C222--RFI Correct FCA Electrical Gaps Salisbury VAMC
Closed Pre-Solicitation Posted
- Solicitation number
- 36C24624Q0180
- Agency
-
Veterans Integrated Service Network 6
Veterans Health Administration, Department of Veterans Affairs
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 541330 Engineering Services
- Place of performance
- W. G. Hefner Vamc Salisbury, North Carolina 28144, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of Veterans Affairs Network Contracting Office 6 seeks architect-engineer services through a future solicitation to complete design and construction work at the Salisbury VAMC in Salisbury, North Carolina. The scope of work involves providing design, drawings, specifications, and cost estimates at 35%, 65%, 95%, and 100% completion stages to correct findings from a facility condition assessment, modernize the main kitchen, and relocate the retail store. Interested parties should respond by December 15, 2023 at 10:00 AM EST to be considered for the anticipated 790-calendar day period of performance comprising 245 days of design services and 365 days of construction period services following award.
The NAICS code is 541330 for engineering services and the PSC code is C222. Responses to the sources sought notice will be reviewed regardless of socioeconomic category or business size to support later determinations for any set-aside requirements if a solicitation is released. The budget range is estimated between $5,000,000 to $10,000,000.
Notice text
Sources Sought Notice
Sources Sought Notice
Page 5 of 5
Sources Sought Notice
*= Required Field
Sources Sought Notice
Page 1 of 5
THIS IS A SOURCES SOUGHT NOTICE ONLY. This notice does NOT constitute a request for proposal, request for quote, or invitation for bid. No formal solicitation document exists currently. We are seeking information for market research purposes only. The Government will not pay for any information solicited.
The Department of Veterans Affairs, Network Contracting Office 6 is conducting market research to identify potential sources for Architect-Engineer services to complete the below scope of work.
The place of performance will be the hospital campus of the Durham VA Medical Center in Durham, Virginia. Forward all questions to the point of contact identified below. This is not a pre-solicitation notice, but the magnitude of construction for this project is currently between $5,000,000 and $10,000,000 but is subject to revision prior to release of a solicitation.
The proposed NAICS 541330 Engineering Services is applicable to this acquisition with a size standard of $25.5 Million.
The proposed PSC code is C222 Architect and Engineering General: Electrical Systems.
The anticipated Period of Performance is 790 days from the Notice to Proceed.
Scope of Work:
Architect/Engineer (A-E):Â Provide a design narrative, drawings, specifications, and a cost estimate at 35%, 65%, 95%, and 100% design stages for project #659-24-800. The final submission shall be stamped by a licensed engineer to include, but not limited to, drawings, specifications, estimate and calculations. The project corrects findings found during Facility Condition Assessment, modernizes the station s main kitchen, and relocates the station s VCS retail store.
Design shall comply with VA guidelines and specifications. Design manuals and specifications can be found at https://www.cfm.va.gov/til/index.asp.
SUBMISSIONS:
Submit review packages so they are received on the noted day (calendar days after NTP) or earlier:
Initial PDT Meeting 0 days
Design Development Documents (35%) 70 days
(PDT Meeting) 98 days
Design Development Documents (65%) 161 days
(PDT Meeting) 182 days
Design Development Documents (95%) 203 days
(PDT Meeting) 217 days
Final Construction Bid Documents 231 days
(PDT Meeting) 245 days
(3 Sets of Drawings and Specifications)
Design completion: 245 calendar days; includes VA design reviews.
Procurement timeframe: 180 days from the time Engineering submits package to contracting. Designer shall answer pre-bid RFIs and provide updated construction documents to capture any changes made through the procurement process.
Construction period services: 365 calendar days from construction award date
Total contract period: 790 calendar days
Small Business Requirements
For market research purposes, all responses to this notice will be reviewed, regardless of small business/socioeconomic category, including those firms that are identified as large businesses. Review of responses to this notice will support later determination of set-aside requirements, if a solicitation becomes available, where the rule of two is met regarding a set-aside, including set-asides under 38 U.S.C. 8127 and 8128 for SDVOSB and/or VOSB firms registered in the VIP database, in accordance with priorities set by regulation.
All interested parties should respond, in writing via email to the contract specialist, Mark Griffin, mark.griffin2@va.gov and contracting officer, Vangie Miller, vangie.miller@va.gov. No telephone inquiries will be accepted. Your response is requested by Friday, December 15, 2023 at 10:00 AM EST. In your response, please include the following:
Company name
Address
Point of contact with email and phone number
SAM Unique Entry ID number and evidence of current SAM registration (see https://www.sam.gov for more information)
Company Socio-Economic SIZE (example large, small, SDVOSB, VOSB, WOSB etc.)
Proposed NAICS code (if different from above)
Proposed PSC code (if different from above)
Capabilities statement, to include experience with contracts of similar scope and magnitude.
Is the anticipated period of performance appropriate for this project?
Is there anything that would deter you from responding to this requirement?
Files
| File | Type | Posted |
|---|---|---|
| 36C24624Q0180.docx | DOCX document |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| C1DA--Renovate Specialty Clinics on 2nd | Veterans Integrated Service Network 5 | Service-Disabled Veteran-Owned Small Business | |
| 613-22-700 | EHRM Infrastructure Upgrades Construction | Martinsburg, WV | VA Technology Acquisition Center | No set-aside | |
| Z2DA--652-24-101 Improve Electrical Distribution | Veterans Integrated Service Network 6 | Service-Disabled Veteran-Owned Small Business | |
| Z2DA--FY27 NRM 558-24-160, Domestic Water, Chilled Water and Steam Piping (VA-26-00066009) | Veterans Integrated Service Network 6 | Service-Disabled Veteran-Owned Small Business | |
| C1DA--578-27-003 - Renovate A Section First Floor of Building 1 - Design FY27 | Veterans Integrated Service Network 12 | Service-Disabled Veteran-Owned Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity