This document is a line description file for snow removal services at West Rail Line light rail stations operated by the Regional Transportation District (RTD) in the Denver metropolitan area, spanning locations in Golden, Lakewood, and Denver, Colorado. The contract encompasses snow and ice removal services across nine stations: West Rail Line Jefferson County Government Center-Golden Station, Red Rocks College Station, Federal Center Station, Oak Station, Garrison Station, Lakewood-Wadsworth Station, Lamar Station, Sheridan Station, Perry Station, Knox Station, and Decatur-Federal Station. Responsibilities include maintaining parking structures (ranging from zero to 1,069 parking spaces depending on location), light rail platforms, bus shelters, sidewalks, pedestrian surfaces, vehicle lanes, stairs, ramps, elevators, and related infrastructure. Each station has specific snow removal boundaries and exclusions clearly delineated, with particular attention to accessibility requirements, ADA-compliant ramps, and pedestrian safety zones. Contractors are responsible for maintaining all RTD property within defined geographic parameters at each location and must ensure removal of snow, ice, graffiti, and debris from pedestrian and vehicular surfaces.

The contract specifies that contractors must maintain all areas according to the scope of work at each station location, with particular emphasis on high-traffic areas such as parking structures and pedestrian walkways. Notable requirements include maintaining shelter areas, elevator landings and platforms, bike paths where applicable, retaining walls, and underpasses. The document indicates that contractors must maintain access to critical infrastructure including Transfer Power Sub Stations (TPSS) and ensure sidewalks remain clear on both sides of streets leading to stations. The contract includes a 25 percent small business enterprise (SBE) goal, indicating a set-aside for disadvantaged businesses. No specific pricing terms, contract duration, award dates, or incumbent information is provided in this line description document.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1.

West Ra i I Line

Jefferson County Government Cente r-Golden Station, 605 Johnson Road, Golden (6th Ave. & Johnson Rd): Responsibility includes but is not limited to; Parking structure with 835 parking spaces; one (1) driver relief station; two (2) elevators; light rail platforms; elevator platforms; landings;

stairs; steps; ramps; and bus lanes. Contractor is responsible for all specifications listed in the scope of work.

Snow Removal responsibility includes all vehicle and pedestrian surfaces south of Jefferson County Parkway, west of Johnson Road and south and east of the bus lane including the bus lane from the roundabout south. Jefferson County

Parkway from the entrance of Johnson Road to the roundabout must be maintained as needed (typically nights and weekends). The sidewalks on the east side of the parking garage leading to the bike path are included in this contract. The entire platform area is included in this contract including pedestrian surfaces ten (10) feet west of the west end of the platform.

Access to the Transfer Power Sub Station (TPSS) entrance on the northwest side must be maintained and is included in this contract. The sidewalk on the south side of the TPSS leading to the Jefferson County parking structure is included in this contract. The sidewalk on the west/northwest side of the bus lane leading from the platform area is included in this contract. The sidewalks on the north side of the parking structure between the structure and

Jefferson County Parkway are included in this contract. The entire RTD parking structure is included in this contract.

Excluded: The bike path east of the parking garage is excluded. Both the Bike

Path bridge southeast of the parking structure and the bike path south of the track area are excluded. Sidewalk leading west from the west end of the platform is excluded. Sidewalk north of the TPSS leading to the Jefferson

County Government Center is excluded. The Jefferson County Parking

Structure is excluded.

2. Red Rocks College Station, 13400 W. 5th Ave., Lakewood (6th Ave. &

Arbutus): Responsibility includes but is not limited to; Zero (0) surface parking spaces; two (2) bus shelters; two (2) light rail platforms; ramps; and bus lanes. Bus shelters are located across the street from station. Sidewalks from shelters to station must be maintained. Contractor is responsible for all

3.

specifications listed in ·the scope of work.

Federal Center Station, 11601 W. 2nd Pl., Lakewood (2nd Pl. & Routt St):

Responsibility includes but is not limited to; 1000 parking spaces in an open lot south of the station; driver relief station; light rail platforms; landings; stairs;

steps; ramps; and bus lanes. Contractor is responsible for all specifications listed in the scope of work.

Snow Removal responsibility includes all RTD property north of W. 2nd Pl., west of Routt St., and RTD property line on the north and west. Responsibility includes, Stairs on the west side of the facility along with an ADA accessible ramp. The sidewalk north of 2nd along Routt St. all the way to the LRT crossing is required to be maintained under this contract.

4. Oak Station, 1311 Oak St .• Lakewood (Oak St. & 13th Ave.): Responsibility includes but is not limited to; 200 surface parking spaces; driver relief station;

bus shelters; light rail platforms; ramps; and bus lanes. Contractor is responsible for all specifications listed in the scope of work.

Snow Removal responsibility includes all RTD property west of Oak St., east of Quail St., and RTD property line on the south and north. Responsibility for

Snow Removal includes but is not limited lot, bus lanes, boarding areas, vehicle drive lanes, sidewalks, and platforms. RTD owns West Rail Road that passes directly thru the property, the contractor must remove snow on West Rail

Road.

5. Garrison Station, 9091 W. 13th Ave .• Lakewood (Garrison St. & 13th Ave.):

Responsibility includes but is not limited to; Zero (0) surface parking spaces;

two (2) light rail platforms; and ramps. Contractor is responsible for all specifications listed in the scope of work. DO NOT PARK ON GARRISON

STREET or in bike lane.

6. Lakewood-Wadsworth Station. 1298 Wadsworth Blvd .• Lakewood

(Wadsworth Blvd. & 13th Ave.): Responsibility includes but is not limited to;

Parking structure with 1000 parking spaces; four (4) elevators; light rail elevated light rail platforms; elevator platforms; landings; stairs; steps; ramps;

bus lanes; and vehicle lanes. Contractor is responsible for all specifications listed in the scope of work.

Snow Removal responsibility includes all sidewalks, platforms, all pedestrian surfaces above Wadsworth Blvd., all pedestrian surfaces on RTD property along Wadsworth Blvd. and 14th Blvd., pedestrian surfaces under the overpass on both sides of Wadsworth Blvd.

West Ra i I Line Continued

3.

4.

5.

1. Lamar Station, 6363 W. 13th Ave.Lakewood (Lamar St. & 13th Ave.):

Responsibility includes but is not limited to; Zero (0) surface parking spaces; two

(2) l ight rail platforms and ramps. Sidewalk area up to bus stop is in cl u de d. Contractor is responsible for all specifications listed in the scope of work.

2. Sheridan Station. 1198 Sheridan Blvd .• Denver (Sheridan Blvd. & 14th Ave.):

Responsibility includes but is not limited to; Parking structure with 800 parking spaces; four (4) elevators; light rail platforms; elevator platforms; landings;

stairs; steps; ramps; bus lanes on Sheridan Blvd.; Shelters on Sheridan Blvd.:

and vehicle lanes. Contractor is responsible for all specifications listed in the scope of work.

Snow Removal responsibility includes shelter area on Sheridan Blvd. including twelve (12) feet on either side of shelter, Shelter area must be accessable to elevator landing area on Sheridan Blvd., pedestrian surfaces under the overpass, elevator landings, stairs next to elevators and the sidewalk under Sheridan Blvd. Drive parallel to Sheridan to east included. Sidewalk to east leading to neighborhood included.

Perry Station, 1199 N. Perry St., Denver (Perry St. & 12th Ave.):

Responsibility includes but is not limited to; Zero (0) surface parking spaces;

two (2) light rail platforms; ramps; crosswalks; and stairs. Contractor is responsible for all specifications listed in the scope of work.

Snow Removal responsibility includes all sidewalks, bike path on the north side of platform from Perry St. to Quitman St., pedestrian surfaces located at

Perry Station and sidewalks along Perry St. on both sides of Perry St. south to the end of the RTD pedestrian surfaces.

Knox Station, 1245 Knox Ct., Denver (Knox Ct. & 12th Ave.): Responsibility includes but is not limited to; Zero (0) surface parking spaces; two (2) light rail platforms; ramps; sidewalks; shelters along Knox Ct.; Contractor is responsible for all specifications listed in the scope of work.

Snow Removal r e s p o n s i b i l i t y includes all sidewalks, steps leading to the open space area, platforms, pedestrian surfaces located at Knox Station, and sidewalks along Knox Ct. on both sides of Knox Ct. including the shelters and bus loading areas south to 12th Street. Contractor is responsible for the pedestrian access from Knox Station north to King St.

Decatur-Federal Station. 1310 N. Federal Blvd., Denver (Federal Blvd. & Howard Pl.): Responsibility includes but is not limited to; 1069 surface parking spaces; driver relief station; two (2) light rail platforms; ramps; and stairs. The property located on the west side of Federal around the TPSS shelter is the responsibility of this contract to police for trash, graffiti and other requirements of this contract. Pay particular attention to the large retaining walls west and east of Federal/Decatur Station on the north and the south side of the alignment. The bases of a few of these walls are in the drainage area and are very difficult to access. Contractor is responsible for all graffiti removal on these walls regardless of accessibility or height. The area under Federal Blvd. is Contractor responsibility including the sidewalk leading west under Federal up to Federal Blvd. The bus shelters on Federal Blvd. including the sidewalk leading to the station and boarding areas are Contractor responsibility. Contractor is responsible for all specifications listed in the scope of work.

Snow Removal responsibility includes, the pedestrian access on the west side of Federal leading west and then east under Federal Blvd. to

Federal/Decatur Station, the sidewalk on the west side of Decatur continuing south approximately twenty (20) feet south of the alignment. This is a significant amount of area and includes the stairs leading northwest from the station to

Federal Blvd.