A21_W91QVN-16-T-0217-0001.docx

DOCX document 31 KB Posted

Attached to
Removal and Replacement of Remote Weather System
Solicitation number
W91QVN16T0217
Issued by

About this file

Amendment 0001

View the file

Other files

File Type Posted
A21_Revised_Statement_of_Work_16T0217-0001.pdf PDF
A21_W91QVN-16-T-0217.docx DOCX document
Statement_of_Work_16T0217.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W91QVN-16-T-0217

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

QUESTIONS AND ANSWERS

Question 1: Looking at the Statement of Work, the last two sections about Warranty Service and Site Visits appear to encompass the items that [redacted] has been doing for the past several years. Are we supposed to include that service into our proposal?

Answer 1:

A one (1) year warranty is required as indicated in the solicitation.

The following sentences from the SOW have been deleted.

6. SITE VISIT

a) The contractor shall conduct all scheduled service on all RWS within the required warranty period.

b) For any irregular reporting from the RWS that by the Government, the COR will contact the contractor to conduct an un-scheduled visit during warrant period.

c) For any un-schedule visit for purpose not covered by the warranty, the contract must contact the Contracting Officer prior to commencing work.

The revised SOW is attached with the deletion stated above.

Question 2: Does the Combined Synopsis/Solicitation under solicitation number W91QVN16T0217 contain requirements similar to a current contract? If possible, please provide the current contract number. Or, is this a new requirement for the government?

Answer 2: The question has no relevance to this solicitation.