Nez Perce-Clearwater NFs - Soda Creek Culvert Replacements

Award Notice Posted

Solicitation number
AG-02RC-S-15-0074
Agency
Awarded
to Stone Ridge Construction, Inc.
Set-aside
Total Small Business

Opportunity facts

Contract number
AG-02RC-C-15-0018 Federal contract award
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Not on record
Place of performance
Red River Ranger District 300 American River Road Elk City, Idaho 83525, United States

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

Contract was awarded on 6/18/2015.

Update #2 ·

This project is being performed on the Red River Ranger District of the Nez Perce-Clearwater National Forests in collaboration with the Nez Perce Tribe Watershed program. Two corrugated steel pipes shall be removed and replaced with steel pipe-arches. The two project sites are located on the same road approximately 0.1 mile apart.

Soda Creek M.P. 3.4 AOP Culvert Replacement: This project is located National Forest System Road No. 1172 at Mile Post 3.4 in Section 31, T. 28 N., R. 10 E., Idaho County, Idaho. This project is for the removal of a 48" corrugated steel pipe on a tributary to Soda Creek and replacing it with a 128" Span x 83" rise corrugated steel pipe-arch, 0.138" thickness and approximately 68' long. The work includes but is not limited to clearing and grubbing, erosion control measures, structure excavation, roadway embankment, removing and disposing an existing culvert, compaction, riprap, roadway surfacing, furnishing and installing a corrugated steel pipe-arch culvert, and all other incidental items necessary to complete the project in accordance with the plans and specifications.


Soda Creek M.P. 3.5 AOP Culvert Replacement: This project is located on National Forest System Road No. 1172 at Mile Post 3.5 in Section 31, T. 28 N., R. 10 E., Idaho County, Idaho. This project is for the removal of a 48" corrugated steel pipe on an unnamed tributary to Soda Creek and replacing it with a 103" span by 71" rise corrugated steel pipe-arch, 0.109" thickness and approximately 74' in length. The work includes but is not limited to clearing and grubbing, erosion control measures, structure excavation, roadway embankment, removing and disposing an existing culvert, compaction, riprap, roadway surfacing, furnishing and installing a corrugated steel culvert, and all other incidental items necessary to complete the project in accordance with the plans and specifications.


Contractors should take note that the site of work for this project is very remote with a drive time from Grangeville, ID of approximately 2-2.5 hours.  Please see L-11 Site Visit for additional details regarding the limited services available.

The Government's construction estimate is between $100,000-$250,000. A formal pre-bid tour is not planned. Construction work on the project shall commence no earlier than July 1, 2015 and be completed by September 15th, 2015. All in-stream work must take place between July 15th and August 30th.


Original bid bonds are required if the total value offered exceeds $150,000. The acquisition has been set-aside for small businesses.  Solicitation issued on 5/15/15. 

Update #1 ·

This project is being performed on the Red River Ranger District of the Nez Perce-Clearwater National Forests in collaboration with the Nez Perce Tribe Watershed program. Two corrugated steel pipes shall be removed and replaced with steel pipe-arches. The two project sites are located on the same road approximately 0.1 mile apart.

Soda Creek M.P. 3.4 AOP Culvert Replacement: This project is located National Forest System Road No. 1172 at Mile Post 3.4 in Section 31, T. 28 N., R. 10 E., Idaho County, Idaho. This project is for the removal of a 48" corrugated steel pipe on a tributary to Soda Creek and replacing it with a 128" Span x 83" rise corrugated steel pipe-arch, 0.138" thickness and approximately 68' long. The work includes but is not limited to clearing and grubbing, erosion control measures, structure excavation, roadway embankment, removing and disposing an existing culvert, compaction, riprap, roadway surfacing, furnishing and installing a corrugated steel pipe-arch culvert, and all other incidental items necessary to complete the project in accordance with the plans and specifications.


Soda Creek M.P. 3.5 AOP Culvert Replacement: This project is located on National Forest System Road No. 1172 at Mile Post 3.5 in Section 31, T. 28 N., R. 10 E., Idaho County, Idaho. This project is for the removal of a 48" corrugated steel pipe on an unnamed tributary to Soda Creek and replacing it with a 103" span by 71" rise corrugated steel pipe-arch, 0.109" thickness and approximately 74' in length. The work includes but is not limited to clearing and grubbing, erosion control measures, structure excavation, roadway embankment, removing and disposing an existing culvert, compaction, riprap, roadway surfacing, furnishing and installing a corrugated steel culvert, and all other incidental items necessary to complete the project in accordance with the plans and specifications.


The Government's construction estimate is between $100,000-$250,000. A formal pre-bid tour is not planned. Construction work on the project shall commence no earlier than July 1, 2015 and be completed by September 15th, 2015. All in-stream work must take place between July 15th and August 30th.


Original bid bonds are required if the total value offered exceeds $150,000. The acquisition has been set-aside for small businesses.

Files

File Type Posted
Amend1MP3.4PipeThickness.doc DOC document
Soda_Trib_1172-3.5_PLANS.pdf PDF
SignedCoversheetsSodaCreek3.4and3.5.pdf PDF
Soda_Trib_1172-3.5_FSSS.pdf PDF
Soda_Trib_1172-3.4_FSSS.pdf PDF
SODA_TRIB_1172-3.4_PLANS.pdf PDF
SodaConRFPdocx.docx DOCX document

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity