Solicitation_W912WJ18Q0151.pdf

PDF 1 MB Posted

Attached to
EBL Morse Road Bridge Repair
Solicitation number
W912WJ18Q0151
Issued by

About this file

Solicitation

View the file

Other files

File Type Posted
Amendment_W91WJ18Q0151-0004.pdf PDF
Amendment_W91WJ18Q0151-0003.pdf PDF
Amendment_W91WJ18Q0151-0002.pdf PDF
Amendment_W91WJ18Q0151-0001.pdf PDF
Photos.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EAST BRIMFIELD LAKE PROJ

KEITH BEECHER

24 RIVERVIEW AVE

FISKDALE MA 01518-1243

TEL: 978-318-8405 FAX: 508-987-3105

REQUEST FOR QUOTATIONS

(THIS IS NOT AN ORDER) 1

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED RATING

W912WJ18Q0151 16-Aug-2018 5a. ISSUED BY

8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this

Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State, and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e) (f)

SEE SCHEDULE

AMOUNT

% No. %

NOTE: Additional provisions and representations [ ] are [ ] are not attached.

13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

15. DATE OF

QUOTATION

16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)

TELEPHONE NO.

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)

PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)

THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE

6. DELIVER BY (Date)

SEE SCHEDULE

AND/OR DMS REG. 1

UNDER BDSA REG. 2

4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE

REQUEST NO.

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

9. DESTINATION (Consignee and address, including ZIP Code)

7. DELIVERY

[ ]X FOB

DESTINATION

[ ] OTHER

(See Schedule)

27-Aug-2018(Date)

PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.

978-318-8814ROBERT C GARRAHAN

(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:

d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS

W912WJ18Q0151

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job EBL Morse Road Bridge Rehab

FFP

The contractor shall furnish all equipment, materials and labor for access bridge concrete wearing surface removal and new bituminous hot mix asphalt wearing surface replacement (approximately 62’ x 20’) at East Brimfield Dam in Fiskdale, MA, in accordance with the attached Scope of Work.

FOB: Destination

NET AMT

QUOTATION INSTRUCTIONS

*SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A QUOTE. SEE CLAUSE

52.236-27 FOR ADDITIONAL INFORMATION. Offerors are notified that the basis for award is price alone.

*PLEASE DIRECT QUESTIONS TO ROBERT GARRAHAN AT (978) 318-8195 or robert.c.garrahan @usace.army.mil. ANY INFORMATION RECEIVED AT THE SITE VISIT

WHICH CONFLICTS WITH THIS SOLICITAION SHOULD BE BROUGHT TO THE ATTENTION OF MR.

GARRAHAN. THE SOLICITATION AND RESULTING CONTRACT SHALL BE THE GOVERNING

DOCUMENT IN ALL CASES.

** QUOTES CAN BE FAXED OR E-MAILED TO ROBERT GARRAHAN AT (978) 318-8207 or robert.c.garrahan@usace.army.mil. E-mail is the preferred method.

NOTE 1: In accordance with FAR Part 28.102-1(b)(1), the Contractor will be required to provide one of the following payment protections for all construction contracts greater than $35,000.00 but not greater than $150,000.00.

(i) Payment bond

(ii) Irrevocable letter of credit

A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.

NOTE 2:

QUOTATION INSTRUCTIONS:

1. If subcontractor will be used for this work, please provide company name and credentials/qualifications:

2. Contractors must be registered in the System for Awards Management (SAM) database (www.SAM.gov) to receive an award. (Formerly the Central Contractor Registration (CCR) database and the On-Line Representations and Certifications (ORCA).) Any reference to CCR or ORCA in any clause or provision is referring to the www.sam.gov website. Please note that Google and Google Chrome are not supported browsers for SAM registration. Mozilla FireFox, Safari, and Internet Explorer are supported browsers.

