W91QVN18R0160_Solicitation.pdf

PDF 259 KB Posted

Attached to
Demolish Electrical Equipment K16
Solicitation number
W91QVN18R0160
Issued by

About this file

Solicitation

View the file

Other files

File Type Posted
W91QVN18R0160_Drawing.pdf PDF
W91QVN18R0160_Submittal_Register.xls XLS spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0011166333

a. This is Non-Work Plan Task Order for the follow ing Area I & II MA IDIQ Construction Contractors only.

Contract Numbers W91QVN-18-D-0021, 0022, 0023, 0024, 0025, 0026, 0027, 0028, 0030, 0031, 0032, 0034, 0035, 0040, 0042, 0043, 0044, 0045, 0046, 0047, 0048, 0049, 0050, 0051, 0052, 0162.

b. In the event a contractor is unable to submit an offer in response to this solicitation, the contractor shall submit the "No-Offer Letter" by closing date and time specified in this solicitation.

MS. KANG, SU-CHONG 315-755-3394

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

03-Aug-2018

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________180 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________ Section F

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES X NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________10 Aug 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

CONSTRUCTION & SUPPLY DIVI, UNIT #15289

APO AP 96271

UNITED STATES

W91QVN

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W91QVN18R0160 18

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W91QVN18R0160

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Repair Work (K)

FFP

The contractor shall provide all necessary resources to accomplish the Project No.

118593, Demolish Overhead lines, equipment, street lighting circuits and poles at K16 Air Base in accordance with the statement of work, drawings, and terms and conditions.

FOB: Destination

PURCHASE REQUEST NUMBER: 0011166333

PSC CD: Z2AA

NET AMT

0002 1 Job Construction Work (L)

FFP

Project No. 118593 FOB: Destination

0003 1 Lot Estimated Cost for War Hazard

FFP

is zero(0).

FOB: Destination

Section C - Descriptions and Specifications

SOW

TECHNICAL PROVISIONS - I

PWO TITLE LOCATION

118593 DEMOLISH OVERHEAD LINES, EQUIPMENT, STREET

LIGHTING CIRCUITS AND POLES

K16 AIR BASE

1. DESCRIPTION: The contractor shall provide all labor, tools, equipment, supplies, and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and in accordance with the specifications. The contractor shall replace existing overhead utilities with underground utilities in accordance with the specifications and drawings. The contractor shall verify the locations and dimensions at the job site.

2. PRINCIPAL FEATURES: This project includes, but will not be limited to, the following principal features:

2.1. Maintenance and Repair (K)

2.1.1. ELECTRICAL

2.1.1.1. Remove existing overhead primary lines on the poles.

2.1.1.2. Remove existing overhead secondary lines on the poles

2.1.1.3. Remove existing pole mounted transformers.

2.1.1.4. Remove existing concrete or wood poles and pole mounted lights.

2.2. Construction or New Work (L)

2.2.1. ELECTRICAL

2.1.1.1. Provide new exterior LED type lights on steel pole including lighting control panel, photocell, underground wiring, and others.

TECHNICAL PROVISIONS - II

TECHNICAL DETAIL SPECIFICATIONS

GENERAL: The specification sections listed below are applicable to this project. The specifications are from the “Standard Technical Specifications for O&MA Projects, Korea, Revision 1” (2014 OMA SPECS, REVISION 1), dated 20151030, located on the 411th CSB Web Page, http://www.usfk.mil/Resources/Contracting-with-USFK/. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader® software.

STANDARD TECHNICAL SPECIFICATIONS FOR O&MA

PROJECT TABLE OF CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00.00 10 QUALITY CONTROL

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION AND DECONSTRUCTION

DIVISION 26 – ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT

26 08 00 APPARATUS INSPECTION AND TESTING

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION

26 56 00 EXTERIOR LIGHTING

DIVISION 27 – COMMUNICATIONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

DIVISION 31 – EARTHWORK

31 00 00 EARTHWORK

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS

DIVISION 33 – UTILITIES

33 70 02.00 10 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

TECHNICAL PROVISIONS - III

1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed Price Construction Contract for this project, the Contractor shall comply with the following "SPECIAL CONDITIONS" which form a part of the contract.

2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours, from 1 October through 30 April and from 0730 hours through 1930 hours from 1 May through 30 September, Mondays through Saturdays, except for Korean Legal Holidays: Any proposed change in working hours should be approved by the Contracting Officer (KO) and Contracting Officer's Representative (COR). The contractor will not be permitted any construction work during scheduled (15 days in March and 15 days in August) and unscheduled training/exercises.

The contractor shall remove heavy equipment and field offices from CP Tango and K-16 training sites during the training/exercises periods.

3. WINTERIZATION: The contractor may be required to perform weather sensitive work during the winter season, which may cause additional costs to be incurred for the contractor. These additional costs are the contractor’s responsibility in the event you are required to work during the winter. Your responsibility regarding the preparation of the proposal is to reflect these additional costs in your proposal.

4. ESCORT PRIVILEGE: The contractor shall be responsible for requesting escorting privileges on base passes for Project Manager, Quality Control Manager, Safety Specialist and Foremen. The maximum number of escorted employee will be three persons and the number of escorted vehicle will be one. The contractor shall ensure that the escorting employee has full control of all escorted individuals at all times. Any individual found on the installation unescorted will be removed from the installation and the escort employee’s escorting privileges will be withdrawn.

Any individual removed from this installation will not be authorized further access to this installation.

5. DISPOSAL OF CONSTRUCTION DEBRIS/WASTE MATERIALS: The Contractor shall be required to dispose all construction debris and waste materials in strict accordance with disposal requirements of Section 024100, Demolition and Deconstruction, and local laws and regulations at the Contractor’s responsibility and his own expense. The waste/unsalvageable materials shall be disposed at the location(s) approved and designated by the local authorities.

6. AT/FP TRAINING REQUIREMENTS OF CONTRACTOR:

a. AT Level 1 Training: All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 14 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 14 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.

b. Access and General Protection/Security Policy and Procedures. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204- 9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

c. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

d. iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 14 calendar days of contract award and within 14 calendar days of new employees commencing performance with the results reported to the COR NLT 14 calendar days after contract award.

e. OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.

Section F - Deliveries or Performance

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 calendar days including the procurement of US origin material after notice to proceed. * The time stated for completion shall include final cleanup of the premises.

(End of clause)

Section J - List of Documents, Exhibits and Other Attachments

DRAWING

LIST OF APPLICABLE CONTRACT DRAWINGS

1. GENERAL: The work shall conform to the following contract drawings and OMA standard detail drawings, 2014 (dated 30 November 2015), located on the 411th CSB Web Page http://www.usfk.mil/Resources/Contracting-with-USFK/, all of which form a part of the specifications.

Ring No. Sheet No. Description Date

GENERAL

1 G-001 TITLE SHEET, SCHEDULE OF DRAWINGS & CROSS

REFERENCING CONVENTIONS

11 DEC 15

2 G-002 PROJECT LOCATION PLAN 11 DEC 15

ELECTRICAL

3 E-001 LEGEND, ABBREVIATION & SCOPE OF WORK 11 DEC 15

4 E-002 GENERAL NOTES 11 DEC 15

5 ES101 REMOVAL EXTERIOR PRIMARY/SECONDARY POWER PLAN-1 11 DEC 15

6 ES102 REMOVAL EXTERIOR PRIMARY/SECONDARY POWER PLAN-2 11 DEC 15

7 ES103 REMOVAL EXTERIOR PRIMARY/SECONDARY POWER PLAN-3 11 DEC 15

8 ES104 REMOVAL EXTERIOR PRIMARY/SECONDARY POWER PLAN-4 11 DEC 15

9 ES105 REMOVAL EXTERIOR PRIMARY/SECONDARY POWER PLAN-5 11 DEC 15

10 ES106 REMOVAL EXTERIOR PRIMARY/SECONDARY POWER PLAN-6 11 DEC 15

11 ES107 REMOVAL EXTERIOR PRIMARY/SECONDARY POWER PLAN-7 11 DEC 15

12 ES108 REMOVAL EXTERIOR PRIMARY/SECONDARY POWER PLAN-8 11 DEC 15

13 ES109 REMOVAL EXTERIOR PRIMARY/SECONDARY POWER PLAN-9 11 DEC 15

14 ES110 REMOVAL EXTERIOR PRIMARY/SECONDARY POWER PLAN-10 11 DEC 15

15 ES111 REMOVAL EXTERIOR PRIMARY/SECONDARY POWER PLAN-11 11 DEC 15

16 ES112 REMOVAL EXTERIOR PRIMARY/SECONDARY POWER PLAN-12 11 DEC 15

17 ES113 REMOVAL EXTERIOR PRIMARY/SECONDARY POWER PLAN-13 11 DEC 15

18 ES114 REMOVAL EXTERIOR PRIMARY/SECONDARY POWER PLAN-14 11 DEC 15

19 ES115 NEW EXTERIOR STREET LIGHT PLAN-1 11 DEC 15

20 ES116 NEW EXTERIOR STREET LIGHT PLAN-2 11 DEC 15

21 ES117 NEW EXTERIOR STREET LIGHT PLAN-3 11 DEC 15

22 ES118 NEW EXTERIOR STREET LIGHT PLAN-4 11 DEC 15

23 ES119 NEW EXTERIOR STREET LIGHT PLAN-5 11 DEC 15

24 ES120 NEW EXTERIOR STREET LIGHT PLAN-6 11 DEC 15

25 ES121 NEW EXTERIOR STREET LIGHT PLAN-7 11 DEC 15

26 ES122 NEW EXTERIOR STREET LIGHT PLAN-8 11 DEC 15

27 ES123 NEW EXTERIOR STREET LIGHT PLAN-9 11 DEC 15

28 ES124 NEW EXTERIOR STREET LIGHT PLAN-10 11 DEC 15

29 ES125 NEW EXTERIOR STREET LIGHT PLAN-11 11 DEC 15

30 ES126 NEW EXTERIOR STREET LIGHT PLAN-12 11 DEC 15

31 ES501 DETAILS 11 DEC 15

2. SUBMITTALS: The Contractor shall process submittals in accordance with Section 013300 – SUBMITTAL PROCEDURES. Specific submittal requirements are shown on attached document entitled, “SUBMITTAL REGISTER”, Enclosure 1.

Section K - Representations, Certifications and Other Statements of Offerors

52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)

(a) The offeror certifies that --

(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –

(i) Those prices,

(ii) The intention to submit an offer, or

(iii) The methods of factors used to calculate the prices offered:

(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and

(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.

(b) Each signature on the offer is considered to be a certification by the signatory that the signatory --

(1) Is the person in the offeror's organization responsible for determining the prices offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision; or

(2) (i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provison ______________________________________________________ (insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization);

(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) above have not participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) above; and

(iii) As an agent, has not personally participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision.

(c) If the offeror deletes or modifies subparagraph (a)(2) of this provision, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.

(End of Provision)

252.209-7999 Representation by Corporations Regarding an Unpaid Delinquent Tax Liability or a Felony Conviction under any Federal Law

REPRESENTATION BY CORPORATIONS REGARDING AN UNPAID DELINQUENT TAX LIABILTIY

OR A FELONY CONVICTION UNDER ANY FEDERAL LAW (DEVIATION 2012-00004) (JAN 2012)

(a) In accordance with sections 8124 and 8125 of Division A of the Consolidated Appropriations Act, 2012, (Pub. L. 112-74) none of the funds made available by that Act may be used to enter into a contract with any corporation that-

(1) Has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, where the awarding agency is aware of the unpaid tax liability, unless the agency has considered suspension or debarment of the corporation and made a determination that this further action is not necessary to protect the interests of the Government.

(2) Was convicted of a felony criminal violation under any Federal law within the preceding 24 months, where the awarding agency is aware of the conviction, unless the agency has considered suspension or debarment of the corporation and made a determination that this action is not necessary to protect the interests of the Government.

(b) The Offeror represents that –

(1) It is ( ) is not ( ) a corporation that has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with authority responsible for collecting the tax liability,

(2) It is ( ) is not ( ) a corporation that was convicted of a felony criminal violation under a federal law within the preceding 24 months.

(End of provision)

5152.204-4032 REPRESENTATIONS AND CERTIFICATIONS

(a) SUBCONTRACTING:

If the offeror contemplates subcontracting, it must obtain prior written approval of subcontractor from the PCO or ACO, and list below: (1) the names and addresses of the subcontractor(s), (2) the type of subcontracting, and (3) the estimated price for each subcontract.

(b) AFFILIATED OFFERORS:

(1) Business concerns are affiliates of each other when, either directly or indirectly, one concern controls or has the power to control the other, or a third party controls or has the power to control both.

(2) Each offeror shall furnish, below, the following information:

(i) Whether the offeror has any affiliates;

(ii) The names and addresses of all affiliates of the offeror; and

(iii) The names and addresses of all persons and concerns exercising control or ownership of the offeror and any or all of its affiliates, and whether they are common officers, directors, stockholders holding controlling interest, or otherwise.

AFFILIATED CONCERNS. : (Name, location and, in detail, controlling interest in each)

(c) PRINCIPAL OWNER(S) OR STOCKHOLDER(S):

Each offeror shall list below the name(s) and address(es) of the principal owner(s) or stockholder(s) of the company and percentage of ownership. If a major portion is publicly traded and/or otherwise widely distributed, state that, with the percentage so affected.

(d) STANDARDS OF CONDUCT CERTIFICATION:

This is to certify that, to the best of my knowledge and belief, except as described below, no representative of this firm who deals with US Government employees on any aspect of this procurement is a former US Government employee, to include former US military personnel. I understand that this certification is continuing in nature and places a duty on me and my firm to notify the Contracting Officer of any additional individual(s) who fit the above description prior to the individual's assuming duties.

(i) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________

(ii) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________

(iii) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________

Firm ____________________________________________________ Name _____________________________________________________ Signature __________________________________________________

Title _____________________________________________________ Date of Execution ____________________________________________

(e) TAXES:

(1) References:

(i) Contract clause entitled "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."

(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.

(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.

(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.

(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

This item will be imported specifically for this contract? Yes _____ No _____

(ii) Special Excise Tax:

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

Name of item manufacturer

(iii) Value Added Tax (VAT):

Input VAT on materials purchased for this contract. 10% _____ Input VAT on transportation leased/rented for this contract.10% _____ Input VAT on equipment leased/rented for this contract. 10% _____ Input VAT on services purchased for this contract. 10% _____ Output VAT on total contract amount. 10% _____

(iv) Special Excise (Petroleum) Tax:

No. of U/P Liters w/o Tax Tax/Unit Total Tax Amount Regular Gasoline ________ (L) ________ w________ w_____________ Premium Gasoline ________ (L) ________ w________ w_____________ Diesel ________ (L) ________ w________ w_____________ Other ________ (L) ________ w________ w_____________

(v) Education Tax.

(3) Name of the oil company from which POL products will be purchased:

Oil Company: _________________________________________ (Name only)

(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except ROK MND-funded contracts and delivery orders), Special Excise Tax, and Education Tax.

Signed (Chop)

(f) CERTIFICATIONS AND REPRESENTATIONS

By submitting an offer, each offeror agrees to be bound by all certifications and representations in this solicitation.

The Government reserves the right to require any and all certifications and representations to be completed and signed in hard copy by the successful offeror prior to contract award. Failure of an offeror to complete the certifications and representations within the time directed by the Contracting Officer may result in a determination that the contractor is not a responsible offeror for this acquisition.

Section L - Instructions, Conditions and Notices to Bidders

1. GENERAL INSTRUCTIONS FOR PREPARATION OF PROPOSAL:

The Government intends to award without discussion, but reserves the right to conduct discussions if deemed necessary and to establish a competitive range for efficiency in accordance with FAR 52.215-1(f)(4).

Offeror(s) may, at the discretion of the Government, be asked to provide more information and clarification regarding their proposals. The Government may make a final determination as to whether an offer is acceptable or unacceptable solely based on the proposals as submitted, without requesting any further information. However, if it is deemed necessary the Government may, at its sole discretion, request additional information clarifying but not substantially changing any proposal as submitted.

2. SUBMISSION OF PROPOSAL:

a. FBO SUBMISSION REQUIRED: Offers shall be submitted to the Federal Business Opportunities (FBO) website (https://www.fbo.gov/), or if FBO is not available, email to suchong.kang.ln@mail.mil with the evidence document such as screen shot. The FBO unavailability is limited to only FBO server problem not individual failure/problem. All questions should be emailed to suchong.kang.ln@mail.mil within five (5) days after the solicitation is issued.

b. CLOSING DATE: The electronic offer shall be submitted by 1300 hours on the closing date of RFP.

c. SUBMISSION REQUIREMENTS

i. PRICING PROPOSAL: The pricing proposal must clearly indicate prices for each Contract Line Item Number in Section B - Supplies or Services and Prices.

ii. DETAILED OFFER BREAKDOWN: The detailed offer breakdown must clearly identify all costs that can materially impact the statement of work.

iii. SECTION K - Representations, Certifications and Other Statements of Offerors:

SECTION K-TAXES: Offerors must complete all tax portions of SECTION K. The offeror shall review all expenses to ensure that all applicable taxes are excluded from the overall price. In addition, offerors shall propose exemptions of specific ROK taxes that are legitimate, attributable to the contract, and authorized by the applicable stated references.

SECTION K-OTHER: Offerors must complete all Non-Tax related portions of SECTION K.

d. COMPLIANCE WITH SOLICITATION: Failure to submit the above requirements under SECTION L may be grounds for determining the proposal to be non-compliant. For example, if a detailed offer breakdown is not submitted, the contracting officer will be unable to find the offeror's pricing proposal acceptable and the offeror's proposal will be ineligible for award. Non-compliance will only be cured if the government holds discussions as detailed in SECTION L.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions

Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for--

Date: 8 August 2018 Time: 1330 hours

(c) Participants will meet at in front of building S400, K16

POC is Mr. Kim, Chong Pil, Construction Inspector, (DSN) 724-4490, Commercial) 0503-324-4490.

(End of provision)

5152.236-4011 CONSTRUCTION PRICE RANGE

Pursuant to FAR 36.204 the estimated price range is between $500,000 and $1,000,000.

Section M - Evaluation Factors for Award

1. Electronic offers submitted by 1300 hours on the closing date of RFP shall be considered timely.

2. EVALUATION CRITERIA

The pricing proposal shall be evaluated to determine whether it is complete and reasonable. A complete and reasonable pricing proposal will be deemed acceptable.

The detailed offer breakdown will be used by the contracting officer to determine whether proposed prices are complete and reasonable. A detailed offer breakdown may be used by the contracting officer to determine whether an offeror is able to complete the requirements under the contract, and/or whether discussions will be conducted pursuant to instructions to the offerors.

3. SECTION K - Representations, Certifications and Other Statements of Offerors

SECTION K-TAXES will be evaluated to determine whether it is complete. In addition, propose exemptions of specific ROK taxes will be evaluated to determine whether they are legitimate, attributable to the contract, authorized, and reasonable. A complete SECTION-K that only proposes exemptions of specific ROK taxes that are legitimate, attributable to the contract, necessary to complete the Task Order, do not improperly overstate any proposed tax exemption, authorized, and reasonable will be deemed acceptable.

SECTION K-OTHER will be evaluated to determine whether it is complete. A complete SECTION K-OTHER will be deemed acceptable.

4. BASIS FOR AWARD: Award shall be made to the responsible offeror submitting the lowest priced offer that is evaluated as acceptable for all evaluation criteria.