J059--Switchgear Maintenance & Testing RFQ

Closed Solicitation Posted

Solicitation number
36C25023Q0725
Agency
Veterans Integrated Service Network 10 Veterans Health Administration, Department of Veterans Affairs
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
811210 Electronic and Precision Equipment Repair and Maintenance
PSC
J059 Maint/Repair/Rebuild Of Equipment- Electrical And Electronic Equipment Components
Place of performance
Detroit VA Medical Center 4646 John R. Street This Rfq Is Strictly Prohibited Usa

Notice details come from SAM.gov. Updated .

Notice text

4 versions

Update #4 · Latest ·

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the

offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY

is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not,

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter

or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to

the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print)

(Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign)

(Signature of Contracting Officer)

1

1

0003

None

36C250

Department of Veterans Affairs

Ann Arbor Healthcare System

Network Contracting Office 10

2215 Fuller Road

Ann Arbor, MI 48105

36C250

Department of Veterans Affairs

Ann Arbor Healthcare System

Network Contracting Office 10

2215 Fuller Road

Ann Arbor, MI 48105

To all Offerors/Bidders

36C25023Q0725

06-23-2023

X

X

X

1

RFQ close date is extended to 06/27/2023 @ 10:00 AM

See CONTINUATION Page

X

1

1. This amendment is to remove two sections from the Statement of Work (SOW).

a. Section C. Generator Control Panel SPB-100 Breakers Qty. 8 is hereby removed from the SOW

b. Section D. Generator Control Panel 480V MCCB Breakers Qty. 33 is hereby removed from the SOW

2. An updated SOW is included herein - please use this updated SOW in any offer submitted.

3. No other changes to the solicitation are made as a result of this amendment.

Jennifer A. Johnson

Contracting Officer

Page 6 of 6

A.1 STATEMENT OF WORK

Scope of Work

Furnish all necessary labor, tools, materials, parts, equipment, and supervision to complete the

Switchgear Testing and Maintenance Project, at the John D. Dingell VA Medical Center, 4646 John R. St, Detroit, Michigan (VAMC). All work shall be coordinated through the Contracting Officer's Representative (COR). All work shall be prescheduled to ensure that power outage periods are suitable to the VAMC. Only 1 substation shall be shutdown per calendar day. All required tools and test equipment shall be on station before the start of any shutdown.

Conformance Standard

All work shall be in accordance with the attached Work Required and shall be in strict compliance with all VA, national, state, county, and local codes so having jurisdiction. All requirements of the VAMC Detroit safety office shall also apply. All testing equipment shall meet sections 5.2 and 5.3 of the International Electrical Testing Association (NETA) Standards for Maintenance Testing Specifications for Electrical Power Distribution Equipment and Systems (2007).

Hours of Work

Phase I: Substation No. 7 and Substation No. 11 shall be performed between Sunday and Thursday from 11:00 P.M. and 7:00 A.M. Only one Substation shutdown is allowed per calendar day.

Phase I: The remainder of Phase I work shall be performed between Monday and Friday from 7:00 A.M. and 3:30 P.M.

Phase II and Phase III: All work shall be performed between Sunday and Thursday from 11:00 P.M. and 7:00 A.M. Only one Substation shutdown is allowed per calendar day.

Work shall not be scheduled on federal holiday, including any day deemed a federal holiday by the President of the United States of America. Please visit https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/ for a list of federal holidays.

Work Required

Provide all labor, materials, supervision, parts and equipment for the testing, inspection, and listed repairs of the electrical switchgear: Phase I, Phase II, and Phase III.

Equipment to be Inspected and Tested

Phase I:

Primary Switchgear - Consists of 2 Siemens 2000-amp Main Breakers, 1 Siemens 1200-amp Tie Breaker, 8 Siemens 1200-amp Primary Circuit Breakers, and all associated typical metering and protective relays.

Generator Control Panels - Consists of 2 locations with a total of 8Westinghouse SPB-100 Circuit Breakers, and 33 Primary Circuit Breakers

Substations - Consists of 5 Structures with breakers listed below. VA Medical Center Subs 7, 11, 13, 14, and 15

Oil Transformers - Consists of 5 transformers (13KV/480V)

480V Circuit Breakers - Consists of 5 Siemens RL & 39 Molded Case Circuit Breakers.

Automatic Transfer Switches - Consists of 20 Switches.

Phase II:

Substations - Consists of 5 Structures with breakers listed below. VA Medical Center Subs 1, 2, 3, 4, and 5

Oil Transformers - Consists of 5 transformers (13KV/480V)

480V Circuit Breakers - Consists of 5 Siemens RL & 39 Molded Case Circuit Breakers.

Automatic Transfer Switches - Consists of 16 Switches.

Phase III:

Substations - Consists of 5 Structures with breakers listed below. VA Medical Center Subs 6, 8, 9, 10, and 12

Oil Transformers - Consists of 5 transformers (13KV/480V)

480V Circuit Breakers - Consists of 5 Siemens RL & 39 Molded Case Circuit Breakers.

Automatic Transfer Switches - Consists of 13 Switches.

Equipment to be Repaired

The following repair is to be completed in conjunction with Phase I testing and inspection of the applicable Substation:

Substation 11: - Repair selector 101/201 selector switch. Blades are very tight making switch inoperable.

Substation 15: - Repair breaker charge/ close sequence - breaker charges and closes instantly before signal to close.

Substation 15: - Oil Transformer Repair sealing gasket between oil transformer and Substation switchgear. Clean/purify and recycle oil, restore correct tank oil level, restore oil tank nitrogen blanket and correct oil tank pressure.

The following repair is to be completed in conjunction with Phase II testing and inspection of the applicable Substation:

Substation 1: - Repair/ adjust mis-aligned selector switch from 101 to 201.

Substation 2: - A pole transfer switch not making positive contact in 102 or 202 position repair as needed for conformity.

Substation 3: - Repair/ adjust mis-aligned selector switch from 101 to 201.

Substation 4: - Repair/ adjust mis-aligned selector switch from 101 to 201.

Substation 5: - Repair/ adjust mis-aligned selector switch from 101 to 201.

The following repair is to be completed in conjunction with Phase III testing and inspection of the applicable Substation:

Substation 6: - Repair/ adjust mis-aligned selector switch from 101 to 201.

Substation 8: - Repair/ adjust mis-aligned selector switch from 101 to 201.

Substation 9: - Repair/ adjust mis-aligned selector switch from 101 to 201.

Substation 10: - Repair/ adjust mis-aligned selector switch from 101 to 201

Substation 12: - Repair/ adjust mis-aligned selector switch from 101 to 201.

Performance Requirements

Primary Switchgear (Medium Voltage) Breakers Qty. 11

All breakers shall be racked out by contractor to perform inspection, cleaning, and testing.

Verify all breaker settings, if applicable, prior to inspecting, testing, or cleaning and document. All settings shall be restored after inspection and testing is complete.

Visually and mechanically inspect for physical damage, proper installation and operating condition.

Inspect physical and mechanical condition of each breaker.

Clean each circuit breaker including main contacts with cleaners or solvents approved by manufacturer.

Verify appropriate lubrication on contacts and moving parts per manufacturer s recommendations. Lubricate where necessary.

Inspect for damaged or worn parts.

Operate circuit breaker using the test station and manually to insure proper operation.

Test the contact resistance using a ductor.

Test the insulation integrity using a megger.

Clean all cells of dust and debris and inspect for damage prior to reinstalling breakers.

Inspect all mechanical interlocks and breaker guides for proper operation and lubricate per manufacturer s recommendations.

Check for proper operation of controls and auxiliary devices.

Document all issues found.

Document all test results with detailed readings from test equipment and not just PASS / FAIL, as applicable.

All recordings, test results, and any other documented information shall be entered a report.

Primary Switchgear (Medium Voltage) Metering / Protective Relays

All relays shall be set to the recommended settings from a previously performed

coordination study prior to any testing or cleaning. Those relays with no recommended

changes shall be verified and documented prior to inspecting, testing, or cleaning. All

settings shall be documented in the report after inspection and testing is complete.

Settings from the coordination study shall be provided by the VA.

Visually and mechanically inspect for physical damage or worn parts, proper installation, wiring connections, screws for tightness, and operating condition.

Electro-mechanical relays shall be inspected for dust, iron fillings, rust, or foreign matter.

