Flooring Installation

Closed Solicitation Posted

Solicitation number
FA4427-18-Q-0072
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Contract number
FA442718P0154 Federal contract award
Awardee
Harbolt Industrial Support Services
NAICS code
238330 Flooring Contractors
PSC
Not on record
Place of performance
Travis AFB, California 94535, United States

Notice details come from SAM.gov. Updated .

Notice text

6 versions

Update #6 · Latest ·

Quetions regarding this solicitation:

1. Is there a wage determination for this project?


- There will be wage determination under Service Contract Act number 2015-5655.


2.Are there any bonds required on this project?


-No


3. Are there any instructions for the site visit?


- Please E-mail A1C Aquino all names of attending members, please bring IDs and car registrations, and we will be meeting at the visitor center.


4. Will a Full-Time Superintendent, CQC Manager and SSHO be required?


-No


 


5. Will an Accident Prevention Plan, a CQC Plan or any other Administrative submittals be required?


 


-Accident Prevention Plan, a CQC Plan or any other Administrative submittals will not be required for this project.


6. Will a schedule be required and can the buildings be done concurrently?


 


-No schedule is required as long as the customer is notified 10 days prior (union workers) and has agreed with the construction date.


 


 


 

Update #5 ·

Questions about this requirement will not be accepted after 1400 PST 18 June 2018.

Update #4 ·

Quetions regarding this solicitation:

1. Is there a wage determination for this project?


- There will be wage determination under wage determination number 2015-5655.


2.Are there any bonds required on this project?


-No


3. Are there any instructions for the site visit?


- Please E-mail A1C Aquino all names of attending members, please bring IDs and car registrations, and we will be meeting at the visitor center.


4. Will a Full-Time Superintendent, CQC Manager and SSHO be required?


-No


 


5. Will an Accident Prevention Plan, a CQC Plan or any other Administrative submittals be required?


 


-Accident Prevention Plan, a CQC Plan or any other Administrative submittals will not be required for this project.


6. Will a schedule be required and can the buildings be done concurrently?


 


-No schedule is required as long as the customer is notified 10 days prior (union workers) and has agreed with the construction date.


 


 


 

Update #3 ·

Quetions regarding this solicitation:

1. Is there a wage determination for this project?


- There will be wage determination under wage determination number 2015-5655.


2.Are there any bonds required on this project?


-No


3. Are there any instructions for the site visit?


- Please E-mail A1C Aquino all names of attending members, please bring IDs and car registrations, and we will be meeting at the visitor center.

Update #2 ·

Quetions regarding this solicitation:

1. Is there a wage determination for this project?


- There will be wage determination under wage determination number 2015-5655.


2.Are there any bonds required on this project?


-No

Update #1 ·

Please see attachments.

Files

File Type Posted
Sign_In_Sheet.pdf PDF
Floor_Plans.pdf PDF
FY18_CONSOLIDATED_FLOORING_PROJECTS_TWCF_SOW.DOC DOC document
SOW.DOC DOC document