Frenchman Creek Bridge Replacement, Sawtooth National Forest

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
1240LT23R0043
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Stanley, Idaho 83278, United States

Notice details come from SAM.gov. Updated .

Notice text

4 versions

Update #4 · Latest ·

Purpose of Modification is to update the percent on the Bid Guarantee.

Refer to Page 18 FAR 52.228-1 Bid Guarantee (c) and change the percent for 10 percent to 20 percent.
The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.

Posting of Sign in Sheet for Site Visit and Q&A

Solicitation Posting

 SITE VISIT, THURSDAY JUNE 8, 2023 AT 11:00am, Meet at Closure gate on the road where the bridge is located.

Update #3 ·

Posting of Sign in Sheet for Site Visit and Q&A

Solicitation Posting

 SITE VISIT, THURSDAY JUNE 8, 2023 AT 11:00am, Meet at Closure gate on the road where the bridge is located.

Update #2 ·

Solicitation Posting

 SITE VISIT, THURSDAY JUNE 8, 2023 AT 11:00am, Meet at Closure gate on the road where the bridge is located.

Update #1 ·

Solicitation Posting

 SITE VISIT, TUESDAY JUNE 8, 2023 AT 11:00am, Meet at Closure gate on the road where the bridge is located.

Files

Notice history

Notice Type Posted
Frenchman Creek Bridge Replacement, Sawtooth National Forest Award Award Notice
This notice Latest solicitation Solicitation
Frenchman Creek Bridge Replacement, Sawtooth National Forest Original Pre-Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities