Copy_of_Technical_Exhibit_3_Material_list.xls
XLS spreadsheet 60 KB Posted
- Attached to
- SCHOOL BUENAVENTURA
- Solicitation number
- W913FT-16-R-0002
About this file
LIST MATERIALS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Technical_Exhibit_3.Furniture.dwg | DWG drawing | |
| 16-R-0002-0002.pdf | ||
| 16-R-0002-0001.pdf | ||
| Escuela_Buenaventura_5.pdf | ||
| Escuela_Buenaventura_1.pdf | ||
| Escuela_Buenaventura_3.pdf | ||
| Escuela_Buenaventura_4.pdf | ||
| Escuela_Buenaventura.dwg | DWG drawing | |
| Escuela_Buenaventura_2.pdf | ||
| 16-R-0002.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
School Buenaventura
| US EMBASSY BOGOTA, COLOMBIA | ||||||||||||
| MILITARY GROUP | ||||||||||||
| GOVERNMENT ESTIMATE | ||||||||||||
| SCHOOL IN BUENAVENTURA | ||||||||||||
| 3,000.0 | ||||||||||||
| Item | Description | Unit | Quantity | Unit Price | Total Value | |||||||
| CONSTRUCTION OF SCHOOL IN BUENAVENTURA | ||||||||||||
| A | DRAWINGS | |||||||||||
| A.01 | Structural Drawings | EA | 1.0 | piso 1 | piso 2 | piso 3 | cubierta piso 1 | cubierta piso 2 | ||||
| A.02 | Hydrosanitary and Rainwater Drawings | EA | 1.0 | area | 196.00 | 235.00 | 43.00 | 205.00 | 35.00 | |||
| A.03 | Architectural Drawings | EA | 1.0 | long | 50.00 | 63.00 | 32.00 | |||||
| A.03 | Electrical Drawings | EA | 1.0 | h | 1.20 | 1.20 | 1.20 | |||||
| A.04 | Soil study | EA | 1.0 | 60.00 | 75.60 | 38.40 | ||||||
| 1 | PRELIMINARIES | |||||||||||
| 1.01 | Location and laying out | m2 | 400.0 | vigas | 165.64 | 0.25 | 0.35 | 14.49 | ||||
| 1.02 | Provisional fencing and camp | LS | 1.0 | |||||||||
| 1.03 | Strip topsoil | m3 | 20.0 | 15.00 | 15.00 | |||||||
| 1.04 | Excavation | m3 | 20.0 | |||||||||
| 1.05 | Back fill and compaction | m3 | 20.0 | |||||||||
| 1.06 | Demolition | LS | 1.0 | |||||||||
| 2 | CONCRETE STRUCTURE | |||||||||||
| 2.01 | Footing | m3 | 5.0 | |||||||||
| 2.02 | Foundation beams | m3 | 5.0 | |||||||||
| 2.03 | Slab floor e=0.12 | M2 | 160.0 | |||||||||
| 2.04 | Aerial concrete beams | m3 | 25.0 | Aerial beams | 0.00 | 0.00 | 0.00 | |||||
| 2.05 | Concrete columns( include reinforcement) | m3 | 23.0 | Columns | ||||||||
| 2.06 | Sidewalks | m2 | 80.0 | Sidewalks | ||||||||
| 2.07 | Structural reinforcement (rebar) | ml | 45.0 | Alfajias and dintels | ||||||||
| 2.08 | Stairs | LS | 1.0 | |||||||||
| 2.08 | Slab tank ( include structural soport) | m2 | 15.0 | |||||||||
| 2.09 | Elevated reinforced concrete tower | LS | 1.0 | |||||||||
| 2.10 | Alfajias and dintels | ml | 30.0 | Alfajias and dintels | ||||||||
| 3 | MASONRY | |||||||||||
| 2.11 | Masonry ( celosia) | m2 | 105.0 | |||||||||
| 3.01 | Conventional Masonry | m2 | 100.0 | |||||||||
| 4 | METALLIC STRUCTURE AND ROOFING | |||||||||||
| 4.01 | Metallic structure for cover support | m2 | 240.0 | Foof tiles | 14.25 | 10.94 | 155.90 | |||||
| 4.02 | Roof tiles | m2 | 240.0 | 7.24 | 2.85 | 20.63 | ||||||
| 4.03 | Handrail for aisle and stairs | ml | 19.0 | |||||||||
| 5 | ELECTRICAL SYSTEM | walls tiles | 12.60 | 2.00 | 25.20 | 50.40 | ||||||
| 5.1 | Electrical conection | |||||||||||
| 5.1.1 | Electrical connection (includes transformer, permmit conection if applicable) | EA | 1.0 | counter | 5.40 | |||||||
| 5.1.2 | Electric meter | EA | 1.0 | 294.00 | 50,000 | 14,700,000 | ||||||
| 5.1.3 | Main panel (principal) | EA | 1.0 | |||||||||
| 5.1.4 | Electrical pole for transformer and main connection | EA | 1.0 | |||||||||
| 5.2 | Internal Electrical Installations | BATH | AREA | H | ||||||||
| 5.2.1 | Electrical conduit | ml | 300.0 | FLOOR TILE | 10.42 | 1.8 | 151.00 | |||||
| 5.2.2 | Electrical wire | ml | 900.0 | walls tiles | 12.00 | 1.8 | 2.00 | 24.00 | ||||
| 5.2.3 | Interior lighting fixtures (LED) | Unit | 42.0 | - 0 | ||||||||
| 5.2.3 | Interior lights with lamps (LED) restroom | Unit | 8.0 | - 0 | ||||||||
| 5.2.4 | Exterior lights with lamps (LED) first and second story aisles | Unit | 18.0 | - 0 | ||||||||
| 5.2.5 | Electrical Switches (two zone for classroom lights and two zone per classroom fans, first and second story aisles, office, and restrooms) | Unit | 17.0 | SALON | ||||||||
| 5.2.6 | Electrical outlets | Unit | 45.0 | FLOOR TILE P1 | 162.00 | 186.00 | ||||||
| 5.2.7 | Electrical outlets (GFCI) | Unit | 2.0 | |||||||||
| 5.2.8 | Four wooden blade 48 inches fan | Unit | 17.0 | hall | 39.00 | 2.00 | ||||||
| 5.2.9 | Emergency lights | Unit | 9.0 | hall | 39.00 | 2.00 | ||||||
| 5.2 | Electrical protection | |||||||||||
| 5.3.1 | Grounded system | EA | 1.0 | |||||||||
| 5.3.2 | Lighting protection system | EA | 1.0 | Placa | ||||||||
| 5.3.3 | Testing and Launching | EA | 1.0 | e | ||||||||
| 6 | HYDRAULIC, SANITARY AND RAINWATER RED | Concrete Volume | ||||||||||
| 6.01 | Water supply red( connecting to the main and red aprox 1.5 KM, include meter) | EA | 1.0 | |||||||||
| 6.02 | Internal water supply network (restroom and elevated tank) | EA | 1.0 | |||||||||
| 6.03 | Rainwater network (Ducts, downpipes) | EA | 1.0 | Excavation | ||||||||
| 6.04 | Storage tank 4000 lt | EA | 4.0 | |||||||||
| 6.05 | Septic system (include leachfield, solid chamber, and liquid chamber) | EA | 1.0 | |||||||||
| 7 | FLOORS | Backfill | ||||||||||
| 7.01 | Floor tile for classroom | m2 | 311.0 | |||||||||
| 7.02 | Floor tile aisle | m2 | 80.0 | |||||||||
| 7.03 | Floor tile bath | m2 | 22.0 | |||||||||
| 7.04 | Floor tile office | m2 | 22.0 | |||||||||
| 8 | FINISHING | Viga correa | ||||||||||
| 8.01 | Stucco | m2 | 50.0 | |||||||||
| 8.02 | Exterior and Interior Paint | m2 | 50.0 | |||||||||
| 8.03 | Wall tile bath (8 ft height) | m2 | 45.0 | |||||||||
| 8.04 | Toilets (include tank, seat, and lid) | EA | 4.0 | |||||||||
| 8.05 | Sinks ( include faucet and drain) | EA | 4.0 | |||||||||
| 8.06 | Toilet paper holders | EA | 4.0 | |||||||||
| 8.07 | Concrete countertop bath ( finished in polished granite) | ml | 5.5 | |||||||||
| 8.08 | Frame doors and doors (includes commercial lock and stainless steel hardware and accessories, mininum door gauge 16) | EA | 7.0 | |||||||||
| 8.09 | Frame doors and doors for restroom stalls (includes commercial latches and stainless steel hardware and accessories, mininum aluminum door gauge 18) | EA | 4.0 | |||||||||
| 8.10 | Restroom stall | EA | 2.0 | |||||||||
| 8.11 | Student desk (include book shelf, pencil holder, and working top) | EA | 100.0 | |||||||||
| 8.12 | Student chair (include back support, seat, and book shelf) | EA | 100.0 | |||||||||
| 8.13 | Teacher desks | EA | 4.0 | |||||||||
| 8.14 | Teacher chair | EA | 4.0 | |||||||||
| 8.15 | Office table (seating 6) | EA | 1.0 | |||||||||
| 8.16 | Office chair for table | EA | 6.0 | |||||||||
| 8.17 | Office wall and base cabinets. Cabinet includes shelves, doors, hardware, and knobs. | EA | 1.0 | |||||||||
| 8.18 | Classroom shelves | EA | 14.0 | |||||||||
| 8.19 | Restroom mirror | EA | 2.0 | |||||||||
| 8.20 | Drop ceiling | LS | 1.0 | |||||||||
| 9 | MISCELLANEOUS WORKS | Masonry | ||||||||||
| 9.01 | Commemorative plate | EA | 1.0 | Area | ||||||||
| 9.02 | Flags (include base, three flag poles, and three flags in accordance with Ministry of Education standards). Connecting sidewalk shall include access to the flag area. | EA | 1.0 | |||||||||
| 9.03 | Boards (1.20m x 2.40m) | EA | 8.0 | |||||||||
| 9.04 | Informative Banner | EA | 1.0 | |||||||||
| 9.05 | General cleaning | EA | 1.0 | |||||||||
| SUM OF ITEMS | ||||||||||||
| Administration and Unforeseen (A,U) | ||||||||||||
| TOTAL COST | ||||||||||||
| SUM OF ITEMS | ||||||||||||
| Estimated IVA (TAXES) for Contractor | ||||||||||||
| Estimated Profit for Contractor | ||||||||||||
| TOTAL COST | 150,000 | |||||||||||
| Execution Time in Calendar Days | 180 days |
&LGOVERNMENT ESTIMATE - SCHOOL CONSTRUCTION IN CAÑASGORDAS, ANTIOQUIA&R&P / &N