WOONSOCKET FLOOD REDUCTION

TRUNNION BEARING ACCESS SYSTEM

U.S. ARMY CORPS OF ENGINEERS

WOONSOCKET FALLS DAM

WOONSOCKET, RI

SCOPE OF WORK

October 2017

I. GENERAL

1. Scope Furnish all equipment, materials and labor for Trunnion Bearing Access System at Woonsocket Falls Dam in Woonsocket, RI, for the purpose of facility maintenance.

2. Location The required services shall be performed at the following project site location, Woonsocket Falls Dam, 121 South Main Street, Woonsocket, RI.

3. Site Visits and Requests for Information Contact the Technical Point of Contact, Joe Zanca 978-318-8419 or joseph.l.zanca@usace.army.mil to arrange a site visit.

4. Schedule The period of performance shall be 120 days from contract award. The project area will be open to the contractor Monday through Friday 7:00 AM to 3:30 PM and all work must be done during those hours unless additional hours are approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays.

5. Safety The contractor will comply with all pertinent provisions of the latest edition of the U.S. Army Corps of Engineers Safety and Health Requirements COE EM 385-1-1. A copy of COE EM 385-1-1 is available for reference at the project office or the manual may be viewed at the following link http://www.usace.army.mil/SafetyandOccupationalHealth/EM38511,2008BeingRevised.asp x The contractor shall also comply with all OSHA work safety standards. The project staff can and will order the cessation of work at any time should the safety of employees and visitors become jeopardized.

mailto:joseph.l.zanca@usace.army.mil http://www.usace.army.mil/SafetyandOccupationalHealth/EM38511,2008BeingRevised.aspx http://www.usace.army.mil/SafetyandOccupationalHealth/EM38511,2008BeingRevised.aspx

6. Preconstruction Conference

Prior to the start of any work, the Technical Point of Contact will schedule and conduct a “Preconstruction Conference”. The Contractor’s Project Manager and Quality Control Personnel will attend this meeting. This conference will be held at the time and location agreeable to the government and contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Preconstruction conference the contractor shall provide to the name of the project superintendent with a telephone number for project coordination.

The following is a general list of items for discussion during this Preconstruction Conference:

• Authority of the Technical Point of Contact.

• Contractor’s Safety Program (including sub-contractors).

• Accident Prevention Plan and Activity Hazard Analysis (Submitted & accepted prior to start of work on site)

• Weekly Safety Meetings (Documented on NED Form 251)

• Accident Reporting (ENG Form 3394)

• Safety Data Sheet (SDS) requirements

• Correspondence, Communication and Administrative Procedures.

• Invoice and payment.

7. Permits

The contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

8. Security The contractor will comply with all established security policies at Woonsocket Flood Reduction Project. Due to periods of heightened security that may affect the access to the areas covered under this contract, areas may be subject to periodic closures, which in turn may reduce or inhibit the contractor’s ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent service in an area. The contractor shall be given at least 24 hour notice of any such closure.

9. Payment

Payment shall be made on a per job basis. After final inspection and acceptance by the Government, the contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. For jobs greater than 30 days the contractor may request progress payment.

This invoice may be mailed to:

US Army Corps of Engineers 518 East Hartford Ave., Uxbridge, MA 01569-1209 or emailed to joseph.l.zanca@usace.army.mil or faxed to the office at (508) 278-4234.

10. Damage to Government and Private Property The contractor shall be responsible for restoring any Government facilities or structures damaged as a result of the firm’s operation. The contractor shall also be responsible for any damage to private property or injury to any person as a result of the firm’s operations. The contractor shall notify the Technical Point of Contact immediately of damage to Government and private property and injury to any person resulting from the firms’ operation.

11. Point of Contact Requirements The contractor shall provide to the Technical Point of Contact a telephone number and a point of contact for discussion of any contractual matters.

II. TECHNICAL

Part 1 General:

Existing Conditions:

Woonsocket Falls Dam was completed in 1959. Eight Trunnion Bearings assist four Tainter gates used to operate for flood reduction management. Due to the location of the Trunnion Bearings, routine inspection and maintenance cannot be performed without special fall protection planning and equipment. Installation of five access systems to trunnion bearings and one ladder to reach the river channel below the Dam will allow for routine inspections and maintenance to occur without increased risk to personnel.

Elevations are as follows:

-Service Bridge Deck Elevation=170.00ft.

-Pier/Abutment Concrete Elevation= 145.00ft -River Channel Bottom=130.00ft.

Note: contractor is responsible for final measurements.

Requests for Information:

Requests concerning the work of this project should be directed to the Technical Point of Contact at (978) 318-8419 or joseph.l.zanca@usace.army.mil

Submittals:

Although the Government technically reviews submissions required by this scope of work, it is emphasized that the Contractor’s work must be prosecuted using proper internal controls and review procedures. The documents identified below must be prepared in accordance with the applicable standards, submitted to the Technical Point of Contact for review and accepted by the government prior to the commencement of any field activities.

• Product specification sheets for ladders, platforms, railings, anchors and associated materials/hardware.

• Installation plan.

• Provide fabricator certification for ladder assembly stating that the ladder and associated components have been fabricated according to the requirements of 29 CFR 1910.27.

• Certificates of qualified welders in accordance with AWS D1.1/D1.1M. Use procedures, materials, and equipment of the type required for the work.

• Manufacturer Warranty for all equipment and hardware

• Accident Prevention Plan (APP) and Activity Hazard Analysis (AHA) (Prior to start of field work)

Clean Up:

The contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials.

Upon completing work in an area the contractor shall remove any tools, equipment, and materials that are not the property of the government. Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government.

Government Resources:

The contractor is responsible for providing all materials to complete the project. Unless specified in the contract, the Government will not provide any equipment, telephone services or other resources.

Omissions:

This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

Quality Assurance:

The contractor is responsible for the quality control of the contract work. The government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.

Other Contracts:

The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor, or by Government employees.

Environmental Protection:

Containers for excess and/ or waste materials, rubbish, etc. shall be provided by the contractor at the site, and the site will be inspected/ cleaned on a daily basis. No burning is permissible.

Water, air and land resources shall not be adversely impacted during the course of the work.

Contractor will take necessary steps to ensure all federal, state, and local environmental regulatory requirements are met.

Receiving and Storing Materials:

The contractor is responsible for protecting any stored material until it is placed in service. The contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive material or supplies for the contractor and will not be responsible for damage to contractor equipment or material.

Part 2 Schedule:

1. Pier No. 1 (Access entrance from land surface): Safety railing on top of pier.

2. Pier No. 2 (Access entrance from Service Bridge): Ladder, fall protection rail system, platforms, safety railing on top of pier. Access entrance from Service Bridge. Ladder from top of pier to river channel, to be installed out of river flow.

3. Pier No. 3 (Access entrance from Service Bridge): Ladder, fall protection rail system, platforms, safety railing on top of pier.

4. Pier No. 4 (Access entrance from Service Bridge): Ladder, fall protection rail system, platforms, safety railing on top of pier.

5. East Abutment (Access entrance from walkway): New fence with gate (replace existing).

Ladder down to pier, safety railing on top of pier.

Part 3 Products:

Trunnion Bearing Access system will meet or exceed specifications as listed specifications and the following:

1. Pier/Abutment Post, Railing and kickplates (Five units): Provide stainless steel handrails, including inserts or fittings, in concrete, steel pipe conforming to ASTM A53/A53M standards. Provide 316 stainless steel railings and fittings of 2-inches nominal size, schedule 40, conforming to ASTM standards.

a. Exterior railings, including pipe, fittings, brackets, fasteners, and other metal components shall be 316 stainless steel.

b. Provide 316 stainless steel kickplates between railing posts where indicated, and consist 1/8-inch steel flat bars 6-inches high.

2. Fixed Ladders, Platforms and Supports (Three units):

a. Shall be 316 stainless steel conforming to ASTM standards.

b. Provide fabricator certification for ladder assembly stating that the ladder and associated components have been fabricated according to the requirements of 29

CFR 1910.27.

c. Platforms will have two safety chains per access opening.

3. Fixed Ladder, Platform, support and hardware for section descending to river channel (One unit):

a. Shall be 316 stainless steel.

b. Provide fabricator certification for ladder assembly stating that the ladder and associated components have been fabricated according to the requirements of 29

CFR 1910.27.

4. Fence with gate (One unit):

a. Existing thirty (30) feet of aluminum fence will be replaced, on east abutment, with 2 in chain link fence, height matched to fence adjoining the Dam, with a pedestrian gate with heavy duty locking mechanism. Fence will be vinyl coated black in color with three inch posts. System will meet or exceed US Army Corps of Engineers, Omaha District, FE5 chain link fence specifications.

5. Safety Chains for Platform/Ladder Openings (Multiple units):

a. Shall be 316 stainless steel, straight link type, 3/16-inch diameter, with at least twelve links per foot, and with snap hooks on each end.

b. Provide 3/16” stainless steel snap hooks of boat type.

c. Provide 316 stainless steel 3/8-inch bolt with 3/4-inch eye diameter for attachment of chain, anchored as indicated.

d. Mount the top chain 6 inches above the deck/platform and mount the lower chain

2 feet above the deck/platform.

6. Concrete Anchors (Multiple units):

a. Shall be 316 stainless steel conforming to ASTM standards.

b. Shall be sized accordingly for installation.

7. Fall protection ladder system (Four units):

a. Shall provide continuous fall protection for climbing fixed ladders.

b. Shall be installed on all ladders in this contract.

c. Shall provide 100% tie-off during transition.

d. Shall be constructed of stainless steel.

e. Shall be a rail type system that meets or exceeds the Sperian Miller GlideLoc vertical height access ladder system.

f. Shall include four (4) fall arrester units for use with rail system.

g. System, arrester and harness shall meet or exceed ANSI Z359 Standards.

Part 4 Execution:

General:

A. Trunnion Bearing Access system:

Trunnion Bearing Access system installation shall reduce safety hazards to employees and contractors on-site.

1. Work area will be restricted to contractors and USACE Employees.

2. Remove eight existing stainless steel trunnion bearing lubrication lines from east abutment and four piers.

3. Install five Trunnion Access Systems, according to Part 2 Schedule, at each of the four piers and one on the East Dam abutment.

4. Install safety railings on pier number one with safety chain closure on entrance access.

5. Three systems, on piers number two, three and four, will begin from the Service Bridge deck of Woonsocket Falls Dam. A portion of the Service Bridge deck railing will be cut, removed and made safe for access. Chains will be installed to prevent fall hazards when not in use.

6. East abutment fence will be removed and replaced with new fence and gate. Ladder and railings will be installed on abutment.

7. Provide break in the rail, with two safety chains to open access on land side of Pier No.

one and same for Pier No. two for ladder to access to bottom of river channel.

8. Service Bridge thermal expansion shall be built into the system and anticipated with the access anchoring system.

9. System shall not impede the operation of full opening of the tainter gates.

10. Platforms with railings and kickplates may be installed as needed, at the Service Bridge deck level or at the pier surfaces for access to new ladders.

11. Ladders will extend from the new platforms to the Piers and Dam Abutments concrete surface.

12. Railings with kickplates will be installed on the concrete platform along the outer edge of all four piers and east abutment.

13. Pier No. 2 will also include access thru the railing for an additional platform with ladder on the pier nose descending to the downstream river channel.

14. Clean up site.

Informational Photo No. 1: Woonsocket Falls Dam, showing the Tainter Gates fully open. Piers one thru four are left to center and the East Abutment is furthest right from view at wall.

Information Photo No. 2: Woonsocket Falls Dam with Tainter Gates Closed. Pier number two will have a platform and ladder installed on the downstream nose of pier.

Informational Photo No. 3: Woonsocket Falls Dam service bridge deck with railing.

Informational Photo No. 4: View of Pier, grease lines to be removed and trunnion bearings from top of deck.

Informational Photo No. 5: East Abutment where fence will be replaced.

Informational Sketch No. 1: Downstream plan of Woonsocket Falls Dam.

Informational Sketch No. 2: Cross section of typical Pier.

Bid Schedule

TASK/ITEM

NUMBER UNIT QUANTITY UNIT PRICE

EACH TOTAL

WFD Trunnion Bearing Access System

JOB 1 $ $

TOTAL $