Relay contacts shall be inspected for freedom of movement.

Clean each relay, including cover, with cleaners or solvents approved by manufacturer.

Lubricate, if applicable, all moving part per manufacturer s recommendations.

All relays shall be tested in accordance with the manufacturer s recommendations. Test shall include but not limited to insulation resistance to ground, pickup, time delay, and instantaneous trip.

All recordings, test results, and any other documented information shall be entered a report

Document all test results with detailed readings from test equipment and not just PASS / FAIL, where applicable.

Substations Qty. 15

Visually and mechanically inspect for physical damage, proper installation and operating condition.

Inspect all connections including buss bars, cables and grounding connections for tightness.

Inspect and clean fuses and fuse holders per manufacturer s recommendations.

Test contact resistance of all fuses and holders using a ductor.

Test the insulation integrity using a megger.

Inspect and clean all barriers, insulators, arcing blades and chutes.

Inspect all mechanical and key interlocks for proper operation and lubricate per manufacturer s recommendations.

Clean all cells of dust and debris and inspect for damage.

Document all issues found.

All recordings, test results, and any other documented information shall be entered a report.

Oil Transformers Qty. 15

Inspect transformers/record nameplate info.

Inspect physical and mechanical condition.

Verify fans and controls operate correctly, as applicable.

Inspect all bolted electrical connections including grounding.

Inspect for leaks.

Record liquid level, liquid temperature, and tank pressure.

Perform insulation resistance test (Winding to winding, and to Ground. Calculate PI).

Perform Turns Ratio test at the designated tap position.

Take liquid samples for Dissolved Gas Analysis tests. Samples shall be delivered to the testing laboratory in a reasonable time as to not compromise the samples. Care shall be taken in storing the samples as recommended by the testing laboratory until they are delivered.

All recordings, test results, and any other documented information shall be entered a report.

480V RL Circuit Breakers Qty. 15

Verify all breaker settings prior to inspecting, testing, or cleaning and document. All settings shall be restored after inspection and testing is complete.

Visually and mechanically inspect for physical damage, proper installation and operating condition.

Inspect physical and mechanical condition of each breaker.

Clean each circuit breaker including main contacts with cleaners or solvents approved by manufacturer.

Verify appropriate lubrication on contacts and moving parts per manufacturer s recommendations. Lubricate where necessary.

Inspect for damaged or worn parts.

Operate circuit breaker manually to insure proper operation.

Check for proper operation of controls and auxiliary devices.

Test the overcurrent protective device using the secondary current injection method.

Test the contact resistance using a ductor.

Test the insulation integrity using a megger.

Document all test results with detailed readings from test equipment and not just PASS / FAIL, as applicable.

All recordings, test results, and any other documented information shall be entered a report.

480V MCCB Circuit Breakers Qty. 118

Verify all breaker settings prior to inspecting, testing, or cleaning and document. All settings shall be restored after inspection and testing is complete.

Visually and mechanically inspect for physical damage, proper installation and operating condition.

Inspect physical and mechanical condition of each breaker.

Clean each circuit breaker with cleaners or solvents approved by manufacturer.

Inspect for damaged or worn parts.

Operate circuit breaker manually to insure proper operation.

Test the overcurrent protective device using the secondary current injection method.

Test the contact resistance using a ductor.

Test the insulation integrity using a megger.

Document all test results with detailed readings from test equipment and not just PASS / FAIL where applicable.

All recordings, test results, and any other documented information shall be entered a report.

Automatic Transfer Switches (ATS) Qty. 49

Unless otherwise specified in the contract, the ATS s shall be Infrared scanned as these switches cannot be de-energized without prior scheduling. Switches shall be scanned under load in both Normal and Emergency positions as follows:

It shall be scanned prior to shutting down the substation from which it s fed while in the Normal position.

It shall be scanned again after completing the maintenance and testing of the substation from which it s fed while in the Emergency position.

Colored pictures of each ATS in both Normal and Emergency positions which shall include room, conductor, and terminal temperature readings.

All issues found shall be documented.

Contractor shall follow NFPA 70E when working around transfer switches.

Required Documents and Reports

All reports shall be delivered electronically within 7 10 business days after work is completed. Coordinate delivery options with the COR.

Miscellaneous

Any deviations from the manufactures suggested testing procedures shall require a document from the manufacturer approving and/or explaining such changes. Contractor shall ground all equipment as needed for this work. VA personnel shall be responsible for de-energizing and re-energizing the substations and shall coordinate such with contractor. VA personnel shall be responsible for providing suitable power to support the maintenance and breaker testing. Contractor shall provide quotes for any breaker components or parts that may be found defective after the work is completed. Replacement parts, if necessary, shall be purchased separately. Verify all breaker settings, if applicable, prior to inspecting, testing, or cleaning and document. All settings shall be restored after inspection and testing is complete.

Invoicing

Refer to http://www.va.gov/oaa/invoicing/faqs.asp for help with the electronic invoicing system.

Reporting Requirements

The contractor shall report to the designated COR prior to engaging in any of the scheduled work. The meeting location shall be coordinated between the COR and the contractor to best suit the performance of the scheduled work. Contractor personnel shall be escorted to and from work areas by a designee of the COR.

Competency of Personnel Servicing the Equipment

All contractor personnel shall complete VA Privacy and Information Security Awareness and Rules of Behavior Training at https://www.tms.va.gov/learning/user/login.jsp. The contractor shall deliver copies of the completion certificates for all contractor personnel to the COR. The certificates shall be delivered before or at the time the personnel arrive at the VA facility.

Required Certifications:

NETA and/or NICET certification or the equivalent

Arc-Flash Training

Contractor shall comply with all State, Federal, and local laws concerning safety (OHSA).

Update #3 ·

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the

offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY

is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not,

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter

or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to

the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print)

(Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign)

(Signature of Contracting Officer)

1

1

0002

None

36C250

Department of Veterans Affairs

Ann Arbor Healthcare System

Network Contracting Office 10

2215 Fuller Road

Ann Arbor, MI 48105

36C250

Department of Veterans Affairs

Ann Arbor Healthcare System

Network Contracting Office 10

2215 Fuller Road

Ann Arbor, MI 48105

To all Offerors/Bidders

36C25023Q0725

06-15-2023

X

X

X

1

RFQ close date is extended to 06/26/2023 at 10:00 AM

See CONTINUATION Page

X

1

1. This amendment is to provide a second site visit opportunity on Wednesday, June 21, 2023, at 9:00 am sharp.

a. Vendors must report to room LL633 (Engineering Conference Room) no later than 9:00 am.

b. The site visit points of contact will be Mr. Christopher Gill and Mr. Jason McNaughton.

c. The site visit is for equipment viewing purposes only please do not ask any questions of VA staff. After the

site visit is completed, you are welcome to provide an offer based on all the information you have at that time.

d. Vendors must sign in on the Site Visit Sign-In Sheet and provide all information requested, legibly.

2. No other changes to the solicitation are made as a result of this amendment.

Jennifer A. Johnson

Contracting Officer

Update #2 ·

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the

offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY

is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not,

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter

or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to

the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print)

(Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign)

(Signature of Contracting Officer)

1

2

0001

None

36C250

Department of Veterans Affairs

Ann Arbor Healthcare System

Network Contracting Office 10

2215 Fuller Road

Ann Arbor, MI 48105

36C250

Department of Veterans Affairs

Ann Arbor Healthcare System

Network Contracting Office 10

2215 Fuller Road

Ann Arbor, MI 48105

To all Offerors/Bidders

36C25023Q0725

06-08-2023

X

X

X

1

RFQ close date is extended to 06/19/2023 at 10:00 AM

See CONTINUATION Page

X

1

1. The purpose of this amendment is to answer industry questions.

2. No other changes to the solicitation are made as a result of this amendment.

Jennifer A. Johnson

Contracting Officer

Page 2 of 2

Switchgear Maintenance & Testing RFQ 36C25023Q0725

Vendor Questions Asked & VA Responses

Why is this an open market solicitation? This solicitation is set aside for any SDVOSB concern, and therefore is open market for any interested and capable SDVOSB.

Request additional information:

Electrical one-lines for the system? Per the requiring department, this information is not available at this time.

Report from last maintenance and testing? Per the requiring department, this information is not being shared at this time.

Technical data for equipment requiring repair?

Substation 15: - Oil Transformer Repair sealing gasket between oil transformer and Substation switchgear. Clean/purify and recycle oil, restore correct tank oil level, restore oil tank nitrogen blanket and correct oil tank pressure. Â Sealing Gasket between Siemens (HV 13200 Delta, LV 480/277 Transformer Serial # PYC-0215) and Siemens Switchgear (I-T-E Switchboard Type/ Cat No. FC II Series 6Â S.O. 17-16247-15C 480Y/277vac)

Substation 11: - Repair selector 101/201 selector switch. Blades are very tight making switch inoperable. Knife switch (Siemens, I-T-E Switchboard Type/ Cat. No. PC Series HVÂ S.O. 17-16247-15Â System 13200V)

Substation 1; 3; 4; 5; 6; 8; 9; 10; 12: - Repair/ adjust mis-aligned selector switch from 101 to 201. Knife switch (Siemens, I-T-E Switchboard Type/ Cat. No. PC Series HVÂ S.O. 17-16247-15Â System 13200V)

Substation 2: - A pole transfer switch not making positive contact in 102 or 202 position repair as needed for conformity. Â Knife switch (Siemens, I-T-E Switchboard Type/ Cat. No. PC Series HVÂ S.O. 17-16247-15Â System 13200V)

I do not see a site visit scheduled. Is there not going to be one? A one-time site visit has been scheduled for Wednesday, June 14, 2023, at 12:30 pm sharp. The site visit is for equipment viewing purposes only please do not ask any questions of VA staff. After the site visit is completed, you are welcome to provide an offer based on all the information you have at that time, if you wish. There will be no other question and answer period.

Update #1 ·

Page 3 of 3

This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; quotes are being requested. The Government reserves the right to make no award from this solicitation.

Solicitation number 36C25023Q0725 is being issued as a Request for Quote (RFQ). The government anticipates awarding a firm-fixed price contract resulting from this solicitation. This solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular (FAC) 2023-03, effective April 26, 2023.

The associated North American Industry Classification System (NAICS) code for this procurement is 811210 (size standard $34.0 million).

This requirement is 100% set aside for Veteran-Owned Small Business (VOSB).

The Department of Veterans Affairs, Veterans Health Administration, Network Contracting Office (NCO) 10 requires a contractor to provide switchgear maintenance and testing services for Detroit VA Medical Center, located in Detroit, Michigan. Please reference the Statement of Work for specific information and requirements. The anticipated contract period is August 1, 2023 September 30, 2023.

Quotes MUST be received on or before the date and time specified in Block 8 of the SF1449 Solicitation. Solicitation posting and closing dates are subject to change as necessary and amendments will be issued accordingly.

This solicitation requires registration with the System for Award Management (SAM) at time of offer, pursuant to applicable regulations and guidelines. Registration information is at www.sam.gov.

This is an open-market combined synopsis/solicitation for services as defined herein. The government intends to award a contract as a result of this combined synopsis/solicitation that will include the terms and conditions set forth herein. To facilitate the award process, all quotes must include a statement regarding the terms and conditions herein as follows:

"The terms and conditions in the solicitation are acceptable to be included in the award document without modification, deletion, or addition."

OR

"The terms and conditions in the solicitation are acceptable to be included in the award document with the exception, deletion, or addition of the following:"

Offerors shall list exception(s) and rationale for the exception(s).

Offerors shall only submit quotes via email only electronically submitted quotes will be accepted. Please submit quote to Jeanne Ortiz, Contract Specialist, at jeanne.ortiz@va.gov.

Any questions for this solicitation shall be sent via email to Jeanne Ortiz, Contract Specialist, at jeanne.ortiz@va.gov. There will only be one question and answer period. The deadline for submitting all questions is Tuesday, June 6, 2023, at 10:00 AM Eastern Time. All questions shall have 36C25023Q0725 - Question as the subject line. The Government will not respond directly to any questions submitted but will gather questions and post the answers to this Contract Opportunities posting for all potential businesses to access.

Attachments

Files attached to this notice, newest first
File Type Posted
36C25023Q0725 0003_1.docx DOCX document
36C25023Q0725 0002_1.docx DOCX document
36C25023Q0725 0001_1.docx DOCX document
36C25023Q0725_1.docx DOCX document

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity