are preferred. Please email all quotes to lynn.hults@usda.gov. NO LATE QUOTES WILL BE ACCEPTED.

To be eligible for an award, all contractors must be registered in the System for Award Management (SAM). A contractor can contact SAM by calling 1-866-606-8220 or e-mail at www.sam.gov. NO EXCEPTIONS. A UEI (Unique Entity ID) number is required in order to register. All invoices shall be submitted and paid electronically.
Quotes must be received no later than Friday July 29, 2022, 4:00pm Central Standard Time.

Questions regarding this combined synopsis/solicitation are due no later than 3:00 PM CST on Friday July 22, 2022. Answers to any questions received by that time will be posted as an amendment to this combined synopsis/solicitation.

Update #2 ·

A site visit has been set for this project. It will be set for Friday July 8th at 9am EST.

The site visit will be at the below location.

Provide license to the gaurd and inform them what you are there for.

Please provide me the name and company of each person you are requesting to attend this site visit at lynn.hults@usda.gov.

I will forward this list to the locations representative.

This is a Combined Synopsis/Solicitation. Solicitation Number 12405B22Q0200. The Associated NAICS code is 238220 (Plumping, Heating, and Air-Conditioning Contractors), with a small business size standard of $16.5 Million.

USDA, ARS, CGBR

950 College Station Rd

Athens, GA 30605

Needs Phase 1 of the Chiller Upgrade fits the associated Statement of Work and Specifications.

The Government anticipates award of a Firm Fixed Price contract.
Each offer must show a breakdown giving price of each element, provide descriptive literature or information showing that the offered service meets all parts of the Statement of Work and Specifications.

Electronic submissions are preferred. Please email all quotes to lynn.hults@usda.gov. NO LATE QUOTES WILL BE ACCEPTED.

To be eligible for an award, all contractors must be registered in the System for Award Management (SAM). A contractor can contact SAM by calling 1-866-606-8220 or e-mail at www.sam.gov. NO EXCEPTIONS. A UEI (Unique Entity ID) number is required in order to register. All invoices shall be submitted and paid electronically.
Quotes must be received no later than Friday July 29, 2022, 4:00pm Central Standard Time.

Questions regarding this combined synopsis/solicitation are due no later than 3:00 PM CST on Friday July 22, 2022. Answers to any questions received by that time will be posted as an amendment to this combined synopsis/solicitation.

Update #1 ·

This is a Combined Synopsis/Solicitation. Solicitation Number 12405B22Q0200. The Associated NAICS code is 238220 (Plumping, Heating, and Air-Conditioning Contractors), with a small business size standard of $16.5 Million.

USDA, ARS, CGBR

950 College Station Rd

Athens, GA 30605

Needs Phase 1 of the Chiller Upgrade fits the associated Statement of Work and Specifications.

The Government anticipates award of a Firm Fixed Price contract.
Each offer must show a breakdown giving price of each element, provide descriptive literature or information showing that the offered service meets all parts of the Statement of Work and Specifications.

Electronic submissions are preferred. Please email all quotes to lynn.hults@usda.gov. NO LATE QUOTES WILL BE ACCEPTED.

To be eligible for an award, all contractors must be registered in the System for Award Management (SAM). A contractor can contact SAM by calling 1-866-606-8220 or e-mail at www.sam.gov. NO EXCEPTIONS. A UEI (Unique Entity ID) number is required in order to register. All invoices shall be submitted and paid electronically.
Quotes must be received no later than Friday July 29, 2022, 4:00pm Central Standard Time.

Questions regarding this combined synopsis/solicitation are due no later than 3:00 PM CST on Friday July 22, 2022. Answers to any questions received by that time will be posted as an amendment to this combined synopsis/solicitation.

Attachments

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Phase 1 of Chiller Upgrade Latest Award Notice
Phase 1 of Chiller Upgrade Award Notice
Phase 1 of Chiller Upgrade This notice · Latest solicitation Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity