Copy_of_Technical_Exhibit_3_Material_list.xls

XLS spreadsheet 60 KB Posted

Attached to
SCHOOL BUENAVENTURA
Solicitation number
W913FT-16-R-0002
Issued by

About this file

LIST MATERIALS

View the file

Other files

File Type Posted
Technical_Exhibit_3.Furniture.dwg DWG drawing
16-R-0002-0002.pdf PDF
16-R-0002-0001.pdf PDF
Escuela_Buenaventura_5.pdf PDF
Escuela_Buenaventura_1.pdf PDF
Escuela_Buenaventura_3.pdf PDF
Escuela_Buenaventura_4.pdf PDF
Escuela_Buenaventura.dwg DWG drawing
Escuela_Buenaventura_2.pdf PDF
16-R-0002.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

School Buenaventura

US EMBASSY BOGOTA, COLOMBIA
MILITARY GROUP
GOVERNMENT ESTIMATE
SCHOOL IN BUENAVENTURA
3,000.0
ItemDescriptionUnitQuantityUnit PriceTotal Value
CONSTRUCTION OF SCHOOL IN BUENAVENTURA
ADRAWINGS
A.01Structural DrawingsEA1.0piso 1piso 2piso 3cubierta piso 1cubierta piso 2
A.02Hydrosanitary and Rainwater DrawingsEA1.0area196.00235.0043.00205.0035.00
A.03Architectural DrawingsEA1.0long50.0063.0032.00
A.03Electrical DrawingsEA1.0h1.201.201.20
A.04Soil studyEA1.060.0075.6038.40
1PRELIMINARIES
1.01Location and laying outm2400.0vigas165.640.250.3514.49
1.02Provisional fencing and campLS1.0
1.03Strip topsoilm320.015.0015.00
1.04Excavationm320.0
1.05Back fill and compactionm320.0
1.06DemolitionLS1.0
2CONCRETE STRUCTURE
2.01Footingm35.0
2.02Foundation beamsm35.0
2.03Slab floor e=0.12M2160.0
2.04Aerial concrete beamsm325.0Aerial beams0.000.000.00
2.05Concrete columns( include reinforcement)m323.0Columns
2.06Sidewalksm280.0Sidewalks
2.07Structural reinforcement (rebar)ml45.0Alfajias and dintels
2.08StairsLS1.0
2.08Slab tank ( include structural soport)m215.0
2.09Elevated reinforced concrete towerLS1.0
2.10Alfajias and dintelsml30.0Alfajias and dintels
3MASONRY
2.11Masonry ( celosia)m2105.0
3.01Conventional Masonrym2100.0
4METALLIC STRUCTURE AND ROOFING
4.01Metallic structure for cover supportm2240.0Foof tiles14.2510.94155.90
4.02Roof tilesm2240.07.242.8520.63
4.03Handrail for aisle and stairsml19.0
5ELECTRICAL SYSTEMwalls tiles12.602.0025.2050.40
5.1Electrical conection
5.1.1Electrical connection (includes transformer, permmit conection if applicable)EA1.0counter5.40
5.1.2Electric meterEA1.0294.0050,00014,700,000
5.1.3Main panel (principal)EA1.0
5.1.4Electrical pole for transformer and main connectionEA1.0
5.2Internal Electrical InstallationsBATHAREAH
5.2.1Electrical conduitml300.0FLOOR TILE10.421.8151.00
5.2.2Electrical wireml900.0walls tiles12.001.82.0024.00
5.2.3Interior lighting fixtures (LED)Unit42.0- 0
5.2.3Interior lights with lamps (LED) restroomUnit8.0- 0
5.2.4Exterior lights with lamps (LED) first and second story aislesUnit18.0- 0
5.2.5Electrical Switches (two zone for classroom lights and two zone per classroom fans, first and second story aisles, office, and restrooms)Unit17.0SALON
5.2.6Electrical outletsUnit45.0FLOOR TILE P1162.00186.00
5.2.7Electrical outlets (GFCI)Unit2.0
5.2.8Four wooden blade 48 inches fanUnit17.0hall39.002.00
5.2.9Emergency lightsUnit9.0hall39.002.00
5.2Electrical protection
5.3.1Grounded systemEA1.0
5.3.2Lighting protection systemEA1.0Placa
5.3.3Testing and LaunchingEA1.0e
6HYDRAULIC, SANITARY AND RAINWATER REDConcrete Volume
6.01Water supply red( connecting to the main and red aprox 1.5 KM, include meter)EA1.0
6.02Internal water supply network (restroom and elevated tank)EA1.0
6.03Rainwater network (Ducts, downpipes)EA1.0Excavation
6.04Storage tank 4000 ltEA4.0
6.05Septic system (include leachfield, solid chamber, and liquid chamber)EA1.0
7FLOORSBackfill
7.01Floor tile for classroomm2311.0
7.02Floor tile aislem280.0
7.03Floor tile bathm222.0
7.04Floor tile officem222.0
8FINISHINGViga correa
8.01Stuccom250.0
8.02Exterior and Interior Paintm250.0
8.03Wall tile bath (8 ft height)m245.0
8.04Toilets (include tank, seat, and lid)EA4.0
8.05Sinks ( include faucet and drain)EA4.0
8.06Toilet paper holdersEA4.0
8.07Concrete countertop bath ( finished in polished granite)ml5.5
8.08Frame doors and doors (includes commercial lock and stainless steel hardware and accessories, mininum door gauge 16)EA7.0
8.09Frame doors and doors for restroom stalls (includes commercial latches and stainless steel hardware and accessories, mininum aluminum door gauge 18)EA4.0
8.10Restroom stallEA2.0
8.11Student desk (include book shelf, pencil holder, and working top)EA100.0
8.12Student chair (include back support, seat, and book shelf)EA100.0
8.13Teacher desksEA4.0
8.14Teacher chairEA4.0
8.15Office table (seating 6)EA1.0
8.16Office chair for tableEA6.0
8.17Office wall and base cabinets. Cabinet includes shelves, doors, hardware, and knobs.EA1.0
8.18Classroom shelvesEA14.0
8.19Restroom mirrorEA2.0
8.20Drop ceilingLS1.0
9MISCELLANEOUS WORKSMasonry
9.01Commemorative plateEA1.0Area
9.02Flags (include base, three flag poles, and three flags in accordance with Ministry of Education standards). Connecting sidewalk shall include access to the flag area.EA1.0
9.03Boards (1.20m x 2.40m)EA8.0
9.04Informative BannerEA1.0
9.05General cleaningEA1.0
SUM OF ITEMS
Administration and Unforeseen (A,U)
TOTAL COST
SUM OF ITEMS
Estimated IVA (TAXES) for Contractor
Estimated Profit for Contractor
TOTAL COST150,000
Execution Time in Calendar Days180 days

&LGOVERNMENT ESTIMATE - SCHOOL CONSTRUCTION IN CAÑASGORDAS, ANTIOQUIA&R&P / &N