SAM.gov registration takes approximately 3 weeks (DUNS registration 1-2 business days; CAGE code validation up to 10 business days; IRS validation and overall submission 7-10 business days). It is the contractor’s responsibility to track SAM.gov registration and follow-up with required tasks. SAM.gov registration does not have to be “active” to be able to submit a quote. However, contractors must have an active record before a contract award can be made. If SAM.gov registration is not completed in a timely fashion in accordance with the SAM.gov timelines, the Government reserves the right to disqualify the quote in accordance with FAR 52.204-7(d).

Contractors should note that 30 September is the end of the Government fiscal year. As that date approaches, the Government will be unable to delay year-end contract awards and will have to disqualify contractors without an active SAM.gov registration. If you have any questions, please contact the aforementioned point of contact.

3. Provide business DUNS number: _______________________________ (phone 800- 333-0505 for DUNS).

4. Provide business CAGE code: __________________________________

5. Tax Identification Number: ___________________________________

6. Contractors shall provide completed FAR clause 52.204-8 (Annual Representations and Certifications) found in Section K of this solicitation with their quote, if the Contractors have not completed their annual representations and certifications electronically via the SAM website at www.sam.gov. (See Paragraph 2 above)

7. Contractors are not required to submit an Accident Prevention Plan (APP) with their quote. The successful offeror will be required to submit this document upon award. The APP must be accepted by the Government Designated Authority prior to the preconstruction conference.

Section C - Descriptions and Specifications

SOW

EAST BRIMFIELD DAM PROJECT

MORSE ROAD BRIDGE REHABILITATION

U.S. ARMY CORPS OF ENGINEERS

FISKDALE, MA

STATEMENT OF WORK

AUGUST 2018

I. GENERAL

1. Scope

Furnish all equipment, materials and labor for access bridge concrete wearing surface removal and new bituminous hot mix asphalt wearing surface replacement (approximately 62’ x 20’) at East Brimfield Dam in Fiskdale, MA for the purpose of facility maintenance.

2. Location The required services shall be performed at the following project site location, the Morse Road Bridge, located in Holland, Massachusetts. This bridge is located within the East Brimfield Dam Flood Reduction Facility with the office at 24 Riverview Avenue, Fiskdale, Massachusetts.

3. Site Visits and Requests for Information Contact the Technical Point of Contact, Keith W. Beecher, 978-318-8405 or keith.w.beecher@usace.army.mil) to arrange a site visit.

4. Schedule The period of performance shall be 120 days from the Notice to Proceed date. The project area will be open to the contractor Monday through Friday 7:00 AM to 3:30 PM and all work must be done during those hours unless additional hours are approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays.

5. Safety

The contractor will comply with all pertinent provisions of the latest edition of the U.S. Army Corps of Engineers Safety and Health Requirements COE EM 385-1-1. A copy of COE EM 385-1-1 is available for reference at the project office or the manual may be viewed at the following link http://www.usace.army.mil/SafetyandOccupationalHealth/EM38511,2008BeingRevised.aspx The contractor shall also comply with all OSHA work safety standards. The project staff can and will order the cessation of work at any time should the safety of employees and visitors become jeopardized.

6. Preconstruction Conference

Prior to the start of any work, the Technical Point of Contact will schedule and conduct a “Preconstruction Conference”. The Contractor’s Project Manager and Quality Control Personnel will attend this meeting. This conference will be held at the time and location agreeable to the government and contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Preconstruction conference the contractor shall provide to the name of the project superintendent with a telephone number for project coordination.

The following is a general list of items for discussion during this Preconstruction Conference:

a. Authority of the Technical Point of Contact.

b.Contractor’s Safety Program (including sub-contractors).

c. Accident Prevention Plan and Activity Hazard Analysis (Submitted & accepted prior to start of work on site) d.Weekly Safety Meetings (Documented on NED Form 251)

e. Accident Reporting (ENG Form 3394)

f. Safety Data Sheet (SDS) requirements g.Correspondence, Communication and Administrative Procedures.

h.Invoice and payment.

7. Permits

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

8. Security The contractor will comply with all established security policies at East Brimfield Dam Project. Due to periods of heightened security that may affect the access to the areas covered under this contract, areas may be subject to periodic closures, which in turn may reduce or inhibit the Contractor’s ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent service in an area. The Contractor shall be given at least 24 hour notice of any such closure.

9. Payment

Payment shall be made on a lump sum basis. After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due. For jobs greater than 30 days the contractor may request progress payment.

This invoice may be mailed to:

US Army Corps of Engineers 24 Riverview Avenue Fiskdale, MA 01518 or emailed to keith.w.beecher@usace.army.mil

10. Damage to Government and Private Property The Contractor shall be responsible for restoring any Government facilities or structures damaged as a result of the firm’s operation. The Contractor shall also be responsible for any damage to private property or injury to any person as a result of the firm’s operations. The Contractor shall notify the Technical Point of Contact immediately of damage to Government and private property and injury to any person resulting from the firms’ operation.

11. Point of Contact Requirements The Contractor shall provide to the Technical Point of Contact a telephone number and a point of contact for discussion of any contractual matters.

II. TECHNICAL

1. General:

Bridge History:

The Old Morse Road Bridge carries Old Morse Road over the Quinebaug River at the East Brimfield Lake Reservoir in Holland, Massachusetts. The structure is a three span, continuous, non-composite steel stringer bridge built in 1939.

Each span measures 20'-0" center to center of bent and the total length of the bridge is approximately 62'-0". Old Morse Road ends 200' beyond the bridge. The bridge is closed to vehicular traffic and functions only as a pedestrian bridge and for USACE vehicles only. The roadway width across the bridge is 20'-0" between concrete curbs.

The superstructure consists of six wide flange rolled beams spaced at 4'-2" on center. The four interior stringers are 16WF40 sections and the fascia stringers are 16WF45 sections.

The stringers support a 61/2" reinforced concrete deck, overlaid with 2" of bituminous concrete on a 1" gravel base. The substructure consists of two gravity type concrete abutments with “U” wing walls and two timber pile bents. The two bents consist of six timber piles each with cross bracing and timber caps.

Rating of the bridge is as follows:

Type: H 3 3S2 Inventory: 15 Ton 20 Ton 31 Ton Operating: 27 Ton 35 Ton 54 Ton

Bridge bituminous wearing surface, curbs and parapets, bridge rails, approach guardrails, pile cap hardware existing conditions:

The access bridge is inspected routinely. The last inspection was in 2014.The results of this inspection are as follows.

A. Approach Roadway and Guardrails

Both the east and west approach roadways remain in poor condition. Sections of bituminous pavement are missing at the east approach for the full width of the bridge (see Photo 1). The differential between the approach pavement and the bridge deck is at least 4" at the east approach on the south side. The concrete posts at the guardrails remain in poor condition. There are no cables.

B. Deck

The overall condition of the concrete bridge deck is fair. However, the bituminous wearing surface, curbs and parapets continue to deteriorate. Heavy vegetation is growing at both edges of the bridge deck (see Photo 2). Pavement on either side of the bridge deck is missing, measuring up to 4' wide. There is about 4” of fill/pavement on top of the deck.

The underside of the deck is in good condition with only minor honeycombing along edges of top flanges of stringers. The bridge rails are in fair condition with moderate surface rusting and pitting. The condition of the spalling and efflorescence at the south parapet and curb is severe (see Photo 3). There is a large area of deteriorated concrete at the east end of the parapet/curb. This area is approximately 9'-10' long x 2' high x 2" deep and continues to worsen.

C. Substructure

Minor debris was noted on the bridge seats. There are some missing nuts and washers on the thru bolts at the pile caps.

Note contractor is responsible for final measurements for this contract.

Requests for Information:

Requests concerning the work of this project should be directed to the Technical Point of Contact at (978) 318-8405 or keith.w.beecher@usace.army.mil

References:

Contractor’s work must meet or exceed industry standards and the following references for the removal and installation of new bridge bituminous hot mix asphalt wearing surface, guardrail, concrete repairs.

U.S. Government Unified Facilities guide specifications and criteria o Division 03, Concrete o Section 32, Asphalt o United facilities criteria, UFC 3-2500, Standard practice for concrete pavements o UFC 3-270-01 Asphalt Maintenance and Repair

Department of the Army and Air Force o Technical Manual, TM 5-600, Bridge Inspection, Maintenance and

Repair Department of the Army, Corps of Engineers o Transportation Systems Center TSC Report 13-1 State of Connecticut Department of Transportation o Construction Manual, Volume 2 ver. 2.2, Bituminous Pavements o CTDOT Standard Sheet for Metal Beam Rail Type R-B 350

Commonwealth of Massachusetts Department of Transportation o Design and construction guidelines and standards Division 32

Asphalt Paving

ASTM

o Guidelines and standards for hot dip galvanizing, preparation, treatment

Submittals:

Although the Government technically reviews submissions required by this scope of work, it is emphasized that the Contractor’s work must be prosecuted using proper internal controls and review procedures. The documents identified below must be prepared in accordance with the applicable standards, submitted to the Technical Point of Contact for review and accepted by the government prior to the commencement of any field activities.

Product specification sheets for:

1. Waterproofing bridge deck membrane system.

2. Asphalt bituminous material/mix overlay.

3. Concrete waterproof sealer.

4. Concrete mix for curbing, parapet repair.

Site Traffic Control plan.

Accident Prevention Plan (APP).

Activity Hazard Analysis (AHA).

Clean Up:

The Contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials. Upon completing work in an area the contractor shall remove any tools, equipment, and materials that are not the property of the government.

Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government.

Government Resources:

The contractor is responsible for providing all materials to complete the project. Unless specified in the contract, the Government will not provide any equipment, telephone services or other resources.

Omissions:

This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

Quality Assurance:

The contractor is responsible for the quality control of the contract work. The government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.

Other Contracts:

The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor, or by Government employees.

Environmental Protection:

Containers for excess and/ or waste materials, rubbish, etc. shall be provided by the contractor at the site, and the site will be inspected/ cleaned on a daily basis. No burning is permissible. Water, air and land resources shall not be adversely impacted during the course of the work. Contractor will take necessary steps to ensure all federal, state, and local environmental regulatory requirements are met.

Receiving and Storing Materials:

The contractor is responsible for protecting any stored material until it is placed in service. The contractor is responsible for receiving and unloading of delivered goods.

Government employees will not receive material or supplies for the contractor and will not be responsible for damage to contractor equipment or material.

2. Products:

Environmentally Preferred Products:

All products provided by the contractor must meet the recycled content requirements set forth by the EPA. Products that fall under these requirements are things such as cement, concrete, non-pressure pipes, etc. The list of approved products is periodically updated, please check the EPA website for the most current list:

https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program#products.

Furthermore, the contractor should also meet the BioPreferred Program requirements set in place by the USDA. These will include products such as wood and concrete sealers, erosion controlled materials, sorbents, etc. For the most current list of products, please visit: https://www.biopreferred.gov/BioPreferred/faces/catalog/Catalog.xhtml.

a. Guard Rail

i. Guardrail and associated posts, hardware will be galvanized; ends will have returns. Will be Steel Beam Highway Guard Rail Type SS, single faced, 6’ foot 3” post spacing, with rubber block spacer block for each post and rail attachment. Will be attached to bridge.

b. Curbing and parapet repair material.

i. Sika Crete 211 SCC Plus, or equal. Sika Crete 211 SCC Plus is a one-component, cementitious, polymer-modified, self-consolidating concrete mix with an integral migrating corrosion inhibitor, the color is gray.

c. Concrete sealant for curbing and parapet.

i. Sika Guard 705L or equal. Sika Guard 705L is a one part low viscosity, solvent free, reactive impregnation for concrete and cementitious substrates based on silane technology.

d. Bridge Deck waterproof membrane

i. Product will meet or exceed referenced specifications for concrete and bituminous hot mix asphalt bridge deck waterproof membrane.

ii. Bridge Preservation LCC, Bridge Deck Membrane meets these requirements.

iii. Membrane color to be approved by technical point of contact.

e. Bituminous hot mix asphalt material/mix.

i. Product will meet or exceed referenced specifications for bituminous hot mix asphalt for use as a bridge deck wearing surface.

ii. Superpave HMA S0.25 for leveling course on bridge

iii. Superpave HMA S0.5 bridge surface course, wearing course for approaches

iv. Superpave HMA S1 base course, approaches

3. Execution:

Traffic (primarily foot traffic, horse, staff service vehicles) will be signed and blocked by installing temporary fencing. It will be the responsibility of the contractor to block and maintain a safe working area, ensuring no one unauthorized enters the work site.

a. Removal and disposal of guard posts, any cable from both bridge approaches.

b. Removal of bridge deck guardrail to galvanizing plant for removal of all paint and rust and then to be hot dip galvanized.

c. Concrete repairs to:

i. Spalling and efflorescence at the south parapet and curb (see Photos 3, 4).

ii. Deteriorated concrete at the east end of the parapet/curb. This area is approximately 9'-10' long x 2' high x 2" deep.

iii. Concrete curbing and parapet repairs will be formed to match the original lines of the bridge.

d. Remove efflorescence, staining from bridge curbing and parapet surfaces.

i. Power wash and brush effloresce from bridge curb, parapet.

e. Application of concrete sealant to curbing, parapet concrete surfaces.

f. Reinstallation of bridge railings can be done at any time, after application of concrete sealant to curbing, and concrete repairs have cured.

g. Removal and disposal of bridge wearing surface.

i. Prepare area around bridge for demolition and removal of the asphalt wearing surface material.

ii. The contractor is responsible for the removal and disposal of all materials removed from the project site. Materials will be disposed offsite according to all local, state and federal regulations.

h. Install waterproof membrane on bridge.

i. Membrane shall be applied according to the manufacturer.

ii. Concrete surfaces will be cleaned, repaired and prepared in accordance with industry standards and membrane manufacturer for the proper bonding, adhesion and curing of the new waterproof membrane, membrane applied where appropriate.

iii. Seal top of bridge deck with waterproofing system primer and or bonding agent.

iv. Apply waterproof membrane on the deck and curbing, thickness shall be approved by membrane manufacture.

v. Membrane will terminate on the curbing above the top of the final proposed asphalt overlay.

vi. Membrane termination line on the curb shall be straight and clean.

i. Install new bituminous hot mix asphalt wearing surface on bridge.

i. The installation shall be in accordance with industry standards and to all referenced specifications in this scope/contract for bridge wearing surface installations and curing.

ii. Bituminous hot mix asphalt will be installed with Superpave HMA S0.25 for leveling course of 1” followed by Superpave HMA S0.5 at 2” thickness maximum, and include a tack coat between each.

iii. Proper compaction by vibratory roller will be used between asphalt lifts.

iv. Proper grading of final compacted surface will allow for proper runoff of precipitation from the new bridge wearing surface.

v. Final surface shall be a minimum of 3” thick at the centerline and 2.5” thick at the curbs.

j. Install new guard posts and rails.

i. Will bolt into bridge and extend 36 feet off of each side for a total of 144 feet. Each end will have returns for a total of four returns.

k. Install new bituminous hot mix asphalt wearing surface on approach roadways.

i. The installation shall be in accordance with industry standards and to all referenced specifications in this scope/contract for road base and asphalt installations.

ii. Removal and replacement of existing failed asphalt and sub base, and replacement with new road gravel base. Properly compacted. New approaches will extend 10 feet beyond bridge, at each end, and match existing road width.

iii. Bituminous hot mix asphalt will be installed with a Superpave HMA S1base course of 3” followed by a Superpave HMA S0.5 course of 2”, include a tack coat between.

iv. Proper compaction by vibratory roller will be used between asphalt lifts.

v. Proper grading of final compacted surface will allow for proper drainage, with a 2” crown.

vi. Final surface shall be of 5.0” thick.

l. Locate missing hardware on underside of bridge, e.g., missing nuts and washers on the thru bolts at the pile caps.

i. Replace missing nuts and washers with new galvanized hardware.

m. Cleanup.

i. Clean bridge deck and work area of construction debris.

ii. Remove traffic control barriers.

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 120 dys. ANP 1 EAST BRIMFIELD LAKE PROJ

KEITH BEECHER

24 RIVERVIEW AVE

FISKDALE MA 01518-1243

978-318-8405 FOB: Destination

961310

Section H - Special Contract Requirements

SECURITY INFORMATION

SECURITY REQUIREMENTS

The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the Technical Point of Contact not later than 5 calendar days after the completion of the training.

The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the Technical Point of Contact no later than 3 business days after the initial award.

UAI 5152.231-9000

UAI 5152.231-9000 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (MAR 199)

(a) This clause does not apply to terminations. See UAI 5152.249-9000, Basis for Settlement of Proposals, and Federal Acquisition Regulation (FAR) part 49.

(b) Allowable costs for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor’s accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor’s accounting records, costs for that equipment shall be based on applicable provisions of Engineer Pamphlet (EP) 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region I. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rated for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.

(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36. Rates for equipment rented from an organization under common control, lease purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization

WAGE RATES

General Decision Number: MA180030 07/06/2018 MA30

Superseded General Decision Number: MA20170030

State: Massachusetts

Construction Type: Highway

County: Worcester County in Massachusetts.

HIGHWAY CONSTRUCTION PROJECTS

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2018. The EO minimum wage rate will be adjusted annually.

Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/05/2018 1 02/09/2018 2 04/06/2018 3 05/25/2018 4 07/06/2018

CARP0107-005 09/01/2017

Rates Fringes

CARPENTER (Includes Form Work)...$ 39.28 27.90

ELEC0103-007 03/01/2018

Rates Fringes

ELECTRICIAN......................$ 50.15 31.60

ENGI0004-030 12/01/2017

Rates Fringes

POWER EQUIPMENT OPERATOR

Group 1.....................$ 46.63 26.90+A Group 2.....................$ 46.17 26.90+A

FOOTNOTE FOR POWER EQUIPMENT OPERATORS:

A. PAID HOLIDAYS: New Year's Day, Washington's Birthday, Labor Day, Memorial Day, Independence Day, Patriot's Day, Columbus Day, Veteran's Day, Thanksgiving Day, Christmas Day

POWER EQUIPMENT OPERATORS CLASSIFICATIONS

Group 1: Backhoe/Excavator/Trackhoe; Bobcat/Skid Steer/Skid Loader; Broom/Sweeper; Gradall; Loader; Paver (Asphalt, Aggregate, and Concrete); Post Driver (Guardrail/Fences) Group 2: Bulldozer; Grader/Blade; Roller

ENGI0004-031 12/01/2017

Rates Fringes

POWER EQUIPMENT OPERATOR:

(Milling Machine)................$ 29.80 26.66+A

FOOTNOTE FOR POWER EQUIPMENT OPERATORS:

A. PAID HOLIDAYS: New Year's Day, Washington's Birthday, Labor Day, Memorial Day, Independence Day, Patriot's Day, Columbus Day, Veteran's Day, Thanksgiving Day, Christmas Day

IRON0007-028 09/16/2017

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 44.41 30.56

IRON0007-029 09/16/2017

Rates Fringes

IRONWORKER, ORNAMENTAL...........$ 44.71 30.56

* LABO0039-003 06/01/2018

Rates Fringes

LABORER

Asphalt, Includes Raker, Shoveler, Spreader and Distributor.................$ 33.50 22.92 Common or General...........$ 33.25 22.92 Guardrail Installation......$ 33.50 22.92

PAIN0035-023 01/01/2018

Rates Fringes

PAINTER (Steel)..................$ 49.66 28.90

SUMA2014-015 01/11/2017

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 56.70 21.08

IRONWORKER, REINFORCING..........$ 56.48 20.62

LABORER: Concrete Saw (Hand Held/Walk Behind)................$ 41.78 18.37

LABORER: Landscape..............$ 40.39 17.68

OPERATOR: Crane.................$ 52.14 21.08

OPERATOR: Forklift..............$ 64.67 0.00

OPERATOR: Mechanic..............$ 48.14 17.02

OPERATOR: Piledriver............$ 44.46 16.94

PAINTER: Spray (Linestriping)....$ 48.00 0.00

PILEDRIVERMAN....................$ 45.65 23.33

TRAFFIC CONTROL: Flagger.......$ 23.00 20.44

TRAFFIC CONTROL:

Laborer-Cones/ Barricades/Barrels - Setter/Mover/Sweeper.............$ 44.49 12.41

TRUCK DRIVER: Concrete Truck....$ 33.69 15.79

TRUCK DRIVER: Dump Truck........$ 30.38 7.20

TRUCK DRIVER: Flatbed Truck.....$ 48.53 0.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

Section I - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.219-6 Notice Of Total Small Business Set-Aside NOV 2011 52.219-28 Post-Award Small Business Program Rerepresentation JUL 2013 52.222-6 Construction Wage Rate Requirements MAY 2014 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records MAY 2014 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and

Related Regulations

MAY 2014

52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment

Exceeding $15,000

MAY 2014

52.222-27 Affirmative Action Compliance Requirements for Construction

APR 2015

52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts

SEP 2013

52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts

MAY 2008

52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving

AUG 2011

52.228-2 Additional Bond Security OCT 1997 52.228-11 Pledges Of Assets JAN 2012 52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014 52.232-23 Assignment Of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

APR 1984

52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.242-14 Suspension of Work APR 1984 52.243-5 Changes and Changed Conditions APR 1984 52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994 52.249-1 Termination For Convenience Of The Government (Fixed

Price) (Short Form)

APR 1984

52.249-10 Default (Fixed-Price Construction) APR 1984

252.203-7000 Requirements Relating to Compensation of Former DoD Officials

SEP 2011

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber

Incident Reporting

OCT 2016

252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or Hazardous Materials

SEP 2014

252.227-7033 Rights in Shop Drawings APR 1966 252.232-7004 DOD Progress Payment Rates OCT 2014 252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.243-7001 Pricing Of Contract Modifications DEC 1991

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 days after notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.213-4 TERMS AND CONDITIONS--SIMPLIFIED ACQUISITIONS (OTHER THAN COMMERCIAL

ITEMS) (JAN 2018).

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses that are incorporated by reference:

(1) The clauses listed below implement provisions of law or Executive order:

(i) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.

113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(ii) 52.222-3, Convict Labor (JUN 2003) (E.O. 11755).

(iii) 52.222-21, Prohibition of Segregated Facilities (APR 2015).

(iv) 52.222-26, Equal Opportunity (SEPT 2016) (E.O. 11246).

(v) 52.225-13, Restrictions on Certain Foreign Purchases (JUN 2008) (E.O.s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

(vi) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).

(vii) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub. L. 108-77, 108-78 (19 U.S.C. 3805 note).

(2) Listed below are additional clauses that apply:

(i) 52.232-1, Payments (APR 1984).

(ii) 52.232-8, Discounts for Prompt Payment (FEB 2002).

(iii) 52.232-11, Extras (APR 1984).

(iv) 52.232-25, Prompt Payment (JAN 2017).

(v) 52.232-39, Unenforceability of Unauthorized Obligations (JUN 2013).

(vi) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (DEC 2013).

(vii) 52.233-1, Disputes (MAY 2014).

(viii) 52.244-6, Subcontracts for Commercial Items (NOV 2017).

(ix) 52.222-55, Minimum Wages Under Executive Order 13658 (MAR 2016) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia)).

(b) The Contractor shall comply with the following FAR clauses, incorporated by reference, unless the circumstances do not apply:

(1) The clauses listed below implement provisions of law or Executive order:

(i) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Oct 2016) (Pub. L. 109-282) (31 U.S.C. 6101 note) (Applies to contracts valued at $30,000 or more).

(ii) 52.222-19, Child Labor--Cooperation with Authorities and Remedies (Jan 2018) (E.O. 13126). (Applies to contracts for supplies exceeding the micro-purchase threshold).

(iii) 52.222-20, Contracts for Materials, Supplies, Articles, and Equipment Exceeding $15,000 (MAY 2014) (41 U.S.C. chapter 65) (Applies to supply contracts over $15,000 in the United States, Puerto Rico, or the U.S. Virgin Islands).

(iv) 52.222-35, Equal Opportunity for Veterans (Oct 2015) (38 U.S.C. 4212) (applies to contracts of $150,000 or more).

(v) 52.222-36, Equal Employment for Workers with Disabilities (JUL 2014) (29 U.S.C. 793) (Applies to contracts over $15,000, unless the work is to be performed outside the United States by employees recruited outside the United States). (For purposes of this clause, ``United States'' includes the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island.)

(vi) 52.222-37, Employment Reports on Veterans (Feb 2016) (38 U.S.C. 4212) (Applies to contracts of $150,000 or more).

(vii) 52.222-41, Service Contract Labor Standards (MAY 2014) (41 U.S.C. chapter 67) (Applies to service contracts over $2,500 that are subject to the Service Contract Labor Standards statute and will be performed in the United States, District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S.

Virgin Islands, Johnston Island, Wake Island, or the outer Continental Shelf).

(viii)(A) 52.222-50, Combating Trafficking in Persons (MAR 2015) (22 U.S.C. chapter 78 and E.O 13627) (Applies to all solicitations and contracts).

(B) Alternate I (MAR 2015) (Applies if the Contracting Officer has filled in the following information with regard to applicable directives or notices: Document title(s), source for obtaining document(s), and contract performance location outside the United States to which the document applies).

(ix) 52.222-55, Minimum Wages Under Executive Order 13658 (DEC 2015) (Executive Order 13658) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia)).

(x) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2017) (E.O. 13706) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia.))

(xi) 52.223-5, Pollution Prevention and Right-to-Know Information (MAY 2011) (E.O. 13423) (Applies to services performed on Federal facilities).

(xii) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (June, 2016) (E.O. 13693)(applies to contracts for products as prescribed at FAR 23.804(a)(1)).

(xiii) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (June, 2016) (E.O. 13693) (Applies to maintenance, service, repair, or disposal of refrigeration equipment and air conditioners).

(xiv) 52.223-15, Energy Efficiency in Energy-Consuming Products (DEC 2007) (42 U.S.C. 8259b) (Unless exempt pursuant to 23.204, applies to contracts when energy-consuming products listed in the ENERGY STAR[supreg] Program or Federal Energy Management Program (FEMP) will be--

(A) Delivered;

(B) Acquired by the Contractor for use in performing services at a Federally-controlled facility;

(C) Furnished by the Contractor for use by the Government; or

(D) Specified in the design of a building or work, or incorporated during its construction, renovation, or maintenance).

(xv) 52.223-20, Aerosols (June, 2016) (E.O. 13693) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons as a propellant or as a solvent; or contracts for maintenance or repair of electronic or mechanical devices).

(xvi) 52.223-21, Foams (June, 2016) (E.O. 13693) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons or refrigerant blends containing hydrofluorocarbons as a foam blowing agent;

or contracts for construction of buildings or facilities.

(xvii) 52.225-1, Buy American--Supplies (MAY 2014) (41 U.S.C. chapter 67) (Applies to contracts for supplies, and to contracts for services involving the furnishing of supplies, for use in the United States or its outlying areas, if the value of the supply contract or supply portion of a service contract exceeds the micro-purchase threshold and the acquisition--

(A) Is set aside for small business concerns; or

(B) Cannot be set aside for small business concerns (see 19.502-2), and does not exceed $25,000).

(xviii) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (MAY 2014) (42 U.S.C. 1792) (Applies to contracts greater than $25,000 that provide for the provision, the service, or the sale of food in the United States).

(xix) 52.232-33, Payment by Electronic Funds Transfer--System for Award Management (JUL 2013) (Applies when the payment will be made by electronic funds transfer (EFT) and the payment office uses…