Fence Solicitations Q_A UPDATED 18AUG2020.xlsx

XLSX spreadsheet 9 KB Posted

Attached to
Fence Replacement at CJAGMTC Federal contract opportunity
Solicitation number
W91364-20-B-0002
Issued by
Department of the Army Ohio Army National Guard

About this file

This document contains a solicitation for fence replacement services at Camp James A. Garfield Joint Military Training Center in Ravenna, Ohio. The scope of work involves removing and replacing approximately 6,175 linear feet of existing perimeter security fence with new posts, fabric, top rail, outriggers, bottom wire and barbed wire. It also includes clearing vegetation within 10 feet of the new fence line and installing temporary fencing during construction. Bids are due at a specified location by August 31, 2020. The selected contractor will be responsible for grading and seeding disturbed areas, and meeting applicable safety and antiterrorism standards. This project provides an opportunity for SDVOSB contractors, but may be opened to unrestricted competition if adequate SDVOSB bids are not received. The soliciting agency is the Department of the Army Ohio Army National Guard.

View the file

Other files for this federal contract opportunity

Other files attached to Fence Replacement at CJAGMTC, newest first.
File Type Posted
SF 1409 Signed 8SEP.pdf PDF
Fence Replacement Amendment 003.pdf PDF
91364-20-B-0002_Fence sign in sheet_13-08-2020.pdf PDF
Fence Solicitations Q_A UPDATED 25AUG2020_Answered.xlsx XLSX spreadsheet
Fence Solicitation Modification 2.0 UPDATED 18AUG2020.docx DOCX document
CJAGJMTC Fence Solicitation Modification.pdf PDF
10_BidForm_CJAG_Perimeter_Fence_rem_rep.docx DOCX document
RFI Template.pdf PDF
CJAGMTC Fence Solicitation.pdf PDF
9_AF Form 66_3916441_Perimeter_Fence_rem rep.xlsx XLSX spreadsheet
CJAGJMTC_SOW_Perimeter_Fence_Rep_3916441_.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

NumberQuestionsAnswers
1Can the bid be submitted via e-mail?No - bids are to be put in the drop box at the bid opening
2If so, What is the email address for submission?Bid opening will be August 31st under the solar canopy on CJAGMTC - across from where we met for the site visit.
3Is attached PDF format acceptable for bid submission?Use the bid form that is included in the solicitation
4Is the fence Selvage knuckle on top twist on bottom?Per section Article 4.1 a iv the top and bottom selvage shall twist
5Is the fence grounding required at every end and terminal post?Fence grounding is normally required if within 16 feet of a power source or 20 feet of a power line. Contractor shall assume that the grounding will be required in 15 locations for lighting and power considerations. Locations shall be coordinated with OHARNG.
6Is there specific gate hardware required other than non-removable hinges?Contractor shall also provide lockable latching mechanisms to be approved by the OHARNG.
7Are there any specifics on temporary fence?Temporary fence shall be 6 foot high chain link.
8What is considered secure?No openings in the fence that would be passable by a large animal or human.
9Can you give us more detail on the clearing specifications for this project? Are we to trim that trees that are not being cut down in order to install the new fence? If so, how far up are we allowed to trim and how many will this entail? Are we clearing on all alternatives or only the base bid?Per SOW section Article 2.1.1 the contractor is to clear and grub a 10' area out side the fence. This shall include a 40' high area for an envelope over the fence.

-Trees that fall in the 10' by 40' envelope shall be trimmed.

-See answer above for height of 40'. It is unknown how many trees this will entail, however using the overall length of fence and the 10' clear zone there are approximately 5 acres of area to be cleared, trimmed and grubbed. Please see Environmental Procedures on how to properly dispose of clearing debris.

-Clearing is assumed on all sections and prorated amount shall be applied to each alternate/option.