OK ERFO SEQU T500(1)Horton Slough Trail
Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- 6982AF21B000012
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Not on record
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Stigler Ok Usa
Notice details come from SAM.gov. Updated .
About this opportunity
This pre-solicitation notice is for the OK ERFO SEQU T500(1) Horton Slough Trail project. The Department of Transportation Federal Highway Administration will procure construction services to repair three sites in the Sequoyah National Wildlife Refuge damaged in 2019 flooding. Improvements include clearing, grubbing, construction of a pedestrian bridge, trail, observation deck, and pavement patching. The agency will evaluate proposals based on technical qualifications and past performance completing similar infrastructure projects. It is anticipated the solicitation will be issued in May 2021 with construction running from June 2021 to August 2022.
The opportunity is set aside for total small businesses. Significant construction elements include 250 cubic yards of embankment, 425 cubic yards of riprap, 120 tons of asphalt pavement, 30 cubic yards of structural concrete, 2150 pounds of structural steel, one pre-fabricated steel bridge, and 18 helical piles. The estimated value ranges from $1,000,000 to $1,500,000.
Notice text
THIS IS NOT A SOLICITATION
PLANS AND SPECIFICATIONS ARE NOT AVAILABLE AT THIS TIME
OK ERFO SEQU T500(1) Horton Slough Trail
PROJECT DESCRIPTION: The project is located in the Sequoyah National Wildlife Refuge, which is 5 miles south of Vian, Oklahoma in Sequoyah County. The project will provide repairs to three sites throughout the refuge damaged in a 2019 flood events. Construction improvements include clearing and grubbing, pedestrian bridge construction, trail construction, observation deck construction and pavement patching.
Significant quantities:
Line Item Unit Est. Quantity
Embankment Construction CUYD 250
Riprap CUYD 425
Asphalt Concrete Pavement TON 120
Structural Concrete CUYD 30
Structural Steel, Furnished, Fabricated and Erected LB 2150
Pre-fabricated Steel Bridge LPSM 1
Helical Pile, In Place Each 18
It is anticipated that this project will be advertised in May 2021. Construction is anticipated from June 2021 to August 2022. Estimated total cost is $1,000,000 to $1,500,000.
Notice history
| Notice | Type | Posted |
|---|---|---|
| OK ERFO SEQU T500(1)Horton Slough Trail | Award Notice | |
| OK ERFO SEQU T500(1)Horton Slough Trail | Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| OK FW TSM 10(1) NFH Entrance Road and Parking Improvements | Federal Highway Administration | Total Small Business | |
| Northeast Region Pavement and Bridge Preservation Construction - NP NER PMS BMS FY24(1) | Federal Highway Administration | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity