Kincaid Campground Paving

Award Notice Posted

Solicitation number
127K1118Q0008
Agency
Awarded
to T.l. Construction, L.l.c
Set-aside
Total Small Business

Opportunity facts

Contract number
127K1118C0008 Federal contract award
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
Kincaid Lake Recreation Area Campground Boyce, Louisiana, United States

Notice details come from SAM.gov. Updated .

Notice text

5 versions

Update #5 · Latest ·

Awarded Vendors: T.L. Construction Inc. Contract Award Dollar Amount: Base bid $73,910.00. Contract Award Date: 2018-08-22.

Update #4 ·

Two additional questions have been received:
1) Could an 8 inch hot mix patch be used in lieu of the 12 inches of 6/10 road base for pothole repair?
A: Yes, an 8" hot mix patch would be an acceptable alternative.
2. Is there an area on site, to place spoils? ie; material removed for pothole patching and all roadside prep where asphalt has broken off or grass and dirt may need to be removed.
A: The spoils can be disposed of on a government road within one mile of the paving project.
This constitutes Amendment 002 to the solicitation; an SF 30 will not be issued. The response date remains 8/20/18..

Update #3 ·

Kincaid Loop Site Visit Notes
Site visit was held at 10AM on July 24, 2018; Forest Service represented by Blake Prevott, COR.
Four contractors were in attendance:
• Terry Westwood (318) 452-1196 tlwestco@westco-contracting.com
• Phil Cardy (337) 378-2086 pcardy@dotconstructioninc.com
• Brandon Vercher, DCMS (225) 278-6184 bvercher@localconstruction.com
• Rocky Bloodsworth (318) 446-3858 (could not read email address)
There were two questions asked:
1) Why is the unit of measure square yards instead of tons?
A: Both are "standard" measures; square yards was chosen because it better quantifies the requirement.


2) Is there any stripe painting required?
A. No, there isn't any painting required.
This constitutes Amendment 001 to the solicitation; an SF 30 will not be issued. The response date remains 8/20/18.

.

Update #2 ·

THE PROJECT SOLICITATION HAS BEEN POSTED..

Update #1 ·

The Kisatchie National Forest has a requirement to repair and repave several asphalt roads in the Kincaid Lake Recreation Area campground as detailed in the Request for Quotes.
The USDA Forest Service encourages the participation of small, disadvantaged, service disabled veteran, and women owned business enterprises. The North American Industry Classification System (NAICS) code is 237310 and the small business size standard is $36.5 million.
The Government estimate for this project is between $100,000 and $250,000.
The proposed contract is 100% set-aside for small business concerns. All responsible, qualified small businesses may submit an offer which will be considered by the Forest Service. All Offerors shall be registered at the System for Award Management (www.sam.gov) to be eligible for award.
The solicitation for this project will be available only through the Federal Business Opportunities website www.fbo.gov.
All questions pertaining to this solicitation must be submitted in writing to Jay Tobin at jtobin@fs.fed.us.
The anticipated date for issuance of the solicitation is on or about July 20, 2018. The actual due date for proposals will be identified on the solicitation.
A pre-proposal site visit will be held at 10:00 AM on Tuesday, July 24, 2018. Plan to meet at the recreation area entrance off FSR 205 and convoy to the campground from there..

Files

File Type Posted
2018-06-25_SOW_PAVING_rev.pdf PDF
SOL__127K1118Q0008.pdf PDF
DBWD_LA17.pdf PDF

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity