WATER_AND_WASTEWATER_FACILITIES_PROCESS_CONTROL_AND_SECURITY_SYSTEM_IMPROVEMENTS_JOB_ORDER_CONTRACT.pdf

PDF 204 KB Posted

Attached to
RFQ Water & Wastewater Facilities Process Control & Security System Improvements Job Order Contract
Solicitation number
JOC258
Issued by
Maricopa County, Phoenix City, Arizona

About this file

Summary

This Request for Qualifications (RFQ) is issued by the City of Phoenix, Arizona Office of the City Engineer for the procurement of qualified contractors to provide Process Control and Security System Improvements Job Order Contracting (JOC) services at water and wastewater facilities. The services include installation and replacement of electrical and process control panels, instrumentation, SCADA system components, RTU and PLC programming, access control enhancements, surveillance system upgrades, intrusion detection devices, conduit and cabling installation, and related construction work including site work, concrete pads, fencing, and emergency repair services. Up to three contractors will be selected through a qualifications-based selection process. The pre-submittal meeting is scheduled for 11:00 am on Tuesday, August 25, 2026, at 200 W. Washington St., Floor 9, Phoenix, Arizona, with remote Teams participation available. Statements of Qualifications must be submitted electronically by 12:00 pm on Friday, September 11, 2026. Selection notification is anticipated in October 2026, with a kick-off meeting scheduled for November 2026. The JOC is structured for a 36-month initial term or $48,000,000 per contractor, whichever occurs first, with an option to renew for an additional 24 months and $32,000,000 for a total contract value not to exceed $80,000,000 per contractor. Individual Job Order Agreements will not exceed $4,000,000 in construction costs.

Contractors must hold the appropriate Arizona contractor license and provide performance and payment bonds for each Job Order. No Small Business Enterprise utilization goal has been established for this project. The evaluation criteria include general firm information and organization (150 points), firm experience and qualifications (250 points), key personnel experience (250 points), and approach to performing required services (350 points), with reference checks providing an additional 21 points out of a total 1,021-point evaluation. Submissions are limited to 12 pages and must be submitted in PDF format through the City's Procurement Portal. All work will be performed in Arizona, and contractors must utilize the City's UNIFIER web-based project management database, maintain electronic project records, and possess computerized networked office infrastructure with broadband internet connectivity. The City will provide construction administration, inspection, and acceptance material testing for all Job Order Agreements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF PHOENIX, ARIZONA

OFFICE OF THE CITY ENGINEER

DESIGN AND CONSTRUCTION PROCUREMENT

REQUEST FOR QUALIFICATIONS

WATER AND WASTEWATER FACILITIES PROCESS CONTROL AND

SECURITY SYSTEM IMPROVEMENTS JOB ORDER CONTRACT

OPENGOV ID NO. JOC258

RFQ Rev. 1/25 Page | 2

The City of Phoenix is seeking qualified contractors to do business on an on-call basis to provide

Process Control and Security System Improvements Job Order Contracting (JOC) Services at water and wastewater facilities as described below. Up to three contractors may be selected for this JOC.

No Small Business Enterprise goal has been established for this project.

Project Description

At a minimum, the Contractor will be expected to successfully perform the following construction services, including, but not limited to:

• Installation and/or replacement of electrical and process control panels.

• Installation of instrumentation and electrical equipment such as analyzers, meters, sensors, variable frequency drives, security upgrades and Supervisory Control and Data

Acquisition (SCADA) system components including conduit and/or wiring.

• Programming of Remote Terminal Units (RTU’s), Programmable Logic Controllers

(PLC’s) and instrumentation to control facilities in accordance with the City Operating

Divisions control strategy.

• Refurbish or replace RTU, PLC and Remote input/output (RIO) panels.

• Access Control Enhancements: Installation or replacement of high-security locks, secured panels, intrusion alarms on hatches, and integration with existing access control architecture.

• Surveillance System Upgrades: Addition or replacement of interior/exterior security cameras, camera system networking components, and communication links, including programming and integration into the central video management system.

• Intrusion Detection Devices: Installation or replacement of motion sensors, glass-break detectors, and warehouse/storage area intrusion detection equipment.

• System Integration with PCS/SCADA: Coordination with process control system upgrades to ensure compliance with security design guidelines and alignment with modernization efforts identified in current PCS/SCADA improvement programs.

• Install conduit and duct banks for power, control wiring and fiber optic cables.

• Configure, program, and calibrate instrumentation and control elements.

• Provide construction services to install concrete pads, fence, shade canopies and other physical infrastructure necessary for security system and process control equipment.

• Installation and replacement of duct-banks, conduits, wiring, fiber optic cabling for electrical, security, and control improvements.

Page | 3

• Site work such as excavation and earthwork, grading and drainage, utilities, road access and paving as it derives from Process Control and Security Improvements.

• General construction work such as building modifications, painting, concrete, masonry, structural steel work, and specialized maintenance as it derives from Process Control and Security Improvements.

• Emergency Repair Services.

• Pre-construction and post-construction services.

• Engineering design services when necessary or required.

This will be for a 36-month duration or $48,000,000 per JOC Contractor, whichever occurs first.

The JOC will include an option to renew, based on the Contractor’s satisfactory performance, the

City’s need for additional services, and funding availability. The option to renew will be for an additional 24-month term and the balance of $32,000,000 for a total contract amount not to exceed

$80,000,000 per JOC Contractor, including all amendments. The City intends that each Job Order

Agreement (JOA) issued under this JOC will not exceed $4,000,000 in construction costs, but in no event will any JOA exceed $4,000,000 after Council approval of the change in limits.

The Contractor is required to provide performance and payment bonds in the amount of each Job

Order proposal prior to executing the Agreement.

During the term of the JOC, work is performed as a series of individual Job Orders. Each Job

Order Agreement, initiated by the City, is defined cooperatively by the City and the Contractor. A scope, schedule, and price are agreed upon, and the Contractor is directed to proceed with the work. JOAs may include pre-construction services, construction work, project management and contract administration as comprised within the Contractor’s construction management plan.

Scope of Work

The scope of work will vary with each JOA. Minor design services may be required for some

JOAs, however, most will be designed through consultants under a separate contract with the

City. City staff may design some projects.

For JOAs that may require design services, the Contractor shall seek the services of an Arizona registered professional architect and/or engineer to prepare plans for permitting. It is the responsibility of the Contractor to provide cost estimating, project scheduling for design, construction and/or maintenance, and obtain permits if needed from the appropriate City departments. The Contractor is also responsible for:

• Knowledge of and compliance with current City of Phoenix adopted codes

• All other work as it relates to this JOC, and

• All work incidental to this JOC

Prior to preparing each Job Order Agreement, a scope of work conference may be scheduled to define design and construction services required of the Contractor.

Page | 4

The City of Phoenix will provide construction administration, inspection, and acceptance material testing for the JOAs.

Assumptions about JOAs:

• All sites will be in the State of Arizona.

• The Contractor will furnish all necessary tools and test equipment required for the performance of its work in accordance with the scope of work.

• All customer-provided documentation is obtained within a reasonable time at project start.

• All customer-required approvals are provided within a reasonable and mutually agreed upon time frame.

• Any work required at each site outside of this scope of work will be performed in accordance with the adjustment process.

• Each JOA Schedule of Values must be submitted in MAG or CSI format or it will not be accepted.

Use of UNIFIER, an Application Service Provider (ASP) web-based project management database, may be required during this JOC. The following information provides a guideline for utilization. Any questions related to the requirements of UNIFIER should be directed to the Project

Manager.

• The Contractor will be required to maintain all project records in electronic format.

• The City provides an ASP web-based project management database which the

Contractor will be required to utilize in the fulfillment of the JOC requirements.

• The Contractor shall provide a computerized networked office platform with broadband internet connectivity.

• UNIFIER training will be provided through the City of Phoenix to firms under this JOC.

Small Business Enterprise (SBE) Requirements

This JOC will be subject to the City of Phoenix Code, Chapter 18, Article VI, pertaining to participation of Small Business Enterprise (SBE) firms in subcontracting opportunities on the

Project. Firms that have been certified by the City of Phoenix Equal Opportunity Department are eligible to meet the SBE subcontracting goals.

No SBE utilization goal for this JOC has been established.

Pre-Submittal Meeting

A pre-submittal meeting will be held at 11:00 am, Phoenix time on Tuesday, August 25, 2026, at

200 W. Washington St., Floor 9 Training Room, Phoenix, AZ 85003 AND via Teams. At this meeting, City staff will discuss the scope of work, general project requirements, and respond to

Page | 5 questions from the attendees. It is strongly recommended that interested firms attend the pre-submittal meeting. Inquiries regarding the project scope outside of this pre-submittal meeting must be directed to the Contracts Specialist.

Pre-Submittal Meeting Teams Information:

Join: https://teams.microsoft.com/meet/288874496804279?p=q5cAHrBD3SmWeZqEv7

Meeting ID: 288 874 496 804 279

Passcode: rS6oJ7FS

Statement of Qualifications Evaluation Criteria

Firms will be selected through a qualifications-based selection process based on the criteria below. Subcriteria are listed in order of importance in relation to project services. City of Phoenix project experience is not required.

No. Evaluation Criteria Scoring Method Weight (Points) https://teams.microsoft.com/meet/288874496804279?p=q5cAHrBD3SmWeZqEv7

Page | 6

1. General Information

A. Provide a general description of the firm that is proposing to provide the requested services under this Job Order Contract.

Explain the legal organization of the proposed firm or team.

B. Provide the following information:

1. List the Arizona contractor licenses held by the firm and the key personnel who will be assigned to this Project.

Provide the contractor license number. Reference the appropriate licenses held, if needed. In order to be considered for this Project, the contractor must hold the correct license as deemed appropriate by the Arizona

Registrar of Contractors prior to submitting a Statement of

Qualifications (SOQ) for this project in accordance with

Arizona Revised Statute §32-

1151.

2. Identify the location of the firm’s principal office and the home office location of key staff on this project.

3. Identify any contract or subcontract held by the firm or officers of the firm, which has been terminated within the last five years. Identify any claims arising from a contract which resulted in litigation or arbitration within the last three years. Briefly describe the circumstances and the outcomes.

4. Provide an organization chart showing the qualifying contractor, and the contractor’s key personnel down to the superintendent level and their availability

Points Based 150 (14.7% of Total)

Page | 7 percentage. (The organizational chart is included in the page limitation.)

2. Experience and Qualifications of the

Firm

A. Identify at least three comparable projects in which the firm played a major role in the last three years.

The projects listed should show the breadth of the firm's experience and demonstrated capabilities and show the experience in managing multiple trade subcontractors, vendors, and suppliers. For each comparable project identified, provide:

1. Description of project

2. Role of the firm either as prime or subcontractor

3. Project’s construction cost

4. Construction dates (identify if this included phased construction)

5. Project Owner

Points Based 250 (24.5% of Total)

Page | 8

3. Experience of Key Personnel to be

Assigned

A. For each key person identified, list their length of time with the firm and at least two comparable projects in which they have played a primary role in the last three years. If a project selected for a key person is the same as one selected for the firm, provide just the project name and the role of the key person. For other projects provide the following:

1. Description of project

2. Role of the person

3. Project’s construction cost

4. Construction dates

5. Project Owner

B. List any proposed subcontractors, including key staff names and the experience and qualifications of these individuals.

Points Based 250 (24.5% of Total)

Page | 9

4. Approach to Performing the Required

Services

A. Describe the firm’s project management approach including its perspective and experience on partnering, quality control, project scheduling, claims, dispute resolution, changes in the scope of work, and construction safety.

B. Describe software systems and processes used for planning, project engineering and scheduling, estimating, and managing construction.

C. Provide a proposed subcontractor selection plan. The selection plan must select subcontractors based on qualifications alone or on a combination of qualifications and price and shall not select subcontractors based on price alone. Describe how you intend to implement this subcontractor selection plan. Discuss the benefit that your subcontractor selection plan provides to the project.

Points Based 350 (34.3% of Total)

5. Reference Checks

Use the form provided in the Attachments section to obtain at least three references.

It is preferred no more than one be a City of Phoenix project. If your firm has not completed prior projects with other agencies, you will not be penalized. It is recommended there be references outside the City of Phoenix.

*These points are in addition to the 1,000 points for the SOQ.

Points Based 21 (2.1% of Total)

Submittal Requirements

Electronic Submittal Process: Firms interested in this project must submit a Statement of

Qualifications (SOQ) electronically through the City's Procurement Portal at https://procurement.opengov.com/portal/phoenix.

Submittal requirements are as follows:

https://procurement.opengov.com/portal/phoenix

Page | 10

Vendor Information: All firms must be registered in the City’s Vendor Management System prior to submitting a proposal. The vendor number should be included on the cover of the

SOQ. Information on how to register with the City is available at:

https://www.phoenix.gov/financesite/Pages/EProc-help.aspx

If your firm is already registered with the City of Phoenix’s Procurement system, visit https://procurement.opengov.com/portal/phoenix to login and access the electronic solicitation.

Submittals:

• Experience Modification Rate (EMR) – provide current rating; the awarded company will be asked to provide verification upon contract execution.

• Submit only one SOQ electronically, in .PDF format only, addressing all evaluation criteria. No hard copies will be accepted.

• Clearly display the firm legal name, vendor number, project title, and project number on the cover of the SOQ.

• A maximum of 12 pages is permitted to address all content in the SOQ submittal.

(Maximum page limit includes evaluation criteria and all additional content. It does not include information sheet.)

• Submit electronically the Statement of Qualifications by 12:00 pm, Phoenix time, on

Friday, September 11, 2026.

• Page size must meet requirements of 8½” x 11”.

• Font size must not be less than 10 point.

• Content count:

o Each side of a page containing evaluation criteria and additional content will be counted toward the maximum page limit noted above.

o Pages that have project photos, charts and/or graphs will be counted towards the maximum page limit noted above.

o Front and back covers, information sheet, Table of Contents pages, and divider (tab) pages will NOT be counted toward the maximum page limit noted above, unless they include evaluation criteria and additional content that could be considered by the selection panel.

Information Sheet: Provide an information sheet that includes project title, OpenGov ID number, legal firm name (not a trade name), address, phone number, vendor number, and the name, title, email address and signature of your contact person for the project. Do not include any additional information.

Evaluation Criteria: Address the SOQ evaluation criteria.

https://www.phoenix.gov/financesite/Pages/EProc-help.aspx

Page | 11

Bonding Statement: As a separate PDF attachment, include a statement of the firm’s bonding capacity from a Surety Company (A- or better for the prior four quarters). This bond statement will not be counted towards the maximum number of pages.

Additional Content: Resumes and other information may be included (content shall be included within the permitted maximum page limit).

Note: All pages exceeding the specified maximum page limit will be removed from the submittal and not considered in evaluating a submitted SOQ.

Grounds for Disqualification

Please be advised that the following will be grounds for disqualification, and will be strictly enforced:

• Submitting a Statement of Qualifications for a different project.

• Violating the “Contact with City Employees” policy contained in this RFQ.

• Failure to provide bonding statement.

Selection Process and Schedule

The successful firms will be selected through a qualifications-based selection process. Interested firms will submit a Statement of Qualifications (SOQ). A Selection Panel will evaluate each SOQ according to the criteria set forth in Statement of Qualifications Evaluation Criteria above. The

City will select two firms based on the SOQs received; no formal interviews will be conducted.

The City may conduct a due diligence review on the firm receiving the highest evaluation.

The City expects to create a final list of at least two, but not more than four firms for this project.

The City will enter into negotiations with the selected firms and execute contracts upon completion of negotiation of contract terms for City Council approval.

The following tentative schedule has been prepared for this project. The Pre-submittal meeting is not mandatory.

Pre-submittal Meeting 11:00 am on Tuesday, August

25, 2026

Last Date for Questions 4:00 pm on Friday, September 4, SOQs Due 12:00 pm on Friday, September

11, 2026

Selection Notification October 2026

Kick-Off Meeting November 2026 https://procurement.opengov.com/portal/phoenix/projects/270970/document?section=2611220

Page | 12

If the City is unsuccessful in negotiating contracts with the best-qualified firms, the City may then negotiate with the next most qualified firms until contracts are executed, or the City may decide to terminate the selection process. Once the contracts are executed with the successful firms, the procurement is complete.

The firms selected for this project will be notified directly by the City. Notification to all other firms on the status of a short list for this project will be posted on the City of Phoenix’s Procurement

Portal:

https://procurement.opengov.com/portal/phoenix

General Information

Citywide Capital Improvement Projects. Consulting and contractor services supporting the

City’s Capital Improvement Projects are procured under the authority of the City Engineer, currently located within the Street Transportation Department. Design and Construction

Procurement coordinates the citywide consulting and construction contracting procurement processes.

Changes to Request for Qualifications. Any changes to this Request for Qualifications

(RFQ) will be in the form of a Notification. The City of Phoenix shall not be held responsible for any oral instructions. Notifications are available on both the Current Opportunities and City's eProcurement Portal at https://procurement.opengov.com/portal/phoenix.

It shall be the responsibility of the registered RFQ holder to determine, prior to the submittal of the Statement of Qualifications, if a Notification has been issued. Registered

RFQ holders may refer to the web page or call Sadie Thompson at (602) 534-1509 to ascertain if a Notification has been issued for this project.

Alternate Format. For more information or a copy of this publication in an alternate format, contact the Contracts Specialist (listed above) - Voice or TTY 711. Requests will only be honored if made within the first week of the advertising period.

Release of Project Information/Public Records Request. The City shall provide the release of all public information concerning the project, including selection announcements and contract awards. Those desiring to release information to the public must receive prior written approval from the City. To submit a Public Records Request, visit phoenix.gov/prr.

City Rights. The City of Phoenix reserves the right to reject any or all Statements of

Qualifications, to waive any informality or irregularity in any Statement of Qualifications received, and to be the sole judge of the merits of the respective Statements of Qualifications received.

Contact with City Employees. This policy is intended to create a level playing field for all

Proposers, assure that contracts are awarded in public, and protect the integrity of the selection process. OFFERORS THAT VIOLATE THIS POLICY WILL BE DISQUALIFIED.

Beginning on the date the RFQ is issued and until the date the contract is awarded or the RFQ withdrawn, all persons or entities that respond to the RFQ, including their authorized employees, agents, representatives, proposed partner(s), subcontractor(s), joint venture(s), member(s), or any of their lobbyists or attorneys (collectively the Proposer), will refrain from any direct or indirect contact with any person (other than the designated Contract Specialist) who may play a part in the selection process, including members of the evaluation panel, the City Manager, Assistant https://procurement.opengov.com/portal/phoenix https://phoenix.gov/prr

Page | 13

City Manager, Deputy City Managers, Department heads, the Mayor and other members of the

Phoenix City Council. As long as the RFQ solicitation is not discussed, Proposers may continue to conduct business with the City and discuss business that is unrelated to this RFQ solicitation with City staff.

Commencing on the date and time a solicitation is published, potential or actual proposers

(including their representatives) will only discuss matters associated with the solicitation with the

Mayor, any members of City Council, the City Manager, any Deputy City Manager, or any department director directly associated with the solicitation (including in each case their assigned staff, except for the designated procurement officer) at a public meeting, posted under the Arizona

Revised Statutes, until the resulting contract(s) are awarded or all offers or responses are rejected and the solicitation is cancelled without any announcement by the procurement officer of the City’s intent to reissue the same or a similar solicitation.

Proposers may discuss their proposal or the RFQ solicitation with the Mayor or one or more members of the Phoenix City Council, provided such meetings are scheduled through the

Contract Specialist (listed above), conducted in person at 200 W. Washington, Phoenix, Arizona

85003, and are posted as open meetings with the City Clerk at least twenty-four (24) hours prior to the scheduled meetings. The City Clerk will be responsible for posting the meetings. The posted notice shall identify the participants and the subject matter, as well as invite the public to participate.

Conflict of Interest. The City reserves the right to disqualify any Proposer on the basis of any real or apparent conflict of interest that is disclosed by the proposal submitted or any other data available to the City. This disqualification is at the sole discretion of the City. Any Proposer submitting a proposal herein waves any right to object now or at any future time, before any body or agency, including but not limited to, the City Council of the City of Phoenix or any court.

Protest Procedures. Firms responding to disqualification or a procurement outcome are referred to the Code of the City of Phoenix Chapter 2, Article XII, Section 2-187 to 2-190.4, which governs protest procedures utilized throughout the selection process. The procedures may be reviewed through the City of Phoenix website at:

http://www.codepublishing.com/az/phoenix/

A copy of the Protest Policy is also available online at:

https://www.phoenix.gov/administration/departments/streets/careers/business-opportunities.html

Good Standing. Any JOC Contractor that currently contracts with the City must be in good standing for its Statement of Qualifications (SOQ) to be considered responsive. For the purpose of the RFQ, good standing refers to compliance with all contractual provisions, including payment of financial obligations.

Questions - Questions pertaining to this selection process or contract issues should be submitted via the e-Procurement Portal.

Vendor Questionnaire

*Response required

*Response required http://www.codepublishing.com/az/phoenix/ https://www.phoenix.gov/administration/departments/streets/careers/business-opportunities.html

REQUEST FOR QUALIFICATIONS
Project Description
Scope of Work
Small Business Enterprise (SBE) Requirements
Pre-Submittal Meeting
Statement of Qualifications Evaluation Criteria
Submittal Requirements
Grounds for Disqualification
Selection Process and Schedule
General Information
Vendor Questionnaire

File details come from the government source that posted it. Updated .